HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Metro Vancouver & the Fraser Valley


Reply

 
Thread Tools Display Modes
     
     
  #2141  
Old Posted May 22, 2017, 5:11 PM
donslade donslade is offline
Registered User
 
Join Date: Feb 2017
Posts: 33
Quote:
Originally Posted by GeeCee View Post
They're not really talking about the towers here so much as the retail components that the leasing site addresses. Turn over is when substantial construction of the building(s) are completed and the individual tenants can begin fitting out their leased space to suit their own needs.
Given that, when would residents move in? Original completion date for tower one is Dec 2017 with an outside date of Dec 2018.
Reply With Quote
     
     
  #2142  
Old Posted May 22, 2017, 7:19 PM
GilmoreStation GilmoreStation is offline
BANNED
 
Join Date: Apr 2016
Location: Burnaby
Posts: 465
All I know is that the presale for tower 5 is now pushed back to Fall 2017 (originally Spring 2017)
Reply With Quote
     
     
  #2143  
Old Posted May 22, 2017, 11:15 PM
Marshal Marshal is offline
perhaps . . .
 
Join Date: Dec 2015
Location: Vancouver
Posts: 1,493
Actually, 'turn over' is a legal/contractual 'event.' It is when the building is literally turned over to the owner from the construction team. It is the step that defines building lien timelines, warantees, legal responsibility for the project in terms of safety, maintenance, operations of HVAC, and even includes the handover of systems and who gets the bills thereafter (for example, the electric bill is no longer the contractor's responsibility, but the owners). Hand over is also the formal process in which final/near final inspections are done and the discrepancy list is compiled (all the things that are unfinished or not done properly) are identified and hold-back amounts are determined. All in all, its a pretty big deal in the timeline.

Tenant improvements and leases involve the owner and the tenant . . . turn over has nothing to do with tenants fitting out their spaces, except that the owner must have possession of the building before they can allow their tenants to proceed.

If I remember, phase 1 included both mall and towers 1 & 2. If that was a legal packaging of the project, these dates should be for all of it. However, a developer can define 'phases' for marketing purposes, and the contractual breakdown is different.
Reply With Quote
     
     
  #2144  
Old Posted May 23, 2017, 1:09 AM
SpongeG's Avatar
SpongeG SpongeG is offline
Registered User
 
Join Date: Jun 2006
Location: Coquitlam
Posts: 39,889
So the mall retail won't open until fall 2019?
__________________
belowitall
Reply With Quote
     
     
  #2145  
Old Posted May 23, 2017, 2:43 AM
donslade donslade is offline
Registered User
 
Join Date: Feb 2017
Posts: 33
Quote:
Originally Posted by SpongeG View Post
So the mall retail won't open until fall 2019?
Website still sez fall 2018 for mall so I assume that means shops etc are open then. As someone who intends to live there I'd really like to see a more specific move in date for residence.
Reply With Quote
     
     
  #2146  
Old Posted May 23, 2017, 6:53 PM
n86 n86 is offline
Registered User
 
Join Date: Apr 2017
Location: North Burnaby, BC
Posts: 9
Found this image on Shape Properties' leasing website. Gives a better idea of the future vision/density of the Brentwood Town Centre area.

http://shapeproperties.com/leasing/asset.../images/gallery/brentwood-gallery-21.jpg
Reply With Quote
     
     
  #2147  
Old Posted May 23, 2017, 7:38 PM
VarBreStr18 VarBreStr18 is offline
Registered User
 
Join Date: Nov 2014
Posts: 748
Quote:
Originally Posted by Marshal View Post
Actually, 'turn over' is a legal/contractual 'event.' It is when the building is literally turned over to the owner from the construction team. It is the step that defines building lien timelines, warantees, legal responsibility for the project in terms of safety, maintenance, operations of HVAC, and even includes the handover of systems and who gets the bills thereafter (for example, the electric bill is no longer the contractor's responsibility, but the owners). Hand over is also the formal process in which final/near final inspections are done and the discrepancy list is compiled (all the things that are unfinished or not done properly) are identified and hold-back amounts are determined. All in all, its a pretty big deal in the timeline.

Tenant improvements and leases involve the owner and the tenant . . . turn over has nothing to do with tenants fitting out their spaces, except that the owner must have possession of the building before they can allow their tenants to proceed.

