Two central library plans in works in case Archives deal falls through

Jon Willing, Ottawa Citizen
Published on: March 7, 2016 | Last Updated: March 8, 2016 8:03 PM EST


The Ottawa Public Library, still without a firm deal with Library and Archives Canada on a joint project, has increased its workload to protect the city’s interests in case a development pact with the national institution falls through.

The library board directed staff on Tuesday night to work on plans for both a stand-alone central library and a super library involving the national archives. The board and the archives signed a letter of intent to explore a partnership, but a firm deal could be still months away.

Library chief executive Danielle McDonald said she hopes to establish by the end of the year whether the OPL will work with the archives on the project. In the meantime, staff and consultants will work on plans for both scenarios.

McDonald said it’s not quite double the work, “but it is more than one.”

The library will draw on the expertise of consultants to decide if or when the OPL should abandon the partnership with the archives. The library wants to break ground on a new central library, with or without the national institution, by the second quarter of 2018.

The board heard from deputations urging trustees to keep the central library project transparent and listen to the public when it comes to potential locations. Community group Bookmark the Core made another presentation to the board, questioning the notion that Ottawa’s downtown is moving west toward LeBreton Flats.

The two LeBreton proposals, each pitching a new municipal library, threw a curveball at the OPL when it comes to managing public relations. There’s a perception that building a library at LeBreton is a done deal, which has prompted library board chair Tim Tierney to emphasize on several occasions that a location hasn’t been determined.

“I love the passion. I think the passion is great, but at the same time there is a process,” Tierney said Tuesday.

Tierney repeated that the LeBreton redevelopment process, which is run by the National Capital Commission, and the OPL’s central library project are independent of each other. Any library proposal for LeBreton would need to fall within the OPL’s tendering process, he said.

OPL staff continue to work on the requirements for a new central library. McDonald said the OPL is “refining” the initial estimate that a new municipal library would require 132,000 square feet of space. The OPL is also ramping up its public engagement efforts on the project. A website could be launched next month and staff are planning a town hall.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/uncategorized/o...-meets-discusses-central-library-project
Reply With Quote
     
     
  #482  
Old Posted Mar 9, 2016, 3:48 AM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,896
'Ottawa: Think Small, Build Smaller' Isn't there a sign on the way into the city with that slogan?
Reply With Quote
     
     
  #483  
Old Posted Mar 9, 2016, 4:08 AM
Buggys Buggys is offline
Registered User
 
Join Date: Dec 2012
Location: Ottawa
Posts: 659
That sign is too small to notice sometimes.
Reply With Quote
     
     
  #484  
Old Posted Mar 9, 2016, 4:42 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,116
Quote:
Originally Posted by rocketphish View Post
Two central library plans in works in case Archives deal falls through

Jon Willing, Ottawa Citizen
Published on: March 7, 2016 | Last Updated: March 8, 2016 8:03 PM EST


[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/uncategorized/o...-meets-discusses-central-library-project
Talk about setting yourself up for failure.
Reply With Quote
     
     
  #485  
Old Posted Mar 9, 2016, 5:37 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,918
Quote:
Originally Posted by J.OT13 View Post
Talk about setting yourself up for failure.
Seems like a prudent strategy. The feds don't seem to know what they want, want to impose a bunch of restrictions and don't seem to have political approval (or funding). If it works out then fine, but having a plan b seems sensible.
Reply With Quote
     
     
  #486  
Old Posted Mar 18, 2016, 5:08 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
Residents want openness on selection of a central library site
Carleton prof worries Lebreton Flats selection a fait accompli

By Jennifer McIntosh
Ottawa East News, Mar 11, 2016


A Carleton professor is calling for an impartial committee to select a site for the city’s new central library.

Paul duBellet Kariouk, who is also an architect, said the committee should be made up of experts and librarians from other municipalities that have a landmark central library – such as Vancouver, Montreal or Halifax.

Kariouk was one of seven delegations that spoke to the library’s board during its meeting on March 8.

Library board chair Tim Tierney said the city’s process follows best practices.

“We have an integrity commissioner,” he said. “As we go through the consultation components, we will then look at best practices that were used in Halifax and Montreal.”

