Originally Posted by GilmoreStation
It does not seem possible for Shape to complete the first tower by the end of the first half of 2018. When is the more likely scenario for completion?
|
Lets give an optimistic week a standard floor plate, thats roughly 52 weeks right there.
They still haven't reached standard floor plates, and in fact need to complete the amenities floor, etc.
Lets give that a month.
So;
- Start standard plates October 2016
- Top out October 2017
- Glazing finishes say December 2017
- 6 months for interior finishing?
- Finish around end of Summer 2018?
Throw in a delay or two, plus the fact retail is being prioritized and End of 2018 doesn't seem unreasonable.