If I remember, phase 1 included both mall and towers 1 & 2. If that was a legal packaging of the project, these dates should be for all of it. However, a developer can define 'phases' for marketing purposes, and the contractual breakdown is different.
thanks for the explanation, you are very knowledgeble.
Wonder how "finished" is the turn over stage such as interior walls partitions etc etc? is this similar to "lock up stage"? thanks
Reply With Quote
     
     
  #2148  
Old Posted May 23, 2017, 8:06 PM
Spr0ckets Spr0ckets is offline
Registered User
 
Join Date: Oct 2015
Posts: 1,924
Quote:
Originally Posted by n86 View Post
Found this image on Shape Properties' leasing website. Gives a better idea of the future vision/density of the Brentwood Town Centre area.

http://shapeproperties.com/leasing/asset.../images/gallery/brentwood-gallery-21.jpg
That's a really great image.

I love how they put the effort into showing or projecting how neighbouring sites will look like with proposed and currently-in-process developments complete, as well as projecting a (currently non-existent) multi-tower project to some sites to their immediate south (unless they know something we don't about those car dealerships).

That's pretty dense, and if they actually realise all of it, it would make the Brentwood area an actual true town center/metropolis.
Reply With Quote
     
     
  #2149  
Old Posted May 23, 2017, 10:29 PM
Marshal Marshal is offline
perhaps . . .
 
Join Date: Dec 2015
Location: Vancouver
Posts: 1,493
Quote:
Originally Posted by VarBreStr18 View Post
thanks for the explanation, you are very knowledgeble.
Wonder how "finished" is the turn over stage such as interior walls partitions etc etc? is this similar to "lock up stage"? thanks
"Lock up" and "Turn over" are informal terms that we don't use in either documents or contracts. I think they are common because contractors use them.

There is a specific terminology that specifies the procedures involved in the turning over (or taking over) of a project. My previous post spoke loosely and I will correct that here.

Take-over procedures typically begin at between 95 and 99% completion. This, of course is strictly impossible to determine, so it is a bit of a fiction and is determined simply through the architect’s acknowledgement.

It begins with a contractor’s inspection of Substantial Performance, and preparation of a list of uncompleted work. On that basis the contractor applies for a Certificate of Substantial Completion.
The issuance of this triggers liens (holdbacks of up to 30 days after substantial performance), warrantees and guarantees.

The architect/engineer inspects and produces the Deficiency List (the actual construction is inspected with regard to drawings/specifications and scope). The architect then prepares a Certificate of Substantial Performance.

The contractor/owner applies to the municipality for a Temporary Occupancy Certificate, or an Occupancy Certificate.

As the unfinished work and deficiencies are rectified, the architect provides a Certificate for Payment of Holdback Monies.
The BC Liens Statute sets ou the following timeline:
Substantial Performance
30 day period for lien registrations
10 day grace (checking of liens)
Hold back released (41 day total)
This requires a notarized declaration that all contributors have been paid by the prime contractor.

The architect and project team perform a final inspection: issuing a Certificate of Total Performance, signifying the contractor has satisfied the architect’s deficiency list
the guarantee period starts
final payment is initiated

Last edited by Marshal; May 23, 2017 at 10:51 PM.
Reply With Quote
     
     
  #2150  
Old Posted May 23, 2017, 10:45 PM
Marshal Marshal is offline
perhaps . . .
 
Join Date: Dec 2015
Location: Vancouver
Posts: 1,493
And while I am going overboard, here is an indication of the required submissions for completion:

Occupancy Permit
Fire Inspection Report
Building Inspection
Factories Act Inspection
Health Inspection
Equipment Manuals and Catalogues Submission
Warranties
Guarantees
Balancing Reports (Air and Water controls & operations)
Hand Over of 'extra' materials to owner
Key Handover
Special Tools and Equipment
All Construction Test Reports
Complete set of As-Built Drawings
Statutory Declaration by Contractor concerning proper payment of Suppliers and Sub-contractors
Hydro Test Certificate
Elevator/Hoist Certificates
Schedule of future Air Conditioning Test
Emergency Generator Manuals
List of all contractors and agencies involved with water, gas, electricity, digital controls and systems, alarms and special safety components
Owner's Operational Staff Training Program
CERTIFICATE OF SUBSTANTIAL PERFORMANCE
CERTIFICATE OF TOTAL PERFORMANCE

I'm sure I have missed a few, but this is the list we manage as part of our coordinating role on projects . . . at least as of the last update of our office manual.
Reply With Quote
     
     
  #2151  
Old Posted May 24, 2017, 2:54 AM
Cypherus's Avatar
Cypherus Cypherus is offline
Registered User
 
Join Date: Jan 2007
Location: Surrey
Posts: 1,759
Quote:
Originally Posted by Marshal View Post
And while I am going overboard, here is an indication of the required submissions for completion:

