Construction Update
Week of November 14
This week, crews are hard at work installing the traction power sub station just east of Tunney’s Pasture Station and pulling rails at Lees Station. Final construction is wrapping up on the bus operators’ building at Hurdman Station, with just the interior finishes remaining. Residents will also see glimpses of the first light rail vehicle being tested on the guideway from Cyrville to Blair stations.
West Stations
Tunney’s Pasture Station: Initial station construction occurs and includes drilling caissons and underground electrical work.
Bayview Station: Activities progress at the station with the installation of duct banks, underground electrical and mechanical work, ground improvement during the daytime and overnight, as well as formwork and pours for grade beams.
Pimisi Station: Construction of the retaining walls is ongoing. Crews also install duct banks, waterproof and backfill walls, and continue mechanical and electrical work.
Lyon Station cavern: Station construction continues to progress with the installation of formwork for the deck and architectural work, including forming walls for the mechanical room and stairs. Final shotcrete continues in the west transition.
Lyon Station west entrance: The station entrance continues to take shape; concrete activities for the mid-landing, including rebar, formwork and pours, and work on tiebacks and rock removals occur.
Lyon Station east entrance: This week, station construction includes structural steel installation, as well as waterproofing, rebar, formwork and concrete pours for the ground floor and mezzanine walls and slabs. Crews continue rock removal at the east vent shaft in preparation for the next phase of activities.
Parliament Station cavern: Station construction advances; crews pour concrete on the last section of L-walls, work on conduits and begin building the invert.
Parliament Station west entrance: Entrance construction takes shape with work on the roof of the head house and mobilization to install flashing. Construction of the east vent shaft is ongoing and includes hoe ramming and removals during the weekend, and rock bolt installations during the week.
Traffic restrictions on Queen and O’Connor streets remain in effect.
Rideau Station cavern: Concrete work is ongoing in the station. In addition to constructing the bloc walls and waterproofing, crews continue spraying shotcrete and waterproofing the arch. Crocodile Rouge moves to the East Portal on the weekend to continue work in the running tunnel.
Rideau Station west entrance: Work progresses at the entrance; crews waterproof walls and slabs, install shoring, work on foundation panels and mobilize to begin the next phase of umbrella installation. Shoring and excavation also occur at the HVAC shaft.
Rideau Station east entrance: Concrete activities ramp up this week and crews continue installing rebar and formwork followed by concrete pours.
Rideau Street is closed 24/7 to vehicular traffic to permit works to advance, including jet grouting activities.
uOttawa Station: The station continues to take shape with crews installing rebar, and pouring concrete for walls and footings. Ongoing activities include work on underground utilities, duct banks and backfilling.
East Portal: Work advances at the ramp and includes waterproofing, pouring conduits and drilling tiebacks to allow for excavation to resume next week.
East Stations
Lees Station: With the raft slab complete, crews work on the watermain protection, and mobilize to begin micro-piling activities which will be followed by underground utilities work.
Hurdman Station: Structural steel and final concrete pours occur for the ancillary building. Formwork and rebar installations are ongoing for the stairs and platforms to allow for more concrete pours in the coming weeks. Crews complete mechanical and electrical work at the bus operator’s building, start framing and continue working on partitions and interior finishes.
Tremblay Station: Activities progress at the station and include concrete pours, framing for upcoming porcelain panel installations, masonry, backfilling and construction of basement walls and underground mechanical and electrical work.
St-Laurent Station: Crews complete work on the ceiling hangers, continue concrete pours for the elevator and electrical room areas and begin installing steel for the platform and plenum.
Cyrville Station: Soffit framing, mechanical and electrical work and glazing are ongoing, in addition to waterproofing activities for the elevator pits. Crews begin interior construction at the auxiliary building.
Blair Station: Crews continue structural framing, exterior wall panel and soffit panel installations, as well as mechanical and electrical work. Construction progresses at bus operators’ building with waterproofing activities.
Tunnel Excavation and Support
Mining and reinforcements will be ongoing in the last section of running tunnel west of Rideau Station during the next weeks.
Guideway
Tunney’s Pasture Station to West Portal: Activities ramp up on the guideway; crews install the traction power sub station just east of Tunney’s Pasture Station, backfill and continue working on the fixation track slab and overlay. Duct banks and Overhead Catenary System foundations installation is ongoing.
Mann Avenue Bridge to west of Tremblay Station: Construction of the guideway in this section of the alignment is advancing and includes installation of fencing and duct banks, pulling rail at Lees Station and working on the traction power sub station foundation just east of Hurdman Station.
Other Activities
Mann Avenue Bridge: Crews continue working on the bridge deck for the next weeks. Intermittent sidewalk closures may be required during bridge reconstruction.
Upcoming Construction Activities
In the coming weeks, the following construction activities are scheduled to occur:
- Removal of the overhead scaffolding at Bayview Bridge requiring intermittent sidewalk closures.
- Lyon Station HVAC and west vent shaft work resumes.
- Rideau Station west TVS shoring.
- Structural steel installation at uOttawa Station.
- Installation of traction power sub stations on the guideway west of Lees Station and just east of Hurdman Station.
- Fencing installation on guideway just west of Tremblay Station.
- Vehicle testing and Overhead Catenary System will be energized in phases along the guideway between Belfast Yard and Blair Station.
- Installation of porcelain panels at Cyrville and Blair stations.