Good Day.
Thx, waterloowarrior, but as I cannot use Scribd (for my own reasons),
here is a brief summary of the O-Train Confederation Line Quarterly Update (Q2 - 2018) of 13 August 2018.
** Stage 1 LRT Project Update.
Construction: Stations
<overall, the same motherhood and all-is-well statements per station as in the Q1 update>
<the updates from the RTG website are essentially repeated, as before>
Guideway
<basically complete, with isolation testing, restraining rail installation, ballast profiling>
MUPs, Cycle Lanes and Roadway RE-instatements
Work has begin on Booth Street Bridge cycling improvements.
MUP paving and lighting installations from Hurdman to uOttawa is underway.
Waller St. south of Laurier is scheduled for Q3.
Systems, Vehicle, Testing, Commissioning
OCS rigid rail hangers have been installed on eastbound tunnel track (westbound was noted in Q1 update).
TPSS 3 has been installed at Rideau station (per Q1 update) and awaits Hydro connection.
Train Control System integration testing continues east of uOttawa, and has begun between Tunney's and Pimisi.
P25 radio systems continue installation.
<other items are as per the Q1 update>
Preparation for Operations
<as per Q1 update>
November 2 RSA
RTG is Committed and Confident
Key Activities to monitor:
Rideau station , Vehicle testing in tunnel , End-to-End tests from Blair to Tunney's ,
Multiple train operations in full CBTC mode along the eastern alignment, Pre-Trial running and Trial running.
Critical is the Trail Running period wherein RTG demonstrates full capability including capacity, headways, etc.
Budget June 30, 2018
Project Description ...... Authority ...... Actual Expend .... Obligations/Draws .... Balance
Confederation Line ..... 130,000,000 ... 1,544,716,608 ....... 575,462,518 ...... 9,820,874
C-Line Contingency .... 100,000,000 ........ 41,217,315 ........ 55,673,800 ...... 3,108,885
LRT 417 Widening ....... 224,500,000 .......223,880,602 ............. 238,391 ........ 381,007
<notations as per Q1 description>
Negotiations with RTG on Delay
Using the Project agreement as the basis for negotiations the City and RTG are
working through delays, disputes and recovery of incremental costs.
Funding Partner Events
<fluff>
Ready for Rail
In July, video footage was captured At Blair and Cyrville for the next phase, featuring transit customers
using the bus and LRT system to increase customer familiarity with the line before revenue service launch.
Public Safety Message Regarding OCS
<as per Q1 update>
Stakeholder Relations and Communications
<as per Q1 update, and fluff>
** Stage 2 LRT Project Update
Transfer Agreements with the NCC
..... completed this past June as the City executed the Trillium and Confederation Line Transfer Agreements with the NCC.
..... establish terms for the transfer to the City of property interests and licenses wrt NCC property and required for
constructing, operating and maintaining the Stage 2 project. It also includes detailed provisions regarding the
construction of infrastructure on NCC lands, including parkland improvement works, the payment of parkland improvement
funs by the City to the NCC and the completion of legacy obligations such as the removal of infrastructure forming part
of the City's BRT system.
Procurement Update
The final version of the Project Agreement and Project Specific Output Specifications are complete, a result of a
collaborative effort between the O-Train Planning Office, Owner's Engineer Team, City departments, and critical
stakeholders such as NCC, MTO, OMCIAA.
For both the Trillium and Confederation line procurement, final submissions are anticipated from proponents this fall.
One the final submissions are received, an evaluation team will reviewthe bids for compliance, and then score the bids
to decide a preferred proponentfor both lines. A report to Council is scheduled for December,
which will recommend the preferred proponent.
Environmental Update
The City has approved EAs for both projects. As there have been additions and changes since their 2016 EAs,
amendments have been required.
The Maitland Bridge Municipal Class EA is now complete. The project includes bridge widening to accommodate cycle tracks
and wider sidewalks, modifications to the south and north ramps, and provision of transitions.
The Federal Envirnmental Effects Evaluation for the Trillium and Confederation Lines are nearing completion.
Byron Corridor Tree Relocation Project and Tree Canada Grant
.... Trees were moved to several locations, including Redwood, Sherbourne, Westwood, Woodroffe, New Orchard, McEwan parks,
along the SJAM Parkway, and on a small number of private lots,
working with ward councillors to area residents who could accommodate them.
To help, the City received a $25K grant from Tree Canada, part of the CN EcoConnexions,
one of 27 communities to receive a grant from 140 applications.
This constitutes a brief summary of the O-Train Confederation Line Quarterly Update (Q2 - 2018) of 13 August 2018.
If there are questions......do ask , no problem! :-)
EnJoy!