Quote:
Originally Posted by WarrenC12
Phase 3 can't begin until one of the other two phases are done to provide access to the station. Do these timelines still look reasonable?
|
TransLink also says "Design of the project was completed by December 2014, with construction is expected to begin early 2015 and continue until winter 2017." They still haven't changed the individual timelines though...
There's a large hole in the platform for the new stairs. They're going to have to move fast if they want the Center Stationhouse completed "Spring 2016" (which ok technically means anywhere between mid-March to mid-June).
Then the new West Stationhouse. The pics officedweller
posted show all sorts of 'stuff' under the station but it doesn't look like there's anything in place where the new stationhouse is going to go. Sure some of it will be prefab and brought to the site, but can they really have the whole thing finished by "Summer 2016" (so between mid-June to mid-Sept)? I'll have to take a good look at the station next time I'm there - maybe they've been really busy recently.
They can start on rebuilding the East Stationhouse with only the Center Stationhouse open. Sure there'll be people cranky about no escalators. If they do it right (which is always debatable) then they'll close the stairs from the ground to the ticket level and get to work on ground level first. That would give them a bit of breathing room before they shut down that whole end.
I think they're going to push off the dates on the East Stationhouse so they can concentrate on building the other stationhouses. Plus they haven't done any work on the platform level (mostly replacing the mesh panels with glass ones) and they'll have a whole bunch of paving / landscaping to do around the station and the promised divided bike path (Spring 2018 for that?).