LRT proposal now includes east end underpass
Hamilton Spectator
By Matthew Van Dongen
http://www.thespec.com/news-story/6849268-lrt-proposal-now-includes-east-end-underpass/
Project designers are now proposing to build a pricey King Street underpass to allow Hamilton's LRT line to travel under an east end industrial rail spur.
The city's original environmental assessment for light rail transit envisioned a negotiated agreement with Canadian Pacific Railway to allow LRT vehicles to drive overtop the industrial spur that crosses King Street near East Bend Avenue.
Those talks, however, have not yielded a workable agreement, said city LRT point person Paul Johnson. "We were looking at a variety of options, but at this point the latest proposal is to look at going under the rail spur," he said.
Johnson declined to discuss the specifics of the negotiations, but said both railway requirements and Metrolinx concerns about rapid, reliable LRT service timelines played into the decision to pitch a Plan B.
The Spectator has yet to receive comment from CPR officials.
The current, tentative proposal would see a LRT-only underpass at the spur. Car traffic would continue to drive over the rail spur at a controlled crossing, as it does today.
Johnson conceded digging under the tracks would be "a bigger cost" than simply negotiating a surface crossing, but added no firm cost estimate is yet available.
The news comes as the city continues negotiations with landowners over a preferred LRT maintenance facility site in the west end.
While early planning suggested the facility could be built on Wentworth Street North, the latest targeted site is 15 to 20 acres of industrial land owned by McMaster University and businessperson Albert Samee near Longwood Road and Aberdeen Avenue.
The newly envisioned spur line feeding the facility would cross the Longwood bridge and dramatically shorten the distance LRT cars would have to travel from the main line to the storage facility.
Ward Coun. Aidan Johnson said he feels "joyous" about the latest plan, which he suggested could mean provincial funding to rehabilitate the aging Longwood bridge.
"My understanding is within a few years from now that bridge would need serious work to maintain it as a safe structure," he said. "This has been a huge source of stress for me."
At the same time, the councillor said the new plan also ends neighbourhood fears that the maintenance facility would be built atop popular Kay Drage Park — one of about 30 sites along the route considered so far.
Basic details about both plans are expected to be made public in LRT information sessions starting Monday evening. Slide decks used for the meetings should be posted online at hamilton.ca Monday morning.
Despite the new bridge-fixing and underpass-building costs, Paul Johnson said project planners still believe the original $1 billion budget will suffice.
"If (Metrolinx planners) thought it would break the bank, they wouldn't be considering it," he said.