Quote:
Originally Posted by Alex Mackinnon
He says as Big Bertha is being sold for scrap...
|
What is being scrapped is the cutting head itself.
Not surprising since the cutters and teeth are always the parts get most damaged during the bore. Some TBM projects build in maintenance schedules to stop the machine and back away from the cut face so the cutter wheels and teeth can be replaced with new parts before resuming the bore.
The TBM used for the Canada Line had it's cutting head removed at the Waterfront retrieval pit, dis-assembled to be trucked back to the Olympic launch pit and refurbished for the second bore. The rest of the TBM was rolled back through the just-built tube from Waterfront back to the Olympic launch pit, shifted over to begin the second bore, the refurbished cutting head was re-attached to the machine, and the second bore to Waterfront was begun.
Once the cutting head has been detached from Big Bertha and cut into manageable 20T pieces for scrapping, the rest of the 300 foot long machine will be dis-assembled and removed from both the launch and retrieval pits.
For its next project, Big Bertha can have a new cutting head attached (and likely scrapped at the end of that project too) specially designed for the geology it will be boring through. The rest of the machine can be refurbished and reused many times for many projects until it also becomes too expensive to repair.