  #3021  
Old Posted Jan 28, 2018, 10:19 PM
Spork's Avatar
Spork Spork is offline
Shoebox Dweller
 
Join Date: Sep 2008
Location: Vancouver
Posts: 1,784
Quote:
Originally Posted by Express691 View Post
Also noticed today that trains are entering platform 3 at walking speed.
I noticed that yesterday too. I wonder if this is temporary (e.g. just yesterday due to some maintenance issue, or temporary while construction wraps up), or permanent (e.g. two platforms = somehow higher risk for people to fall on tracks).
Reply With Quote
     
     
  #3022  
Old Posted Jan 28, 2018, 10:36 PM
cganuelas1995 cganuelas1995 is offline
Registered User
 
Join Date: Jan 2017
Posts: 1,681
Quote:
Originally Posted by Spork View Post
I noticed that yesterday too. I wonder if this is temporary (e.g. just yesterday due to some maintenance issue, or temporary while construction wraps up), or permanent (e.g. two platforms = somehow higher risk for people to fall on tracks).
Isn't one platform gonna be an exit only?
Reply With Quote
     
     
  #3023  
Old Posted Jan 28, 2018, 10:37 PM
dpogue dpogue is online now
Registered User
 
Join Date: Aug 2013
Posts: 770
Quote:
Originally Posted by Spork View Post
I noticed that yesterday too. I wonder if this is temporary (e.g. just yesterday due to some maintenance issue, or temporary while construction wraps up), or permanent (e.g. two platforms = somehow higher risk for people to fall on tracks).
I think I heard on Friday morning that one of the LIM rail plates at Broadway inbound was sticking up a bit and posed a risk of hitting the bottom of the train as it went through. A "go slow" results in the train motors generating less magnetic force, which is less likely to incur damage.

It should be fixed soon, and I'm a bit surprised it wasn't fixed Friday evening. On the other hand, now is the perfect time to try to film the current state of construction from the front of the train
Reply With Quote
     
     
  #3024  
Old Posted Jan 29, 2018, 3:13 AM
Express691 Express691 is offline
Registered User
 
Join Date: Aug 2015
Posts: 650
Quote:
Originally Posted by dpogue View Post
I think I heard on Friday morning that one of the LIM rail plates at Broadway inbound was sticking up a bit and posed a risk of hitting the bottom of the train as it went through. A "go slow" results in the train motors generating less magnetic force, which is less likely to incur damage.

It should be fixed soon, and I'm a bit surprised it wasn't fixed Friday evening. On the other hand, now is the perfect time to try to film the current state of construction from the front of the train
Seems to be fixed as of today, the Mk1 I was on entered the platform at normal speed.
Reply With Quote
     
     
  #3025  
Old Posted Jan 29, 2018, 6:30 AM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
What is the latest news on the Mark I retirement plan and have all 114 original Mark I's gotten Translink ivory 2.0?And when will the third order of 28 Mark III trains begin to arrive and enter service? Also when will the second order enter service if they arrive at the end of this year?
Reply With Quote
     
     
  #3026  
Old Posted Feb 16, 2018, 12:57 AM
Sheba Sheba is offline
Registered User
 
Join Date: Jan 2015
Location: BC
Posts: 4,597
I received an 'occupant' letter in the mail from TransLink - they're going to start repainting Edmonds Station.
Reply With Quote
     
     
  #3027  
Old Posted Feb 16, 2018, 9:39 PM
Urbanmetro Urbanmetro is offline
Registered User
 
Join Date: Apr 2016
Posts: 219
Surrey Central SkyTrain station North entrance is moving along. Substructure complete, elevator shaft complete. I see the project finishing late fall 2018 ������ I just don't see how it is costing 30 mil. The whole station should be upgraded for that amount...
Reply With Quote
     
     
  #3028  
Old Posted Feb 16, 2018, 9:44 PM
Urbanmetro Urbanmetro is offline
Registered User
 
Join Date: Apr 2016
Posts: 219
Oh and Metrotown upgrade is double in scope and cost less than 10 million more. Is TransLink in the real estate bubble too?!
Reply With Quote
     
     
  #3029  
Old Posted Feb 16, 2018, 10:55 PM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
How is the East station house coming along at Metrotown? Anyone have photos from this week of it?

Also how is Broadway coming along? photos?
Reply With Quote
     
     
  #3030  
Old Posted Feb 17, 2018, 12:50 AM
Sheba Sheba is offline
Registered User
 
Join Date: Jan 2015
Location: BC
Posts: 4,597
Quote:
Originally Posted by Mac Write View Post
How is the East station house coming along at Metrotown? Anyone have photos from this week of it?
No photos. I seem to remember seeing the escalators are physically in place. TransLink said at their open meeting that Metrotown Station would be completed second quarter this year (so between April - June) which seems pretty plausible.
Reply With Quote
     
     
  #3031  
Old Posted Feb 17, 2018, 3:43 AM
Waders Waders is offline
Registered User
 
Join Date: May 2009
Posts: 1,361
Quote:
Originally Posted by Sheba View Post
No photos. I seem to remember seeing the escalators are physically in place. TransLink said at their open meeting that Metrotown Station would be completed second quarter this year (so between April - June) which seems pretty plausible.
A lot of work is being done to the sidewalk outside the station.
Spring 2018 is the target completion date. So probably the east stationhouse can be opened between March and May.

