Quote:
Originally Posted by J.OT13
From Confederation Line website.
I get why Rideau and maybe Parliament are a little behind with the sinkholes, the flooding and the stop work orders, but what's the excuse for the above ground stations.
Even the trains. Technically, they're late. Not Bombardier late, but late. They should have been complete and all assembled months before the original May deadline for full system hand over.
Here's another from Twitter.
https://twitter.com/rail613/status/1014953962867437568
|
Good Day.
Yeah, I had come to thinking the same thing..... and the only think I can imagine is RTG saving some amount of cash flow by not having as many sub-contractor crews all working at all stations all at the same time, and using the delay of the 2 stations noted to draw out the completion of all the rest. Less overtime, fewer crews, less cost.
And as for the LRVs, 2 ideas - that the same concept is at play, inasfar as they no longer need to overtime the assemblies to get them finished for delivery, or, that they never intended to finish them all by the May 7/24 deadline because not all would be required Day One.
Your last pic is of the plot of land across the street from Bayview station, beside City Center, and it has no connection to the C-Line construction nor to the T-Line temp location. It is the new Trinity triple tower site prep, wherein they got permission (and site contamination cleanup funding assistance) to relocate and rebuild the storm and sanitary sewer intersections in that field, to make way for development and construction of the 30 oops 45 oops 53 oops 65 story towers.
But depending on negotiations and permissions and back-room machinations, they MIGHT be 'allowed' to build a ped or MUP overpass to connect to either/or/both the T-Line / C-Line, or a tower over the T-Line, or......