Quote:
Originally Posted by Daveography
Stats from the pour, via Stantec:
- Raft sits on 39 piles, 1.8m in diameter, deepest of which runs 80m into the ground (a separate source indicates that these may be the deepest ever used in an office tower in North America)
- Typically raft slabs act as one big footing and bear directly on the soil, but because of the height and loading of this tower, piles were also needed
- 760 tonnes of rebar was used for the raft slab
- 2800 cubic metres of concrete was used
- Raft Dimensions are 24m wide x 36m long x 3m tall
- Pour start time 5am, end time 3pm - roughly 10 hours
- About 311 concrete trucks were needed
- Pour rate was ~300m3/hr; ~33 trucks every hour
- Largest continuous pour in the city's history
|
yes, a large pour, but not the largest continuous pour in the city's history...
not to be picky or to make claims (i don't know about manulife or canada place or some of the large pours in the initial construction of the shaw conference centre) but the epcor tower raft slab was roughly 140' x 100 ' x 12' and took almost 4,000 cubic metres of concrete in a single pour that started at 6:00 pm on a friday and wasn't completed until the following afternoon. 120 men, 35 concrete trucks in a continuous loop from plant to site and 5 concrete pumps working non-stop with an on-site diesel refueling truck to keep them fueled.