Quote:
Originally Posted by jsbertram
The Canada Line tracks at City Hall Stn are entirely under the Cambie northbound traffic lanes.
From the existing City Hall station mezzanine, a new pedestrian tunnel through the west wall knock-out can connect to the new Millennium Line Broadway/Cambie station mezzanine and can be buried under the Cambie southbound traffic lanes.
|
Yeah, there's about 2 lanes plus sidewalk width.
You just won't have an expansive space like some of the comments about the need for lots of capacity, etc. suggest.
http://canadalinephotos.blogspot.ca/sear...0Z&max-results=20&start=37&by-date=false
The knock-out panel is marked in red here:
Quote:
Originally Posted by jsbertram
I haven't seen any plans showing direct connections from M-line platforms to C-line platforms.
For crowd management, they prefer to have the crowds leave a platform to the station mezzanine, transfer to the other station mezzanine (crossing the street or via a connecting passageway), then to the platform.
|
Agreed that circulating to the mezzanine at Broadway City-Hall requires travel to a higher level when it isn't really necessary, especially if the M-Line extension is under Broadway rather than under 10th Ave.
It would be nice to have a direct connection from the Broadway City hall platform ends to the M-Line platform (centre platform?)
but then you have the problem of people taking the wrong escalator from the M-Line and ending up on the wrong Canada Line platform.
So I can see the simplification aspect of it.
I could see a set of 3 long escalators (like Granville Station) coming up from the M-Line to the mezzanine.
M-Line Station placement and centre/outside platforms would determine configurations for its exits (i.e. end of platform, mezzanines, etc.).