Tierney said when the city releases the requests for proposals, that is when a site will be named.

“There is no site selected, I have to stress that,” he said.

Kariouk worked with Friends of Lansdowne to fight the deal with Ottawa Sports and Entertainment Group and said he worries about a similar one-source deal with the new library branch. He said he worries that a Lebreton Flats site is a done deal, citing rumours that the city has done soil testing at the location.

Tierney said it’s far from a done deal.

The site at 557 Wellington St. is the only city-owned of the nine identified as potential spots for the central branch of the library.

Tierney confirmed that there had been soil testing at that site.

“The understanding is we have to do it as part of the city process,” he said. “It’s not to say we are choosing 557 Wellington St. There will be plenty of consultations around components of the library. And we are waiting to roll out the plan, it will come out in the next couple of months and people will be advised how they can participate.”

The Wellington Street site is the only one the city has done soil testing on, Tierney said.

Kariouk said it doesn’t make sense for the city to choose a site west of Bronson Avenue. He said the population won’t increase to the west for at least another 10 years.

“All we have to do is look at the War Museum,” he said. “It’s a beautiful facility, but the amount of traffic that goes through it is negligible because there’s nothing else around there. Maybe there will be more there in 10 years, but they told us that 10 years ago.”

Kariouk isn’t the only one calling foul on the site selection process.

Jevone Nicholas, who spoke on behalf of Bookmark the Core, said he wants to see the new library closer to the existing Metcalfe Street branch.

“It’s about access,” he said, adding people should be able to walk or take transit to the central branch – and visit it as part of things they were going to do.

That makes more sense in the downtown core, he said.

Five of the library’s nine identified potential sites are located west of Bronson Avenue, and Nicholas said users won’t be able to access those locations as readily as they do now.

Nicholas said he’s glad to see the commitment to open houses and town halls.

Right now the city is running two plans concurrently, one would be to build a standalone library and one to do a joint project with Library and Archives Canada.

“By the end of this year we would be in a position to know whether we are partnering with them or going on our own,” Tierney said.

The Ottawa Public Library will launch a project website in the spring in an effort to keep residents in the loop.

“The good part is people are very passionate about this library,” Tierney said.

- with files from Michelle Nash

Jennifer McIntosh is the political reporter for Metroland Media's Ottawa papers. She can be reached at [email protected]. Follow her on Twitter and Facebook.

http://www.ottawacommunitynews.com/news-...-on-selection-of-a-central-library-site/
Reply With Quote
     
     
  #487  
Old Posted Apr 8, 2016, 1:24 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
Library board to launch site selection for new central branch

Matthew Pearson, Ottawa Citizen
Published on: April 7, 2016 | Last Updated: April 7, 2016 2:31 PM EDT




An expanded search could soon begin for a place to build Ottawa’s new central library.

The Ottawa Public Library board will be asked Tuesday to approve the launch of a formal site selection process, which includes a callout for potential, yet-to-be identified locations for either a stand-alone central branch or a joint facility to be shared with Library and Archives Canada.

This comes after the library board directed staff last month to work concurrently on plans for a stand-alone central library and a super library involving the national archives. The board and the archives signed a letter of intent to explore a partnership, but a firm deal could be still months away.

The library board has said it wants to build the new central branch in the downtown area, roughly bounded by the Ottawa River, King Edward Avenue, Lisgar Street and the Trillium LRT line.

A staff report says the site selection process must begin soon in order to locate the best possible site within this area.

The city’s real estate partnerships and development office will begin by creating an inventory of potential sites and evaluate them based on criteria to be approved by the board later this year.

In addition to several city-owned properties and those subsequently identified in recent months, the city will issue an open call through MERX and newspaper advertisements for other potential sites. In order to be considered, the sites must have a minimum area — 40,000 square feet for the OPL stand-alone and 64,500 square feet for the joint option — and be able to meet the project schedule.

Potential sites can be publicly or privately owned, the report says.

The reference to “project schedule” is noteworthy because both redevelopment proposals for LeBreton Flats include a library. But library chair Tim Tierney has said previously that the LeBreton process, which is run by the National Capital Commission, and the OPL’s central library project are independent of each other and that any library proposal for LeBreton would need to fall within the city’s timelines.