Quote:
We’re getting close to the finish line on Metrotown upgrades! The station upgrades are on target to be complete in spring 2018.
Source
Reply With Quote
     
     
  #3032  
Old Posted Feb 17, 2018, 5:11 AM
Shift Shift is offline
Registered User
 
Join Date: Sep 2014
Location: Surrey
Posts: 1,944
Quote:
Originally Posted by Urbanmetro View Post
Surrey Central SkyTrain station North entrance is moving along. Substructure complete, elevator shaft complete. I see the project finishing late fall 2018 ������ I just don't see how it is costing 30 mil. The whole station should be upgraded for that amount...
Is the platform not getting any upgrades? - replacement of the metal grate walls with glass and upgraded platform lighting (to match the new station house)
Reply With Quote
     
     
  #3033  
Old Posted Feb 17, 2018, 6:32 AM
Urbanmetro Urbanmetro is offline
Registered User
 
Join Date: Apr 2016
Posts: 219
Quote:
Originally Posted by Shift View Post
Is the platform not getting any upgrades? - replacement of the metal grate walls with glass and upgraded platform lighting (to match the new station house)
You can see the reports on the city of surrey planning reports and news outlets. All the station is getting is one new elevator, three new escalators, a new staircase and better lighting to go with the new north entrance... Poor use of money in my opinion. They should do it right and do it now...
Reply With Quote
     
     
  #3034  
Old Posted Feb 17, 2018, 7:16 AM
Colin4567 Colin4567 is offline
Registered User
 
Join Date: Oct 2017
Location: Lower Mainland-ish
Posts: 234
Quote:
Originally Posted by Urbanmetro View Post
You can see the reports on the city of surrey planning reports and news outlets. All the station is getting is one new elevator, three new escalators, a new staircase and better lighting to go with the new north entrance... Poor use of money in my opinion. They should do it right and do it now...
If they had a good-looking station they'd weaken the appeal of the LRT's glass panels and lighting.
Reply With Quote
     
     
  #3035  
Old Posted Feb 17, 2018, 7:36 AM
Urbanmetro Urbanmetro is offline
Registered User
 
Join Date: Apr 2016
Posts: 219
Quote:
Originally Posted by Colin4567 View Post
If they had a good-looking station they'd weaken the appeal of the LRT's glass panels and lighting.
Hahahaaaaa. Funny!!!
Reply With Quote
     
     
  #3036  
Old Posted Feb 17, 2018, 3:04 PM
Reecemartin's Avatar
Reecemartin Reecemartin is offline
YouTube Creator
 
Join Date: Sep 2015
Location: Vancouver/Toronto
Posts: 1,776
[Deleted]

Last edited by Reecemartin; Nov 17, 2020 at 8:34 PM.
Reply With Quote
     
     
  #3037  
Old Posted Feb 22, 2018, 10:15 AM
mcminsen's Avatar
mcminsen mcminsen is online now
Registered User
 
Join Date: Sep 2007
Location: Downtown Vancouver
Posts: 9,980
Commercial - Broadway.



Feb.21 '18, my pics



Reply With Quote
     
     
  #3038  
Old Posted Feb 22, 2018, 3:52 PM
Reecemartin's Avatar
Reecemartin Reecemartin is offline
YouTube Creator
 
Join Date: Sep 2015
Location: Vancouver/Toronto
Posts: 1,776
[Deleted]

Last edited by Reecemartin; Nov 17, 2020 at 8:34 PM.
Reply With Quote
     
     
  #3039  
Old Posted Feb 22, 2018, 5:47 PM
Shift Shift is offline
Registered User
 
Join Date: Sep 2014
Location: Surrey
Posts: 1,944
Quote:
Originally Posted by Reecemartin View Post
Well Surrey Central is a pretty ugly station.
I think it's by far one of the nicer stations on the expo line - aside from those upgraded. It's quite grande (as far as skytrain stations go).
  • Nice glass elevator and escalators/staircases - integrated well with the streetscape.
  • Nice integration of retail units at the base along the street
  • High vaulted ceilings on platform level
  • Coffered ceilings above the sidewalk on City Parkway (nice design feature)
  • I also like the roof design.



Reply With Quote
     
     
  #3040  
Old Posted Feb 23, 2018, 1:38 AM
MIPS's Avatar
MIPS MIPS is online now
SkyTrain Nut
 
Join Date: Mar 2013
Location: Kamloops
Posts: 2,123
I always found the Surrey stations embraced 90's design as opposed to the rest of the Expo Line which was all about that early-80's Space Frame.

For some reason I think of 90's malls.


Image courtesy of the CBC
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 4:24 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.