Quote:
Originally Posted by skyscraperpage17
I'm not sure what other type of hurdles you're referring to. There are no zoning restrictions and the issue with the rail lines would not impede development on the parking lots.
Can you please elaborate?
|
At the concept stage of any project, a ton of work remains. In this case it seems like:
--99% of the design work
--Land use permits, which can be a lengthy process even if the buildings meet basic zoning
--Deals with the railroads, who typically have tons of leverage for anything in their RoWs
--Geotech studies
--The impact topics you mentioned, with local decisions required about how to address them
--Hiring the rest of the team, and digging into sizable design issues such as structural types, shoring methods, sustainability goals, enclosure, etc., all dependent on the details of those railway agreements, zoning variances, etc. I mean general contractor(s), engineering firms, key early subcontractors, etc. (I don't know who's on board yet.)
--Figuring out the general price and schedule parameters, which will be extremely vague at this point.
--Building permits (probably quick, toward the end on a per-building basis)
This might all be streamlined and easy, but at this stage barriers can go up, anything from a political backlash to lawsuits to simply being wrong about cost. I'm imagining that Amazon might give points to a place where much of this work has already happened and there are fewer potential wildcards.