Some new info regarding Cressey's
King's Crossing development at Kingsway & Edmonds. They've added a bit of height (not extra floors) to each of the towers. Also, they're asking for an extra floor of office space:
Quote:
|
slightly increase the floor plate of the office building and add an additional level, increasing office floor space to 7,918 m^ (85,226 sq.ft.). As there has been some interest from post-secondary institutions in locating within the office building, the applicant is also proposing that the P6 Regional Institutional District be included in the CD zoning guidelines.
|
https://burnaby.civicweb.net/filepro/documents/?preview=16704 (page 4)
-------------------------
Here's the site plan for Millenium's
Étoile development. We have very little info so far, so I figured this would be helpful:
https://burnaby.civicweb.net/filepro/documents/?preview=16698 (page 8)
^Note the curving road along the southern frontage. That's currently an intersection where you have to turn left from Douglas Road onto Goring Street. As I noted in an earlier post (pic below), Dawson/Douglas/Goring will eventually become a single through road parallel to Lougheed. The current Douglas Road rail crossing will also eventually be closed so you will need to make a right turn to continue along Douglas for now.