Occupancy Permit
Fire Inspection Report
Building Inspection
Factories Act Inspection
Health Inspection
Equipment Manuals and Catalogues Submission
Warranties
Guarantees
Balancing Reports (Air and Water controls & operations)
Hand Over of 'extra' materials to owner
Key Handover
Special Tools and Equipment
All Construction Test Reports
Complete set of As-Built Drawings
Statutory Declaration by Contractor concerning proper payment of Suppliers and Sub-contractors
Hydro Test Certificate
Elevator/Hoist Certificates
Schedule of future Air Conditioning Test
Emergency Generator Manuals
List of all contractors and agencies involved with water, gas, electricity, digital controls and systems, alarms and special safety components
Owner's Operational Staff Training Program
CERTIFICATE OF SUBSTANTIAL PERFORMANCE
CERTIFICATE OF TOTAL PERFORMANCE

I'm sure I have missed a few, but this is the list we manage as part of our coordinating role on projects . . . at least as of the last update of our office manual.
Good to know about "Statutory Declaration by Contractor concerning proper payment of Suppliers and Sub-contractors". Very useful information to common people who visit this message board...
Reply With Quote
     
     
  #2152  
Old Posted May 24, 2017, 5:08 AM
Marshal Marshal is offline
perhaps . . .
 
Join Date: Dec 2015
Location: Vancouver
Posts: 1,493
It's not supposed to be useful in that sense. Its just good sometimes to see the real thing (the full list) to get an idea of what something really is.

Its just information, nothing to be scared of. No need to be an ass because your curiousity is limited. Besides, you denigrate "the common people" by thinking you know what they might find useful.
Reply With Quote
     
     
  #2153  
Old Posted May 24, 2017, 8:49 PM
Spr0ckets Spr0ckets is offline
Registered User
 
Join Date: Oct 2015
Posts: 1,924
I could be wrong, but I really didn't read that as him being an ass.

He seems (to me anyway) to be genuinely grateful to be informed with knowledge that laypeople (i.e 'the common people', as he put it and which he seems to count himself as) don't typically get exposed to nor appreciate - which account for a good amount of people who visit this forum.

Besides which, all knowledge is useful.
It just depends on how it applies (or not) to the person receiving it and possibly using it.
Reply With Quote
     
     
  #2154  
Old Posted May 24, 2017, 11:23 PM
Marshal Marshal is offline
perhaps . . .
 
Join Date: Dec 2015
Location: Vancouver
Posts: 1,493
You could be right. Maybe I was too quick to see sarcasm. Regardless, he can let me know.
Reply With Quote
     
     
  #2155  
Old Posted May 26, 2017, 1:52 PM
Klazu's Avatar
Klazu Klazu is offline
Registered User
 
Join Date: Apr 2012
Location: Above Metro Vancouver clouds
Posts: 10,387
Drove by yesterday and the dark spandrel looks pretty good in person. I was also pleasantly surprised by the wood being installed on top of the podium spandrel. I am back to hopeful for this project.
Reply With Quote
     
     
  #2156  
Old Posted May 26, 2017, 4:54 PM
Caliplanner1 Caliplanner1 is offline
BANNED
 
Join Date: Mar 2015
Posts: 692
Quote:
Originally Posted by Klazu View Post
Drove by yesterday and the dark spandrel looks pretty good in person. I was also pleasantly surprised by the wood being installed on top of the podium spandrel. I am back to hopeful for this project.
It would be cool to get a picture shot of your verbal praise for the dark spandrel and the complementary wood atop the podium spandrel. Thanks for the mental stimulation.
Reply With Quote
     
     
  #2157  
Old Posted May 26, 2017, 8:09 PM
logicbomb logicbomb is offline
Joshua B.
 
Join Date: Sep 2010
Posts: 1,187
Driving around there is going to suck. It already sucks.
Reply With Quote
     
     
  #2158  
Old Posted May 26, 2017, 10:05 PM
donslade donslade is offline
Registered User
 
Join Date: Feb 2017
Posts: 33
The camera down again?
Reply With Quote
     
     
  #2159  
Old Posted May 27, 2017, 9:26 PM
Locked In's Avatar
Locked In Locked In is offline
Registered User
 
Join Date: Aug 2008
Location: Vancouver
Posts: 1,977
My photos from May 22:


IMG_8825 by 604 City, on Flickr



IMG_8824 by 604 City, on Flickr
__________________
My Flickr Photostream
Reply With Quote
     
     
  #2160  
Old Posted May 27, 2017, 10:08 PM
Caliplanner1 Caliplanner1 is offline
BANNED
 
Join Date: Mar 2015
Posts: 692
Thanks for the update. This project is looking good. I like the dark glass and wood.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Metro Vancouver & the Fraser Valley
Forum Jump



Forum Jump


All times are GMT. The time now is 3:47 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.