As our inaugural year, 2016 will always be an unforgettable one. But 2017 promises to be every bit as monumental, filled with more exciting firsts and memorable highlights. Here’s a look ahead at construction milestones we can all look forward to happening in the next 12 months:
January
Excavation on the future residences and retail on the west side of ICE District was completed.
February
Work will commence on the final section of the main ICE District underground parkade, which will be accessible from the JW Marriott, The Legends Private Residences, Stantec Tower, residences at Stantec Tower, and the future retail and residences on the west side.
May
Stantec Tower and the JW Marriott/The Legends Private Residences tower will near the 20-storey mark.
July
The JW Marriott hotel levels will top out and the residential portion of The Legends Private Residences will commence. The Public Plaza footprint will be taking shape south of Ford Hall, with the cladding and glazing on the Stantec Tower podium well underway.
September
Parkade grade slabs, under the future residences on the west side, will be nearing completion and will allow erection of the steelwork for the retail podium to commence. The tower core will reach grade.
November
Work on the future residential tower, located on the west side, should be above grade alongside the developing retail podium.
December
The Stantec Tower office levels will top out and the residential portion of the tower will commence. All towers in this phase of ICE District will be well underway. The floors of The Legends Private Residences will be about half-way done.
|