By the end of this year, the library board will receive a business case that includes recommendations on the potential partnership, site selection and financial framework for the project.

If council signs off on that plan, the report says there would be further public consultation followed by design and construction.

The groundbreaking would be in the spring of 2018 and the official opening would follow in 2020.

[email protected]
twitter.com/mpearson78

http://ottawacitizen.com/news/local-news...ch-site-selection-for-new-central-branch
Reply With Quote
     
     
  #488  
Old Posted Apr 22, 2016, 4:57 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
Ottawa Public Library announces consultations on central library project

Jon Willing, Ottawa Citizen
Published on: April 22, 2016 | Last Updated: April 22, 2016 12:11 PM EDT


The Ottawa Public Library will hold two consultations May 16 to gather advice on where a new central library should be located.

The two-hour sessions at Ottawa City Hall will be at 4 p.m. and 7 p.m. in Jean Pigott Place.

The library recommends people register for the event at a refreshed central library project website.

The library says it will also collect feedback through an online questionnaire in June.

Library management is working with the city’s real estate branch until June to build a list of possible sites for a new central library.

The city doesn’t know yet if it will partner with Library and Archives Canada to build a super library. Both organizations are interested in exploring the opportunity, but in the meantime, municipal library trustees have directed staff to prepare game plans for both a standalone library and a joint project.

The library will also make an open call for landowners to suggest potential sites.

Armed with public feedback and a list of properties, the library will develop evaluation criteria for the board to approve in July. From there, staff will test the sites against the board-approved criteria and develop a shortlist. A recommended location, along with a plan to deliver the project, will be in front of the board by the end of 2016.

Refurbishing the current central library at Laurier Avenue and Metcalfe Street is out of the question. The library board wants a new one.

While there is a bit of controversy over what “central” means on the downtown map, the library board has already defined the area: The Trillium Line O-Train to the west, the Ottawa River to the north, King Edward Avenue to the east and a jagged border of Wellington Street, Albert Street, Gloucester Street and Lisgar Street to the south. Ideally the library would establish a central facility close to a Confederation LRT station.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news...consultations-on-central-library-project
Reply With Quote
     
     
  #489  
Old Posted Apr 29, 2016, 4:55 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
New central library at redeveloped LeBreton still a possibility

Matthew Pearson, Ottawa Citizen
Published on: April 29, 2016 | Last Updated: April 29, 2016 11:10 AM EDT


The successful Ottawa Senators-backed bid to redevelop LeBreton Flats included space for a new central public library, but that won’t become a reality unless the group formally proposes the site as part of a call for potential locations in the downtown area.

RendezVous’s IllumiNation LeBreton plan sees a library placed adjacent to the NCC’s LeBreton Flats property, on the northeast corner of Albert and Booth streets — a stone’s throw from the future Pimisi LRT station.

But because the site in question, which is jointly owned by the NCC and the city, falls outside the area included in the NCC’s recent competition for redeveloping LeBreton Flats, that part of the bid wasn’t included in the adjudication.

It could, however, still be considered by the city.

The Ottawa Public Library board approved the launch of a formal site selection process earlier this month, which includes a call for potential locations for either a stand-alone central branch or a joint facility to be shared with Library and Archives Canada.

In a statement circulated after the NCC announced the successful bid on Thursday, the board invited all prospective proponents to “follow the proper process that the Ottawa Public Library has initiated to evaluate potential sites and find the best possible location for the new flagship Ottawa central library in Ottawa’s central area.”

The library board has said it wants to build the new central branch in the downtown area, roughly bounded by the Ottawa River, King Edward Avenue, Lisgar Street and the Trillium LRT line.

The city’s real estate partnerships and development office is creating an inventory of potential sites and will evaluate them based on criteria to be approved by the library board later this year.

In addition to several city-owned properties and those subsequently identified in recent months, the city will issue an open call through MERX and newspaper advertisements for other potential sites. In order to be considered, the sites must have a minimum area — 40,000 square feet for the OPL stand-alone and 64,500 square feet for the joint option — and be able to meet the project schedule.

Potential sites can be publicly or privately owned, the report says.

