Sneak peek: five things you’ll find in the new light rail stations
From cafes and kiosks to digital schedule boards, the new light rail stations are far from your basic O-Train platform.

By: Emma Jackson
Metro Published on Wed Oct 19 2016


The 13 light rail stations opening in 2018 aren’t your regular O-Train platforms. Far from it: these state-of-the-art buildings will be packed with all-new integrated signage, ticket booths, digital schedules and, if you’re lucky, cafes and convenience stores. Check out the coolest features transit commission approved at its meeting Wednesday.

On the run

Grab a fresh muffin on your way to work, or pick up your dry cleaning on the way home: these are the kinds of services that will keep customers riding the rails, OC Transpo staff said Wednesday. There’s retail space planned at Tunney’s Pasture, Rideau, Hurdman and Blair stations, and staff want them filled with bright, open-concept cafes, convenience stores and services. Kiosks, vending machines and ATMs could also make an appearance. But the city doesn’t stand to make much money from the deals: securing the right services for customers – regardless of what the owner can pay in rent – is as important as making money, staff said.

The O Dot

Like London’s infamous tube signs, staff want the O-Train’s “big, red O” to become a universally recognizable symbol that transit is ready and waiting nearby. The illuminated Os will be posted outside all train station entrances, and the same theme will be incorporated into major station signs. Staff are working with tourist agencies to make sure visitors get the message, too.

Get with the times

Real-time digital schedules will tell passengers when the next two trains are expected, and audio messages will announce their arrival. With trains arriving every few minutes during rush hour, the signs will keep passengers in the loop without having to check the schedule, staff said. Digital bus schedules with real-time updates will also be installed for passengers transferring to local routes.

Take a walk

Using transit can be disorienting if you don’t know where you’re going, so staff have developed localized maps for each station that show passengers what’s within five minutes walking distance of the exit. Particularly in the downtown core, this will help tourists (and inexperienced residents) figure out which way is up and how to access major landmarks, staff said.

Seeing red (and green)

System maps will look a lot like Christmas – even in July – since the system will use red and green markers to differentiate lines one and two. Staff dismissed concerns this choice could impact people with colour blindness: they said particular red and green hues will create contrast between the two colours, and they’ll be tested to make sure they’re legible to everyone.

http://www.metronews.ca/news/ottawa/2016...find-in-the-new-light-rail-stations.html
     
     
  #3922  
Old Posted Oct 20, 2016, 7:06 PM
OTSkyline OTSkyline is offline
Registered User
 
Join Date: Jun 2012
Posts: 2,818
Get with the times

THIS!! This is a big reason why I prefer train/subway travel than bus. I love being in the subway station and having those big electronic signs showing the waiting time for the next trains "2 minutes - 8 minutes".. That way you sit tight and you know what to expect. I had waiting right now at an OC Transpo bus stop for whatever random amount of time I need to.. Perfect scenario:

-Walks into station at 5:02
-Checks schedule, oh great next trip is at 5:08.
-5:08, no bus goes by
-Checks schedule, next trip says 5:15
-5:15, no bus goes by
-Stands at the station like an idiot, wondering what the hell is going on frustrated
-5:21, 3 buses arrive, some empty, some at crushload.
-Arrives to work/home/whatever function late because of OC
     
     
  #3923  
Old Posted Oct 20, 2016, 7:30 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,834
There's no reason why they couldn't do that with the bus. Even other cities in Ontario have that feature (Kitchener-Waterloo, for example).
     
     
  #3924  
Old Posted Oct 20, 2016, 8:29 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
The big problem currently is the downtown stations have umpteen billion buses leaving the station to every corner of the city, so by the time you figure out when the bus you want is coming, 3 buses have gone by. With LRT, there will only be 2 destinations initially (and up to 4 after stage 2), so it will be very easy to see when your train is coming. Once you get to the transfer station, only the buses that go to that station will be listed. Initially Tunnies Pasture will still be a bit chaotic, but once stage 2 is complete, things should be reasonable at all stations.
     
