Vaughn Palmer: SkyTrain construction soars to $500M per Km, but why is 'confidential?'
The NDP commissioned the detailed budget for the project, vetted the numbers, and know what each component is expected to cost. They just aren’t telling the taxpaying public anything about it.
VAUGHN PALMER Updated: September 6, 2018
VICTORIA — At first glance the report on the Broadway SkyTrain extension posted on the transportation ministry website holds out the hope of shedding light on how construction costs have soared to half a billion dollars per kilometre.
“Cost report,” it says, followed by a comprehensive statement of purpose: “This document details the preliminary cost estimate of the reference concept design for the Millennium Line Broadway extension project.”
But the first indication that the contents offered less than full disclosure came when I clinked on the link and learned that the copy released for public consumption had been “redacted” and, yes, “sanitized.”
I’ll say it was.
Doubtless the unsanitized and unredacted version of the 13-page report from March of this year contained a full breakdown of the cost of extending the existing SkyTrain line from the Clark Drive campus of Vancouver Community College westward along Broadway to Arbutus.
“The estimate assumes that all the work is carried out as one single project and covers costs including project management, preliminary design and technical investigations, engagement and consultation, procurement, design, construction, risk, contingencies and interest during construction,” according to the text.
The methodology was thorough. The costs include money spent to date on planning the project, through the 18 months or so it will take to put the expansion out to tender and award the contract, and then the years of construction up to a targeted in-service date of 2025.
Finally the report from the provincial Partnerships B.C. agency insists that all the numbers have been checked and double checked: “A due diligence review of the capital cost estimate was conducted, which confirmed that the budget currently carried is reasonable to design, construct and commissioning of the approximately 5.7 (kilometre) extension to the existing Millennium Line SkyTrain network.”
In short, the New Democrats commissioned the detailed budget for the project, vetted the numbers, and know what each component is expected to cost. They just aren’t telling the taxpaying public anything about it.
For when you get the dollar breakdowns on Page 9 of the report, every last detail is blanked out in the name of confidentiality and protecting the public interest.
For instance, five of the 5.7 kilometres will consist of twin, bored tunnels, hence the name Broadway Subway. The estimated cost of doing this is withheld.
...
https://vancouversun.com/opinion/columni...rs-to-500m-per-k-but-why-is-confidential