Old Posted Apr 24, 2017, 3:17 PM
mitchellk12's Avatar
mitchellk12 mitchellk12 is offline
 
Join Date: Sep 2015
Posts: 677
Quote:
Originally Posted by prairieguy View Post
Those most recent pics give a great perspective as to the scope and depth of the "dig". I noticed the very first portion of tower/crane was vertical the other day. Could this be the start of assembling the crane!? So exciting!!
i believe so since the base was assembled last week. usually thats a clear sign.

this week or next week for sure.
Reply With Quote
     
     
  #702  
Old Posted Apr 24, 2017, 5:29 PM
Crisis's Avatar
Crisis Crisis is offline
 
Join Date: Apr 2010
Posts: 1,335
Quote:
Originally Posted by mitchellk12 View Post
i believe so since the base was assembled last week. usually thats a clear sign.

this week or next week for sure.
Hopefully the pace will pick up once the tower crane is erected. We're told that they're supposed to be done the parkade this summer. That won't be happening at the current rate of progress.
Reply With Quote
     
     
  #703  
Old Posted Apr 24, 2017, 5:42 PM
mitchellk12's Avatar
mitchellk12 mitchellk12 is offline
 
Join Date: Sep 2015
Posts: 677
Quote:
Originally Posted by Crisis View Post
Hopefully the pace will pick up once the tower crane is erected. We're told that they're supposed to be done the parkade this summer. That won't be happening at the current rate of progress.
By going off of the college quarter hotel. That went up fast even the parkade. Now i dont know how much of a difference in constructing an underground parkade as to an above ground...but that crane even with the 9 storeys looked quick to me...maybe im wrong.

But with the crane coming soon...and with the second. Im optomistic that it will take off quick.
Reply With Quote
     
     
  #704  
Old Posted Apr 25, 2017, 12:54 AM
dsmmace dsmmace is offline
 
Join Date: Jun 2012
Posts: 423
Parkade should be done, as the structure will start on the second floor and the slab on grade will be later, it should go up to ground level relatively quickly.
Reply With Quote
     
     
  #705  
Old Posted Apr 28, 2017, 2:44 PM
mitchellk12's Avatar
mitchellk12 mitchellk12 is offline
 
Join Date: Sep 2015
Posts: 677
http://thestarphoenix.com/news/local-news/revised-schedule-proposed-for-next-river-landing-phases

not sure if i should post this here, or the stoon III thread

but interesting article.
Reply With Quote
     
     
  #706  
Old Posted Apr 28, 2017, 9:31 PM
saskatoonborn saskatoonborn is offline
 
Join Date: Aug 2013
Posts: 297
Wow the banks has either not updated their website in a while or sales have really ground to a halt I am sure that is disapointing for the dev. Im glad that the pumphouse is going to be leased as a restaurant.... also it absolutly has to be called The Pumphouse.
Reply With Quote
     
     
  #707  
Old Posted May 1, 2017, 3:37 PM
prairieguy prairieguy is offline
 
Join Date: Apr 2007
Posts: 1,577
There is a tall crane/lift at the Riverlanding site adjacent to the first upright red piece of the main crane by the excavated hole....this must mean the assembly of crane is imminent?!
Reply With Quote
     
     
  #708  
Old Posted May 1, 2017, 5:09 PM
mitchellk12's Avatar
mitchellk12 mitchellk12 is offline
 
Join Date: Sep 2015
Posts: 677
Quote:
Originally Posted by prairieguy View Post
There is a tall crane/lift at the Riverlanding site adjacent to the first upright red piece of the main crane by the excavated hole....this must mean the assembly of crane is imminent?!
its been there since thursday/friday. since its still on the site, im assuming its to assemble the crane - whatever the schedule is for that. i havent seen anymore sections of the crane appear yet. but i expect a couple trailers with the rest of it to come at some point soon. the base is in....so we all know its happening finally. when crane bases are installed, its usually a short time frame before they get assembled.
Reply With Quote
     
     
  #709  
Old Posted May 1, 2017, 7:17 PM
Crisis's Avatar
Crisis Crisis is offline
 
Join Date: Apr 2010
Posts: 1,335
^^^ The tower crane erection is simply going at the same pace as the rest of the parkade...

OK, that's a little catty, but this thing isn't exactly setting records for progress. And, no, Capital Pointe in Regina is not a project that should be used for comparison purposes.
Reply With Quote
     
     
  #710  
Old Posted May 1, 2017, 7:51 PM
Tumu Gongchengshi Tumu Gongchengshi is offline
 
Join Date: May 2017
Posts: 2
Does anyone know if Stuart Olson is the general contractor only for the parkade or the whole condo structure? I know that Bockstael is the construction manager.