     
  #3925  
Old Posted Oct 20, 2016, 11:42 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
One more tidbit that came up in the meeting that didn't make the papers: they confirmed the dwell times of trains in stations: between 7-15 seconds, depending on ridership levels, with the exception of Parliament and Lyon at the height of rush hour which will be about 20-30 seconds.
__________________
"It is only because the control of the means of production is divided among many people acting independently that nobody has complete power over us, that we as individuals can decide what to do with ourselves." - Friedrich Hayek
     
     
  #3926  
Old Posted Oct 20, 2016, 11:45 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,556
The train is coming: LRT track testing to start in November

Matthew Pearson, Ottawa Citizen
Published on: October 20, 2016 | Last Updated: October 20, 2016 5:52 PM EDT


Just weeks from now, Alstom Citadis Spirit trains will begin rolling along a stretch of track between Blair station and the Belfast Yard plant where they are being assembled.

They won’t pick up passengers just yet but instead will use the coming months to test and troubleshoot the fully automated LRT system in advance of its opening in 2018.

The latest milestone — expected sometime in November — in the construction of the $2.1-billion Confederation line, comes near the end of a big year for the project during which construction began or continued at all 13 LRT stations. Necessary detours were put in place to shut down a stretch of the Transitway for the conversion to rail. And, if all goes well, there will be the completion of a 2.5-kilometre tunnel underneath downtown.

Matthew Pearson brings us the latest on Ottawa’s largest construction project.


The Citizen gets a sneak peek inside the construction of the LRT lines.

Italian ingenuity

How do you build a tunnel underneath a busy Via Rail line without disrupting train service?

Ask some Italians.

Rideau Transit Group, Ottawa’s LRT builders, hired an Italian firm famous for what it calls the Verona system.

This involves building a concrete box culvert adjacent to an underpass, moving it on a horizontal sliding slab and putting it in place with hydraulic jacks. The method supports and reinforces railway tracks and allows trains above to travel at up to 80 km/h.

It’s a popular method because it ensures construction stays on schedule and means little to no interference to train traffic, said Roger Schmidt, RTG’s technical director.

The only real disruption to Via service between Montreal and Ottawa was a single overnight closure that stretched into the next morning, Schmidt said.

Tunnel graffiti

Some walls in the tunnel that connects Confederation line to Belfast Yard — officially known as the MSF Connector — are already adorned with graffiti.

In one spot, a fluorescent pink tag, outlined in black and blue paint, stands out on the sombre concrete canvas.


Ottawa Light Rail Construction is warning people to stay out of tunnels and off the tracks as it prepares to begin testing new LRT trains and systems.

O-Train Construction, the recently renamed city department overseeing the LRT project, has already sent out a memo to city councillors, schools and other agencies to warm them that trains will soon be using the tracks and that the overhead wires will soon be live.

“We’re concerned people are wandering around on the tracks,” said Steve Cripps, head of O-Train Construction. “The graffiti just highlights the need to let the public know what’s coming.”

The ties that bind

So far, about seven kilometres of rail have been laid in Belfast Yard and along the MSF Connector, and another nine kilometres have been laid along the main line between Blair station and points west. Keep in mind the line is twinned, so this actually represents about 4.5 kilometres of rail out of a total 12.5 kilometres.


St. Laurent Station under construction.

Rails are fastened in two ways. The traditional method involves attaching rail to concrete ties that sit on heavy gravel, which is called ballast.

There’s also direct fixation, which is when rails are drilled directly into concrete. This is common in the MSF Connector, the downtown tunnel and St. Laurent station.

Rail comes in 18-metre long sticks. They are pulled into place by a machine and then seamlessly welded together in the field, Schmidt explained.


Travelling above and below ground from the MSF Connector area on Belfast Road east to what will become the St. Laurent Station.

Made-in-Ottawa trains

Inside Belfast Yard, about four dozen Alstom workers are busy building trains.

Since the first one rolled off the line in July, two more have been completed. And work is underway on three others.

The goal is to complete two per month until all 34 are done.

Building trains in the same facility where they will eventually be maintained and stored overnight isn’t common for LRT projects, but it’s pretty ingenious, says Schmidt. “It’s a good innovation.”

