  #5981  
Old Posted Feb 6, 2018, 3:20 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
It is what it is. Its only 5 months, we'll live. Still think they should be aiming for a multi-stage opening. If the whole line can open late November I see no reason why Blair-oTtawa couldn't open over the summer. Hopefully someone asks that question.
     
     
  #5982  
Old Posted Feb 6, 2018, 3:31 PM
daud's Avatar
daud daud is offline
Registered User
 
Join Date: Jun 2012
Location: Ottawa
Posts: 763
Quote:
Originally Posted by OtrainUser View Post
http://www.cbc.ca/news/canada/ottawa/ottawa-lrt-date-announced-today-1.4520183

Now im furious, looks like what I overheard from the busdriver was correct. Like give me a break a Nov 2 handover virtually gaurantees a December start which gives us no time to adjust while Stage 2 construction is supposed to start in Q1 of 2019.

Is there anyone else just as pissed as I am?
Its disappointing for sure, not totally unexpected, but unfortunate. The sinkhole really threw everything into disarray though I think they would have been late without it too.

I would not be surprised if they miss the November 2 date or they barely make it and actual service is pushed to December. Really would not surprise me one bit.
     
     
  #5983  
Old Posted Feb 6, 2018, 3:32 PM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
Quote:
Originally Posted by 1overcosc View Post
I see no reason .
really? no reason at all? I can imagine all sorts of potential ownership and liability questions that lawyers would recommend avoiding with extreme prejudice.
     
     
  #5984  
Old Posted Feb 6, 2018, 3:37 PM
ars ars is offline
Registered User
 
Join Date: Feb 2013
Location: Ottawa
Posts: 473
Does anyone know the justification for giving RTG an extension? Was the extension given due to the sinkholes?
     
     
  #5985  
Old Posted Feb 6, 2018, 3:54 PM
acottawa acottawa is online now
Registered User
 
Join Date: Aug 2009
Posts: 18,928
So there were no penalties for being late?
     
     
  #5986  
Old Posted Feb 6, 2018, 4:13 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by acottawa View Post
So there were no penalties for being late?
They won't have to pay the $1 million penalty for missing the May 24 deadline, but there will be financial consequences. From Twitter:

Quote:
Joanne Chianello
@jchianello
Manconi says city will not be paying the "milestone" bonuses (obviously) -- which is basically a fine for being late -- and city will not hand over $4 -million monthly payments to RTG until it's handed over. So financial consequences to RTG for being late. #ottnews
10:05 AM - 6 Feb 2018
     
     
  #5987  
Old Posted Feb 6, 2018, 4:23 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,701
The sinkhole does not explain why the non-tunnel stations are also late. It's funny how the Spring 2017 newsletter is still a sticky on the website. Looking at the photos in it, which are almost a year old, progress on the eastern stations seem very slow.
     
     
  #5988  
Old Posted Feb 6, 2018, 4:34 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,131
Quote:
Originally Posted by roger1818 View Post
I think you hit the nail on the head. I am curious what other material J.OT13 would rather see used. Powder coated steel (either carbon or stainless)? Painted wood? Anodized aluminum? Carbon fibre? Other? Of those the only other reasonable option would be powder coated steel but it isn't as durable as stainless steel.
Not necessarily pointing to better materials, just an observation; stainless-steel is commonly used for subway entrances while retail and offices use regular steel or painted steel.
     
     
  #5989  
Old Posted Feb 6, 2018, 4:34 PM
acottawa acottawa is online now
Registered User
 
Join Date: Aug 2009
Posts: 18,928
That's pretty small financial consequence for a multi-billion dollar project. It certainly doesn't provide much incentive for the consortium to take steps to finish by the deadline (including working on weekends and holidays).
     
     
  #5990  
Old Posted Feb 6, 2018, 4:56 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by J.OT13 View Post
Not necessarily pointing to better materials, just an observation; stainless-steel is commonly used for subway entrances while retail and offices use regular steel or painted steel.
I suspect the retail and offices you are referring to use powder coated steel (not painted). Powder coating is much more durable than paint (though not as durable as bare stainless steel). Those that do probably don't mind spending more in the long run to portray a certain image, which would probably change before the powder coating starts looking bad.
     
     
  #5991  
Old Posted Feb 6, 2018, 5:54 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,698
City to open LRT by the end of November

Jon Willing, Ottawa Citizen
Published on: February 6, 2018 | Last Updated: February 6, 2018 10:48 AM EST


The $2.1-billion first phase of the Confederation Line LRT will open to customers by the end of November, Mayor Jim Watson said Tuesday.

Watson provided the date during a finance and economic development committee meeting. City management will provide more details.

The city was scheduled to take possession of its 12.5-kilometre LRT system on May 24, but over the past three months it became increasingly clear to city management that the handoff would be delayed.