Have the general contractors been awarded for the hotel or east office towers?
Reply With Quote
     
     
  #711  
Old Posted May 1, 2017, 8:17 PM
Crisis's Avatar
Crisis Crisis is offline
 
Join Date: Apr 2010
Posts: 1,335
Quote:
Originally Posted by Tumu Gongchengshi View Post
Does anyone know if Stuart Olson is the general contractor only for the parkade or the whole condo structure? I know that Bockstael is the construction manager.

Have the general contractors been awarded for the hotel or east office towers?
If someone has information to the contrary, please feel free to correct me, but here is my understanding of what is happening on site:

- Stuart Olson is the Construction Manager and General Contractor for the parkade beneath the hotel/condo only. They are self-performing the concrete work.

- Bockstael is the Construction Manager for both the Hotel and the Condo. They will not be self-performing the concrete work.

- Ledcor is Construction Manager for the East Tower and the parkade beneath it. They will not be self-performing the concrete work.
Reply With Quote
     
     
  #712  
Old Posted May 1, 2017, 8:58 PM
Tumu Gongchengshi Tumu Gongchengshi is offline
 
Join Date: May 2017
Posts: 2
Thanks for the quick reply Crisis. You read my mind by about the concrete work; that's exactly what I wanted to know.
Reply With Quote
     
     
  #713  
Old Posted May 1, 2017, 9:37 PM
mitchellk12's Avatar
mitchellk12 mitchellk12 is offline
 
Join Date: Sep 2015
Posts: 677
Quote:
Originally Posted by Crisis View Post
If someone has information to the contrary, please feel free to correct me, but here is my understanding of what is happening on site:

- Stuart Olson is the Construction Manager and General Contractor for the parkade beneath the hotel/condo only. They are self-performing the concrete work.

- Bockstael is the Construction Manager for both the Hotel and the Condo. They will not be self-performing the concrete work.

- Ledcor is Construction Manager for the East Tower and the parkade beneath it. They will not be self-performing the concrete work.

and the East office tower is good to go this year? the MVA site says so, and you guys on here.

in the link i posted last friday about the D/E parcel being opened up, something said a feature building is going to begin once the traffic bridge is completed. dont know if they are talking about the East office, the parcel d/e OR something else...

im curious on that topic.
Reply With Quote
     
     
  #714  
Old Posted May 1, 2017, 9:44 PM
The Bess The Bess is offline
 
Join Date: Apr 2008
Posts: 892
The feature building was something totally different. I believe it was supposed to be a building with a restaurant in it. This was to be on land other than the parcels you mentioned. There was no interest in it on the first go around a while back.
Reply With Quote
     
     
  #715  
Old Posted May 1, 2017, 10:42 PM
SaskE30 SaskE30 is offline
 
Join Date: Oct 2014
Posts: 182
Tower crane is up!
Reply With Quote
     
     
  #716  
Old Posted May 1, 2017, 11:17 PM
Stormer's Avatar
Stormer Stormer is online now
 
Join Date: Jan 2008
Posts: 8,086
Quote:
Originally Posted by SaskE30 View Post
Tower crane is up!
pictures please.
Reply With Quote
     
     
  #717  
Old Posted May 2, 2017, 1:55 AM
Echoes's Avatar
Echoes Echoes is offline
 
Join Date: Oct 2006
Posts: 4,542
Didn't get a shot, but it's just a baby right now. Typical length boom for a tower crane, but it's very low to the ground. Maybe 15-20 m above grade? I laughed when I saw it.
Reply With Quote
     
     
  #718  
Old Posted May 2, 2017, 9:04 PM
prairieguy prairieguy is offline
 
Join Date: Apr 2007
Posts: 1,577
I had same reaction.....that's it???!!! But I guess this is just for the parkade portion of project and a crane of more significance will go up when they get to grade. This one is for sure "underwhelming" after so much built up anticipation...haha But it is progress!
Reply With Quote
     
     
  #719  
Old Posted May 3, 2017, 3:26 AM
SaskE30 SaskE30 is offline
 
Join Date: Oct 2014
Posts: 182
Quote:
Originally Posted by Stormer View Post
pictures please.
As requested:

(Taken 02/05/2017)



Reply With Quote
     
     
  #720  
Old Posted May 3, 2017, 7:25 AM
Dalreg's Avatar
Dalreg Dalreg is offline
 
Join Date: Mar 2006
Posts: 2,004
You can always add sections in and make it grow. No need for a crane 100 metres up for now especially if all the work is below grade.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Manitoba & Saskatchewan
Forum Jump



Forum Jump


All times are GMT. The time now is 4:40 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.