Quote:
Originally Posted by acottawa
If the geography of eastern ontario was such that you had to load your car onto a train or take a ferry to get across it I would believe Via could get 10 million passengers on its train/car ferry service.
|
You seem to ignore the fact that those people can take the ferry and they choose the train. I think it's pretty deceiving to say only 10 million ride the Eurostar. That's clearly not true. And the Tunnel's owners themselves would take exception to that.
When it comes to the topic at hand, I don't see how demand suddenly goes up if you had a barrier like the Channel. Unless you have policies in place to induce demand. If the ferry had a substantially better value proposition, they wouldn't be bleeding ridership to the Eurotunnel. So your assertion that demand happens just because of geography is rather suspect.
Quote:
Originally Posted by acottawa
It is an example of the level of detail in the analysis and cost estimates that would be normally done for a major project such as this (which Via is either keeping secret or has not done).
Before the study, people like you kept saying how easy a Peterborough GO train would be, how there is an existing line, etc. After more detailed study (and costing) was available enthusiasm waned.
|
I have never said the GO Train was easy. And thought it was ridiculous when first proposed. And still do.... The only reason to have commuter services on that corridor is to better serve Scarborough. Peterborough would be a byproduct of that investment.
And you are right that more detail is required. I don't get though, why you expect such detail on the first cut of an idea. Until the last budget, they hadn't been allocated funds to study the concept. I think they did as much as they could for a Rough Order of Magnitude estimate and put that out.
And for a ROME, it's decent. Their per km estimate is not out of line with most pre-dominantly rural rail lines. That's enough to get the conversation rolling and fund actual analysis and EAs and such.
Quote:
Originally Posted by acottawa
Also, you have to wonder if the necessary upgrades to Peterborough (expecting much slower speeds and lower frequencies than HSR) had capital costs of 900M to 1.5 billion, one has to wonder where Via is getting its cost estimates from for a project 4x longer that requires a significant greenfield construction project.
|
The proposal to Peterborough has expenses built in which HFR would never need. Higher corridor capacity, more stations and more vehicles. To suggest that this is indicative of substantially poor staff work on HFR is to assume that the entire HFR line is going to be built and operated at a performance level of commuter rail in Toronto. That's quite the assumption.