The early usage of the Belfast Yard MSF as an assembly facility encourages the entire project team to consider the vehicle as an integral project component rather than a separate element that is added later by others, he explained. “It makes a lot of sense to do testing in the same city in which it will eventually operate.”

The trains used on Vancouver’s Canada line were built in Korea, and trains used on the city’s Millennium line were built off-site in Burnaby, a suburb of Vancouver, Schmidt said.


Belfast Road east to what will become the St. Laurent Station.

Rideau delay

Only about 50 metres of tunnelling remained when a massive sinkhole opened up on Rideau Street on June 8, throwing a wrench into the plans.

Work has resumed, but progress is slow. Crews are tunnelling from east to west, starting in the Rideau station cavern and working toward Sussex Drive. They’ve progressed about 20 metres, Cripps said.

In the area where the sinkhole was, RTG is using extra ground stabilization techniques, such as jet and compaction grouting. The technique involves injecting grout into the ground to make it more stable for when crews are tunnelling through, as well as for the road above.

“That’s the work that’s been going on on Rideau Street for the last week or so at night, when Rideau Street is shut down,” Cripps said.

Nightly closures began Oct. 3, but the street, as of Wednesday at 8 p.m., is closed completely between Sussex Drive and Dalhousie Street until the end of the year.

Were it not for the sinkhole, the entire 2.5-kilometre tunnel would be done already. It’s now expected to be done by the end of the year, Cripps said.

“It’s obviously something we’re watching and we’re working closely with RTG on, but they’ve committed to us to take all reasonable measures to get themselves back to where they need to be and keep themselves on schedule,” Cripps said.

It’s important to remember, he added, that work on the balance of the tunnel — including at the three underground stations — has continued.

Stations rising

Blair and Cyrville stations in the east end definitely look like stations. And in early 2017, the same will be true for stations at the other end of line — Tunney’s Pasture, Bayview and Pimisi.

“You’ll see them rising from the ground and looking more like stations similar to what Blair and Cyrville and Tremblay look like today,” said Cripps.

Construction at all stations is scheduled to be complete by the end of 2017.

[email protected]
twitter.com/mpearson78

http://ottawacitizen.com/news/local-news/the-train-is-coming-lrt-track-testing-to-start-in-november
     
     
  #3927  
Old Posted Oct 21, 2016, 12:14 AM
TMA-1's Avatar
TMA-1 TMA-1 is offline
Registered User
 
Join Date: Jul 2006
Location: Ontario
Posts: 298
Yellow

I am not now, nor have I ever been, a rail nut. So. What's the yellow thing just past the upper VIA station access road?



ottawa rail D828160
by Chuck Clark, on Flickr
     
     
  #3928  
Old Posted Oct 21, 2016, 12:24 AM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,834
Quote:
Originally Posted by 1overcosc View Post
One more tidbit that came up in the meeting that didn't make the papers: they confirmed the dwell times of trains in stations: between 7-15 seconds, depending on ridership levels, with the exception of Parliament and Lyon at the height of rush hour which will be about 20-30 seconds.
Seven seconds seems awfully short.
     
     
  #3929  
Old Posted Oct 21, 2016, 12:34 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,556
Quote:
Originally Posted by TMA-1 View Post
I am not now, nor have I ever been, a rail nut. So. What's the yellow thing just past the upper VIA station access road?
A rail tamper?
     
     
  #3930  
Old Posted Oct 21, 2016, 12:38 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,556
Construction Update
Week of October 17


At Tremblay Station, which will serve as a vital connection to Ottawa’s VIA Rail Station, crews complete structural steel. At Parliament Station west entrance, the head house takes shape and concrete work continues for the station’s entrance.



Tunney's Pasture Station foundation work

West Stations


Tunney’s Pasture Station: Crews continue building the station foundation including installation of rebar for station footings and initial caisson work.

Bayview Station: Ground improvement activities continue during the day and overnight as part of work in the area. Crews install rebar and formwork for the station walls. Duct bank and grade beam installations are ongoing.

Pimisi Station: Construction of the station walls and lower concourse level continues; activities include waterproofing and concrete work.



Parliament Station east entrance line drilling

Central Stations


West Portal: Excavation for the ramp concludes and preparation for guideway work continues.

