'I'm pretty angry right now': LRT likely won't be ready until 2019
Jon Willing, Ottawa Citizen
Updated: September 10, 2018
The Confederation Line LRT likely won’t be ready for customers by the end of 2018, councillors learned Monday.
Transportation general manager John Manconi told the finance and economic development committee that he received a call from RTG on the way home from work on Friday around 6 p.m. suggesting a new schedule of completion.
RTG was supposed to deliver the $2.1-billion LRT system on Nov. 2. The company has now suggested it can deliver it on Nov. 30. Based on the testing that would need to happen, the city doesn’t think the LRT system would open until the first quarter of 2019.
RTG wanted to “carve” out part of the delivery agreement that promised a Nov. 2 handover — which would have meant the partial opening of some stations and a reduced fleet size — but Manconi says the city won’t buckle on the transit system it’s paying for. That means having 34 vehicles and seeing all stations open.
Rideau Station is the one major area of construction that continues to be behind. City staff started raising warning flags about the timelines in August.
“We called them out. We did our due diligence,” Manconi said.
A $1-million penalty is now in play.
Councillors said they were upset during the Monday briefing.
“I’m pretty angry right now,” Coun. Stephen Blais said.
More to come.