The reference to “project schedule” is noteworthy because library chair Tim Tierney has said previously that the LeBreton process and the OPL’s central library project are independent of each other and that any library proposal for LeBreton would need to fall within the city’s timelines.

Stephen Willis, the NCC’s chief planner, said Thursday it could take three to five years before construction begins on LeBreton Flats, though Sens owner Eugene Melnyk said he’s eager to get moving.

Meanwhile, the library boards hopes to receive a business case that includes recommendations on the potential partnership, site selection and financial framework for the project by the end of this year.

If council signs off on that plan, the report says there would be further public consultation followed by design and construction.

The groundbreaking would be in the spring of 2018 and the official opening would follow in 2020.

[email protected]
twitter.com/mpearson78

http://ottawacitizen.com/news/local-news...redeveloped-lebreton-still-a-possibility
Reply With Quote
     
     
  #490  
Old Posted May 11, 2016, 5:06 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
OPL board approves central library public engagement strategy

Jon Willing, Ottawa Citizen
Published on: May 10, 2016 | Last Updated: May 10, 2016 5:39 PM EDT


The Ottawa Public Library board on Tuesday approved a public consultation strategy for the central library project as management develops a list of potential sites.

The library has hired consulting firm PACE to run the public engagement program. The consultant says the OPL’s consultations on the central library must show people it’s a city-building project. The consultant also notes the OPL needs to build more trust in the process of establishing a new facility.

Two public consultations are scheduled for Monday at City Hall. Anyone interested in participating is asked to register at ottawacentrallibrary.ca. The OPL will also launch an online questionnaire and assemble focus groups.

The community group Bookmark the Core is urging the library to share the results of the consultation before the library board finalizes the selection criteria for a site. The group also wants an international design competition.

“A library is a place to open up horizons to everything,” group member Jevone Nicholas told library trustees.

After receiving feedback on the location, the OPL will ask the public what should be in a new central library. There are sessions planned for June 15 at City Hall and June 22 at the Library and Archives Canada building on Wellington Street.

The OPL is still trying to determine if it should build a stand-alone facility or a super library with Library and Archives Canada.

The OPL has made an open call for potential sites. The library board will be asked to sign off on site selection criteria July 12.

The OPL wants to open a new central library in 2020.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news...ntral-library-public-engagement-strategy
Reply With Quote
     
     
  #491  
Old Posted May 17, 2016, 1:37 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
New library should go where people live, work, shop, consultation told

Megan Gillis, Postmedia
Published on: May 16, 2016 | Last Updated: May 16, 2016 9:10 PM EDT


Judging by applause, many of the people who turned out Monday to tell the Ottawa Public Library Board how it should pick a site for a new central library want it to be not just central but downright downtown.

About 125 people turned out at one the first of two public consultation sessions at city hall where, again and again, the roundtable groups concluded that the new building should be located where lots of people live, work and shop. They said it should be easily accessible on foot or walkable from public transit and parking.

There was clapping for conclusions from several that “central means core” and that means east of Bronson Avenue.

“We want a central library for today — not 50 years from now,” said Paulette Dozois, who walks to work downtown through largely-empty LeBreton Flats, now slated for redevelopment, and says the library should be near existing homes, offices and businesses.

Jack Davis, a retired school principal who walks to the current Metcalfe Street main branch almost daily, wants the library to be between Bronson and Elgin Street and adjacent to a planned light-rail station.

“That’s where the people are — the residents, the workers and the visitors,” he said. “It needs to be included in the slate of things you do at lunch hour before you jump on the LRT to go home.”

The sessions Monday included an outline of the process by Coun. Tim Tierney, chairman of the library board, and a talk by Judith Hare, the longtime chief executive of the Halifax library system who oversaw the construction of its now-iconic central branch, which attracts 6,000 visitors a day and made CNN’s list of top-10 buildings.

The Ottawa Public Library board hopes to approve the criteria for shortlisting potential sites on July 12.

People will also be able to give their feedback on how a site should be picked in an online survey this month and next.

A planned site is expected to be made public before the end of 2016, including whether to go ahead with a proposed partnership with Library and Archives Canada for a joint building, how the project will be implemented and a price tag.