Lyon Station cavern: Work continues at the concourse level; activities include shoring, rebar and formwork installation. Shotcrete final lining work continues in the east transition. Arch final lining pours are ongoing.

Lyon Station west entrance: Crews install rebar, formwork and pour the escalator pit and station walls.

Lyon Station east entrance: Station wall and column work is ongoing; crews install rebar and pour concrete. Crews mobilize to begin structural steel installation later this week. At the east vent shaft, rock removals are ongoing in preparation for waterproofing and concrete work.

Parliament Station cavern: The station continues to take shape; activities include rebar installation and concrete pours for the station slab and L-walls. Mechanical and electrical work continues and crews waterproof the station arch.

Parliament Station west entrance: Crews install rebar and pour concrete for the station slab, stairs and escalator walls. Structural steel installation is finalized. At the east vent shaft, crews continue hoe ramming and rock removal during the weekend.

Traffic restrictions on Queen and O’Connor streets remain in effect.



Rebar installation in Rideau Station cavern

Rideau Station cavern: Crews waterproof the station invert and arch in preparation for concrete work. The station continues to take shape with rebar installation and arch concrete pours. Mechanical and electrical work is ongoing.

Rideau Station west entrance: Crews install rebar and falsework in anticipation of pouring the roof slab.

Rideau Station east entrance: Crews finalize formwork in anticipation of significant concrete pours by the end of the week.

Rideau Street will close nightly to all vehicular traffic to permit works to advance.

uOttawa Station: Construction of the platform slab continues; activities include rebar installation and concrete pours. Electrical work is ongoing.

East Portal: Excavation of the ramp continues and crews install whaler beams as part of reinforcement work.



Masonry work at Hurdman Station

East Stations


Lees Station: Work on the raft slab continues; activities include rebar and formwork installations. Electrical installations are also ongoing.

Hurdman Station: Crews begin structural steel and continue masonry installation. Construction of the bus operator’s building is ongoing.

Tremblay Station: Crews continue installing formwork in preparation for concrete pours. Structural steel installation is finalized and work on the roof begins.



Structural steel installation at Tremblay Station

Tremblay Station: Crews continue installing formwork in preparation for concrete pours. Structural steel installation is finalized and work on the roof begins.

St-Laurent Station: The station continues to take shape; crews prepare to install escalators, elevators and structural steel. Work on the hydro room is ongoing.



Forming railbeds and roof work at Cyrville Station

Cyrville Station: Crews work on the station roof, structural framing and elevators.

Blair Station: Work on the station roof is being finalized. Crews install exterior wall panels and the soffit. At the bus operator’s building, electrical installations continue. Removals are being completed as part of work on the permanent bus loop.



Reinforcements installed in the last section of the running tunnel

Tunnel Excavation and Support


Excavation of the running tunnel continues and crews install reinforcements.



Backfilling on the guideway east of Tunney's Pasture Station

Guideway


Tunney’s Pasture Station to West Portal: Construction of the guideway continues; crews backfill and finalize the installation of Overhead Catenary System foundations during the day and overnight. From Merton Street to West Portal, crews excavate, backfill and install ballast. Trackwork is ongoing in sections and includes distressing rail.

Mann Avenue Bridge to west of Tremblay Station: Guideway work occurs in sections; crews complete sewer work and install duct banks, fencing and ballast. Trackwork is ongoing from Rideau River Transitway Bridge to Tremblay Station.



Girders installed on the Mann Avenue Bridge

Other Activities


Bayview Bridge: Reconstruction of the bridge is ongoing; crews pour the concrete overlay. The bridge is expected to be completed by the end of 2016.

Mann Avenue Bridge: Bridge reconstruction progresses with crews working during the day and overnight. Bridge work will continue until spring 2017.



