Thanks Katherine for the info!!
Some tidbits from quickly scanning the document:
- This is only the first phase. The whole station makeover is actually quite complex, and will likely require the North Surrey Arena to go before they can move on past this. The concrete walls on the west side will 🞵🞵🞵🞵 up against future development sites.
- This phase includes a new North station house, with a new elevator, and entries from the north (103rd) and the east (City Parkway).
- Future phase to include a new South station house.
- New CRU along 103 Avenue (likely a cafe).
- Surrounding paving will be similar to, and blend in with City Hall Plaza.
- Roof to be replaced in future phase.
- Once LRT is built, the sidewalk along City Parkway will expand by 3 metres.
- Translink wants to start work in May, 2016.
Here's another render from the document:
http://www.surrey.ca/bylawsandcouncillibrary/PLR_7915-0361-00.pdf