If approved by the library board and city council, groundbreaking is slated for spring 2018 with an official opening in 2020.

A year ago, the library board defined the “central area” where the library would be located as bounded by the Ottawa River to the north and Wellington, Albert, Gloucester or Lisgar streets to the south, King Edward Avenue to the East and Bayview Station to the west.

But the group Bookmark the Core launched a petition Friday calling for the library to be located within an area bounded by Wellington Street to the north, Somerset Street to the south, the Rideau Canal to the east and Bronson Street to the west.

More in-person consultations on what the new library spaces and services should look like are scheduled for June 15 and 22.

http://ottawacitizen.com/news/local-news...-people-live-work-shop-consultation-told
Reply With Quote
     
     
  #492  
Old Posted May 19, 2016, 2:21 AM
ServiceGuy ServiceGuy is offline
Registered User
 
Join Date: Dec 2009
Posts: 335
Not meant to be a big Lowell Green kind of rant topic but... are libraries still actually used for books or are they more multimedia type centers these days? Honestly, I don't know because I don't use the library. Reason I ask is that best location would be determined by the end users. If it is mostly hard cover books then one location would suit but if it's mostly electronic media another would be better. I just don't know what the demographics of users are.
Reply With Quote
     
     
  #493  
Old Posted May 30, 2016, 3:02 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
Food for thought on the new central library

Phil Jenkins
Published on: May 29, 2016 | Last Updated: May 29, 2016 9:18 PM EDT


There was a day, somewhere in the late 1950s, when I took my Mum down to the Carnegie (Ottawa) Public Library on the corner of Metcalfe and Laurier and got myself a library card.

That beautiful, Nepean limestone Classical building was full of self-help books —I consider all books, fiction and documentary, to be self-help books — and I began reading my way down the shelves, a nourishing task I’m still engaged in. The library then was all about words on paper, on pages and index cards, and in the foyer was a large globe of the world that awaited me. The windows on that world were the pages of the books I read.

When I returned to Ottawa in 1978, after an 18-year absence, that building was gone, demolished three years earlier. After all, it was close to 70 years old and built to last hundreds. But it was deemed too small for the growing city. It had been replaced by a, um, structure that more resembled a police station than a library. The only thing in it remaining from the old edifice is the stained glass window with its gallery of profiles of famous writers.

My association with the library deepened when I was asked to write a history of the Ottawa Public Library that was published in 2006, the 100th anniversary. (It’s called, naturally, The Library Book.) While writing, I realized that as goes the central library and its branches, our most-used public set of buildings, so goes the city. We were late in getting one, and we needed a private/public partnership to get it built and stocked. As the city expanded, the branches popped up further and further from the central hub, and eventually a new library fit for the times was apparently required. It became evident that a new central library, one that could serve both the page and the screen, serve a city of a million potential users, and be what is now called a “destination,” was needed.

Recently I attended, at city hall, some public consultations to harvest criteria for quite where the next central library should go. The big Jean Pigott hall was full, and after the speeches and a fine, informative talk with the woman who had been responsible for much the same shift from old library to new one in Halifax, the chattering at the round tables began, and a raft of location criteria — all of them sensible — were arrived at. You can go online (ottawacentrallibrary.ca) and put in your toonie’s worth as well and keep track of the project. The next step is to provide a hit list of top-10 sites and that will eventually narrow down to one. (There is also talk of partnering with the National Library. Just talk at the moment.)

After a recent visit with a builder of some of the better-designed buildings in Ottawa, I received a message from him regarding where the new main branch should be, recalling that the winning bid for the LeBreton redevelopment made mention of a library down there. Here’s part of what he had to say:

“I would like to convince the city to open up their minds to the possibility of locating the new central library at Lansdowne Park, backing on the football stadium … on land which the city already owns. This context, located on the Rideau Canal, a World Heritage Site, could allow the building to become a serious tourist attraction and a real destination.”

Food for thought, but I’m afraid unlikely.

For myself, I favour the existing buildings of the 1913 Ottawa Technical School, now under the control of the board of education and partially empty, and fetching in an expert library builder to incorporate them into something destinational, if that is a word. But that’s just me. I’d be interested to hear from readers on this one. What next in the library’s history, and where?