Upcoming Construction Activities

In the coming weeks, the following construction activities are scheduled to occur:
  • Tunney’s Pasture Station work requiring right turn lane restriction.
  • Installation of traction power sub station on the guideway near Tunney’s Pasture Station and elsewhere along the alignment.
  • Lyon Station HVAC and west vent shaft work resumes.
  • Work begins at the Rideau Station HVAC shaft; traffic pattern adjustments are required. [link to notice]
  • Ottawa Station work requiring intermittent closures of the pedestrian tunnel.
  • Structural steel installation at uOttawa Station.
  • Mann Avenue Bridge work and overnight lane closures.
  • Vehicle testing and Overhead Catenary System will be energized in phases along the guideway between Belfast Yard and Blair Station.

http://www.ligneconfederationline.ca/construction/construction-update-95/
     
     
  #3931  
Old Posted Oct 21, 2016, 1:45 AM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by rocketphish View Post
Sneak peek: five things you’ll find in the new light rail stations
From cafes and kiosks to digital schedule boards, the new light rail stations are far from your basic O-Train platform.

By: Emma Jackson
Metro Published on Wed Oct 19 2016


The 13 light rail stations opening in 2018 aren’t your regular O-Train platforms. Far from it: these state-of-the-art buildings will be packed with all-new integrated signage, ticket booths, digital schedules and, if you’re lucky, cafes and convenience stores. Check out the coolest features transit commission approved at its meeting Wednesday.

Take a walk

Using transit can be disorienting if you don’t know where you’re going, so staff have developed localized maps for each station that show passengers what’s within five minutes walking distance of the exit. Particularly in the downtown core, this will help tourists (and inexperienced residents) figure out which way is up and how to access major landmarks, staff said.

http://www.metronews.ca/news/ottawa/2016...find-in-the-new-light-rail-stations.html
This is probably the single best thing a transit authority can do. Knowing what is within a 5 minute walk will help everyone.

Looking forward to visiting Ottawa and riding the line with this available.
     
     
  #3932  
Old Posted Oct 21, 2016, 2:04 AM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
Quote:
Originally Posted by acottawa View Post
Seven seconds seems awfully short.
Seven seconds is probably what will be seen at low ridership stations like Cyrville or Iris in the off peak.

It may seem really short to us given that we're used to buses which take a long time to load, but it's totally normal for rail transit systems. In Toronto subway and Montreal metro dwell times are typically in the 7-15 second range as well.
__________________
"It is only because the control of the means of production is divided among many people acting independently that nobody has complete power over us, that we as individuals can decide what to do with ourselves." - Friedrich Hayek
     
     
  #3933  
Old Posted Oct 21, 2016, 3:18 AM
Beedok Beedok is offline
Exiled Hamiltonian Gal
 
Join Date: Jun 2012
Posts: 6,793
Quote:
Originally Posted by acottawa View Post
There's no reason why they couldn't do that with the bus. Even other cities in Ontario have that feature (Kitchener-Waterloo, for example).
Thunder Bay even tries. (And honestly the displays use a better intereface than Ottawa's tend do, with a larger and more visible font.)

Plus trains can get delayed too. I've been on the Toronto subway and had it just sit at a station for a few minutes or travel at 1/4 the usual speed between stations (sometimes in the same trip) making getting somewhere on time quite nail biting.
     
     
  #3934  
Old Posted Oct 21, 2016, 3:34 AM
Acajack's Avatar
Acajack Acajack is offline
Gros Méchant Loup
 
Join Date: Aug 2006
Location: Province 2, Canadian Empire
Posts: 72,949
Quote:
Originally Posted by acottawa View Post
There's no reason why they couldn't do that with the bus. Even other cities in Ontario have that feature (Kitchener-Waterloo, for example).
STO has these electronic boards in Rapibus stations.
__________________
Loin des yeux, loin du coeur.
     
     
  #3935  
Old Posted Oct 21, 2016, 11:00 AM
Horus's Avatar
Horus Horus is offline
I ask because I Gatineau
 
Join Date: Jul 2013
Location: Aylmer (by way of GTA)
Posts: 1,213
Quote:
Originally Posted by 1overcosc View Post
One more tidbit that came up in the meeting that didn't make the papers: they confirmed the dwell times of trains in stations: between 7-15 seconds, depending on ridership levels, with the exception of Parliament and Lyon at the height of rush hour which will be about 20-30 seconds.
Quote:
Originally Posted by acottawa View Post
Seven seconds seems awfully short.
30 seconds will seem like an eternity
     
     
  #3936  
Old Posted Oct 21, 2016, 1:35 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by rocketphish View Post
A rail tamper?
Correct.
I had seen it at Blair when they were jusat starting...
has a huge pantograph rail alignment sensor out front to straighten the rail and ties, and then shakes them into place. Then passes over it several more times to settle them into place. Back and forth several times. There was a pic previous on this or an associated thread of it.
EnJoy.
     
