Quote:
Originally Posted by CharlesCO
I think I've said this before on here, but I just don't understand how the AGTS is now deemed unsuitable for theoretical Concourses D and E to the north of the current concourses when the original airport design accounted for those two concourses to eventually be built and mirror the existing concourses' designs. The idea of concourses or a separate terminal to the south of the current one just sounds like a mess.
|
As I understand it, Concourses D and E would require additional AGTS capacity that was known all along but was left for future Generations to figure out how to do. Of course capacity can be added but after analyzing the possibility and how much it would cost they have come up with a different game plan.
Reading from the most recent Master Plan update in 2012 and trying to understand and connect different dots this is what I believe.
Starting in 2015 through 2020 it feels like they're rebuilding the existing airport. Coolers, boilers, pipes, drains, conveyors for escalators and moving walkways, drainage and erosion correction and lots and lots of concrete replacement which is ongoing. You name it, they're doing all the nuts and bolts stuff.
Starting in 2021 through 2030 is when they're looking at expansion projects, the phasing of which will depend on this and that. Plans always anticipated adding more terminal space. Jeppesen Terminal is not considered to have adequate capacity to handle the 2030 demands.
It was always anticipated that new terminal space would be added to the south. Apparently that's still the plan but their new preferred option is NOT to build Concourses D and E but to instead build concourses East and West out from the new terminal. This way they can build a new AGTS at a much lower cost. They've redesigned the layout of the new terminal with this in mind. One advantage of this is that for unanticipated additional capacity needs can be met by just adding another terminal pod to the south again. While I'm sure they'll be nice it sounds like Jeppesen will remain the "signature" terminal.
For everything they're looking at a 6-year enabling period. Construction periods would depend on the specific projects. The new terminal will have its own separate road system, ramps and parking etc.