Phil Jenkins is an Ottawa writer and author of a history of LeBreton Flats, An Acre of Time: The Enduring Value of Place. Reach him at [email protected]

http://ottawacitizen.com/opinion/columnists/jenkins-food-for-thought-on-the-new-central-library
Reply With Quote
     
     
  #494  
Old Posted May 30, 2016, 2:18 PM
kwoldtimer kwoldtimer is offline
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 26,250
A "central" Library located out back of the football stadium? I guess that at least scores points for showing "out of the box" thinking.
Reply With Quote
     
     
  #495  
Old Posted May 31, 2016, 3:58 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,116
Quote:
Originally Posted by kwoldtimer View Post
A "central" Library located out back of the football stadium? I guess that at least scores points for showing "out of the box" thinking.
Terrible idea. Lansdowne in general is a bad location for the library.
Reply With Quote
     
     
  #496  
Old Posted Jun 1, 2016, 12:57 PM
AndyZagg's Avatar
AndyZagg AndyZagg is offline
Registered User
 
Join Date: Apr 2016
Location: Ottawa
Posts: 28
Quote:
Originally Posted by J.OT13 View Post
Terrible idea. Lansdowne in general is a bad location for the library.
Ditto. The new library should be connected to the LRT for a multitude of reasons. Bayview or Pimisi are my preferences but anywhere along the line is fine.
Reply With Quote
     
     
  #497  
Old Posted Jun 1, 2016, 1:34 PM
kwoldtimer kwoldtimer is offline
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 26,250
Centretown, Centretown, Centretown. Repeat after me - Centretown.
Reply With Quote
     
     
  #498  
Old Posted Jun 1, 2016, 5:22 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,116
Quote:
Originally Posted by AndyZagg View Post
Ditto. The new library should be connected to the LRT for a multitude of reasons. Bayview or Pimisi are my preferences but anywhere along the line is fine.
That's it. Lansdowne has poor accessibility for the vast majority of the population. And behind the stadium? The stadium's vale is one of the most interesting features of the park? Why would you hide it?

Ottawa Tech or the site proposed by RV are the best options in my opinion.
Reply With Quote
     
     
  #499  
Old Posted Jun 17, 2016, 1:36 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,674
Sixty people show up at Ottawa central library consultation on spaces and programs

Jon Willing, Ottawa Citizen
Published on: June 16, 2016 | Last Updated: June 16, 2016 1:42 PM EDT


About 60 people attended a consultation Wednesday on what should be in a new central library in Ottawa, according to library staff.

The four-hour session at city hall is one of two open houses this month that encourages residents to share ideas about how to plan and program the spaces inside a new municipal library.

Another open house will happen next Wednesday at Library and Archives Canada, 395 Wellington St., between 4 p.m. and 8 p.m.

Display boards from the sessions are expected to rotate around some library branches this summer.

The Ottawa Public Library is working with the federal Library and Archives to see if they should combine their efforts to build a super library. A standalone municipal library is still an option for the OPL.

The OPL wants a new facility in the downtown area between the Trillium Line and King Edward Avenue. There’s a strong preference for the facility to be near a future LRT station.

The library hasn’t determined where exactly it should establish a new central facility, but it’s getting closer to figuring out how to decide which properties are best. Library trustees are scheduled to consider a report at their next meeting in July that will recommend site-selection criteria.

In December, trustees will see a recommended course of action for establishing a new central library, including the funding requirements and public-private partnerships.

The open houses this month will inform the library design, which will be subject of consultations in 2017.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news...rary-consultation-on-spaces-and-programs
Reply With Quote
     
     
  #500  
Old Posted Jun 23, 2016, 3:36 PM
AndyMEng AndyMEng is offline
Registered User
 
Join Date: Jun 2015
Posts: 393
Ottawa should take a page from Tianjin. This is absolutely amazing.

http://www.dezeen.com/2016/06/23/tianjin-binhai-library-mvrdv-china-eye-shaped-nears-completion/

Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Downtown & Urban Ottawa
Forum Jump



Forum Jump


All times are GMT. The time now is 11:37 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.