     
  #3937  
Old Posted Oct 22, 2016, 3:10 PM
Mikeed Mikeed is offline
Registered User
 
Join Date: Jun 2013
Posts: 377


That trench is wide! Considering it's just a straight line, running trench. No wonder they're adding a traction power station there. I do wish this system was being built with express trains in mind. I feel like an under appreciated asset was the already wide right of ways for BRT though the trenched transitways, and at stations.

Though, probably some significant disadvantages with this. But again, let's not forget this isn't a 'Cadillac' system. Yes, they roughed in fully automated trains for some time in the future. But I think it would be compelling to consider a fully automated system with express trains to the suburbs.

Yes, the oft mentioned suburban focus of Ottawa is often criticized, but ultimately most of the growth is happening in the suburbs. Making the LRT competitive means making it fast and stopping at every stop on these long lines is going to become and issuing in getting more people to take transit.
__________________
Long time reader.
Seldom post.
     
     
  #3938  
Old Posted Oct 22, 2016, 6:06 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Good Day..
actually, what you see here is the eastern end of the station reserved area for the 120m platforms, and the bed for the crossover switches to the east of that. As well, (given that we have no actual real plans for the stations beyond the 2011 prelims) they have to reserve space for infrastructure - power station and access road (tho not well stated or found, there is a requirement for a service road to all TPSSs), driver's bldg, conduits, power feeds, water, sewage, bathrooms, side platforms, stairs, elevators, escalators (i hope ?). Also not well documented is that they place TPSSs at each end of the line so as to accommodate the local load (as they do at the MSF). Plus... they have to accommodate the drainage/sewage tunnels just (!just!) barely underneath the platforms and running way. They cannot be moved or modified (contract). All that put together, and it will be interesting to see the true layout of Tunney's Station.
(Aside... we have a better idea of Stage2 stations and guideway than we do Stage1. Sheesh!)

And stopping at every station is truely the only real way to run this type of railroad. the very very few times that there would be no one getting on or off does not rate the added complications of trying to detect that 'demand'. High use stations are high use. Low use stations will simply have low dwell times. This statistic is easily incorporated into schedules (yeah, i know, OC, but even so).

EnJoy.
     
     
  #3939  
Old Posted Oct 23, 2016, 12:57 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by PHrenetic View Post
And stopping at every station is truely the only real way to run this type of railroad. the very very few times that there would be no one getting on or off does not rate the added complications of trying to detect that 'demand'. High use stations are high use. Low use stations will simply have low dwell times. This statistic is easily incorporated into schedules (yeah, i know, OC, but even so).
I think you missed the point. The suggestion isn't that we have some sort of on demand stop but have an extra track so that while a local train is stopped picking up passengers, an express train is whizzing by, stopping only at major stations.

The problem with this approach is without quadruple track for the entire length, the express trains would have to merge onto the other tracks at some point, and scheduling that merge while keeping the minimum spacing without causing extra delays would be difficult.
     
     
  #3940  
Old Posted Oct 23, 2016, 1:11 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,834
Quote:
Originally Posted by Mikeed View Post

Though, probably some significant disadvantages with this. But again, let's not forget this isn't a 'Cadillac' system. Yes, they roughed in fully automated trains for some time in the future. But I think it would be compelling to consider a fully automated system with express trains to the suburbs.

Yes, the oft mentioned suburban focus of Ottawa is often criticized, but ultimately most of the growth is happening in the suburbs. Making the LRT competitive means making it fast and stopping at every stop on these long lines is going to become and issuing in getting more people to take transit.
The problem is the system was designed for inside-the-greenbelt use and the choice of technology and design of the system reflects that. The decision to extend it outside of the greenbelt creates problems.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 3:37 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.