Construction started in spring 2013.

The first phase of the electrified rail system will have 13 stations between Tunney’s Pasture and Blair stations. Trains will travel through the downtown via a 2.5-kilometre tunnel between roughly Bronson Avenue and the University of Ottawa.

The city will get the keys to the LRT system on Nov. 2. It doesn’t have a launch date, only “by the end of November.”

So, by Nov. 30, people will be tapping their Presto cards and hopping on the train, if all the testing and safety compliance is perfect.

If the Rideau Transit Group doesn’t deliver the LRT system by Nov. 2, the city can charge a $1-million penalty.

The penalty, however, doesn’t apply to the May 24 missed hand-over deadline.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news/city-to-open-lrt-by-the-end-of-november
     
     
  #5992  
Old Posted Feb 6, 2018, 6:20 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by acottawa View Post
That's pretty small financial consequence for a multi-billion dollar project. It certainly doesn't provide much incentive for the consortium to take steps to finish by the deadline (including working on weekends and holidays).
One reason for the city to not apply the full weight of the penalty now is if they do, there is less incentive for the RTG to finish by the new Nov. 2 date. They city will also need to keep working with them for the next 30 years. Showing some leniency now may help maintain a better relationship in the long run.
     
     
  #5993  
Old Posted Feb 6, 2018, 6:34 PM
acottawa acottawa is online now
Registered User
 
Join Date: Aug 2009
Posts: 18,928
Quote:
Originally Posted by roger1818 View Post
One reason for the city to not apply the full weight of the penalty now is if they do, there is less incentive for the RTG to finish by the new Nov. 2 date. They city will also need to keep working with them for the next 30 years. Showing some leniency now may help maintain a better relationship in the long run.
Which is why there should be a daily penalty for such projects.
     
     
  #5994  
Old Posted Feb 6, 2018, 7:06 PM
HighwayStar's Avatar
HighwayStar HighwayStar is online now
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Quote:
Originally Posted by roger1818 View Post
One reason for the city to not apply the full weight of the penalty now is if they do, there is less incentive for the RTG to finish by the new Nov. 2 date. They city will also need to keep working with them for the next 30 years. Showing some leniency now may help maintain a better relationship in the long run.
Sure.... now that they've learned that penalties are meaningless threats... they'll have *real* incentive to honour all the rest of their contractual commitments.
     
     
  #5995  
Old Posted Feb 6, 2018, 7:08 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by acottawa View Post
Which is why there should be a daily penalty for such projects.
I don't know about daily, but certainly some sort of time based penalty for being late.
     
     
  #5996  
Old Posted Feb 6, 2018, 7:09 PM
c_speed3108 c_speed3108 is offline
Registered User
 
Join Date: May 2007
Posts: 1,859
The other thing is RTG is getting hit with big costs as the city is not paying for things that are not ready.

For example the maintenance contract start gets pushed back 6 months. I read someplace that is $4m a month (x 6 months).

They also have to pay the cities extra costs to keep the buses running.

...and of course the added construction costs.


Granted Taxpayers don't really directly get anything out of those, but I don't see how they would be motivated to drag this thing out.
     
     
  #5997  
Old Posted Feb 6, 2018, 7:23 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
Quote:
Originally Posted by acottawa View Post
Which is why there should be a daily penalty for such projects.
Newer Infrastructure Ontario P3s have daily penalties. I'm surprised ours doesn't.
     
     
  #5998  
Old Posted Feb 6, 2018, 7:24 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
Quote:
Originally Posted by HighwayStar View Post
Sure.... now that they've learned that penalties are meaningless threats... they'll have *real* incentive to honour all the rest of their contractual commitments.
They don't get paid until its done, and they're carrying a lot of project debt. That's their incentive to get this done.

Apparently RTG wanted a revised handover date earlier than Nov 2 but city staff insisted on Nov 2. I'm curious to know the machinations that led to that one.
     
     
  #5999  
Old Posted Feb 6, 2018, 7:25 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
Quote:
Originally Posted by Kitchissippi View Post
The sinkhole does not explain why the non-tunnel stations are also late. It's funny how the Spring 2017 newsletter is still a sticky on the website. Looking at the photos in it, which are almost a year old, progress on the eastern stations seem very slow.
I think they diverted resources away from the surface segments and into the tunnel after the sinkhole. Pre-sinkhole the surface sections were actually a few months ahead of schedule.
     
     
  #6000  
Old Posted Feb 6, 2018, 7:34 PM
acottawa acottawa is online now
Registered User
 
Join Date: Aug 2009
Posts: 18,928
Quote:
Originally Posted by 1overcosc View Post

Apparently RTG wanted a revised handover date earlier than Nov 2 but city staff insisted on Nov 2. I'm curious to know the machinations that led to that one.
A few days earlier or a few months earlier?
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 6:56 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.