Construction Update
Week of November 2




Signalization work, part of Scott Street widening

Scott Street Widening


Crews finalize signalization in the intersections, and prepare to pave and install lighting on the rehabilitated multi-use pathways. O-Train platform relocation work is being completed.



Mining in drifts in the Lyon Station cavern

Lyon Station


Crews install conduits and pour pre-slab in west running tunnel. Jawbreaker mines the bench.



Ongoing piling on Lyon Street

Lyon Station East and West Entrance


East Entrance: crews pour walls and overhead slab for the lower level elevator.

West Entrance: crews continue excavating and reinforcing for the station entrance, in addition to piling.




Parliament Station Cavern

Crews begin forming and pouring walls in the tunnel transition moving west toward Lyon Station. Installation of a section of the umbrella begins and Chewrocka mines the central pillar.



Mining in drifts in Rideau Station cavern

Rideau Station


Crews continue constructing the invert and assembling the arch formwork for final concrete lining work in the east running tunnel. In the cavern, Crocodile Rouge excavates the bench in the north side and umbrella installation occurs in the south drift.



Hoe ramming and rock excavation at Rideau Station east entrance

Rideau Station East and West Entrance


East Entrance: crews continue line drilling, hoe ramming, rock excavation, material removals and blasting operations in phases.

West Entrance: station entrance reinforcement continues and includes, installing piles, followed by rebar, in addition to pouring concrete piles,

Traffic restrictions on Rideau Street remain in effect.



Installing sections of the utility corridor at uOttawa Station

uOttawa Station


The majority of the installation of the utility corridor has been completed. Final installations are ongoing adjacent tothe University of Ottawa buildings along Nicholas Street.



Pouring mud slab at Blair Station

Tremblay, St-Laurent, Cyrville and Blair Stations


Demolition of the Transitway structure is completed at Hurdman Station. Piling, reinforcements, installation of hoarding and removals occur at Tremblay Station. Preliminary foundation work begins at St-Laurent Station. At Cyrville Station, crews install rebar, form and begin pouring footings. At Blair Station, station foundation work involves pouring mud slabs and initial rebar installation for footings and walls.



Pouring panels at the Booth Street Bridge north abutment

Guideway – Booth Street Bridge


Crews continue pouring the panels on the north abutment.



Constructing pier caps on Hurdman Station elevated guideway

Guideway – Hurdman Station


Crews continue pouring the deck for the elevated guideway, and begin pouring the deck of the structure east of the station.



Ongoing formwork installation on abutment of east ring structure at Tremblay Station

Guideway – Tremblay Station


Crews pour the abutment walls on the road east of VIA Rail Station.



Pulling rail strings on the guideway west of Blair Station

Guideway – St-Laurent, Cyrville and Blair Stations


Grading, excavation for overhead catenary pole foundations and duck bank installations begin west of St-Laurent Station. Crews install sub-ballast and rail ties in sections from Cyrville Station moving west. Trackwork progresses from Blair to Cyrville stations.



Roundabout landscaping at Belfast Yard

Belfast Yard Administration and Maintenance Building and Yard


Crews finalize ceilings, work on tooling inside the building and install exterior panels outside. Paving, drilling for light bases, landscaping, and trackwork occur in the yard. Rehabilitation of the sidewalks and fence installation continue on Belfast Road.



Formwork for roof installation at the Belfast Yard connector

Belfast Yard Vehicle Storage Shed and Connector Works


Crews finalize tracks and pave pathways in the shed. Work at the connector involves waterproofing and completing walls, formwork for roof installation, finalizing vents and ongoing rebar installation for trackwork. Relocation of the watermain and grading occurs on Tremblay Road.



Upcoming Construction Activities

In the coming weeks, the following construction activities are scheduled to occur:
  • Parliament Station entrance utilities relocations.
  • Watermain relocation for Rideau Station entrances.
  • Installation of girders on the remaining Hurdman Station elevated guideway columns.
  • Rideau Street to close between Sussex and Dalhousie beginning evening of Friday, November 21st and ending before the peak Monday, November 23rd

In the coming months:
  • Lyon Station west entrance blasting operations.
  • Lyon Station east entrance and west shaft construction.

http://www.ligneconfederationline.ca/construction/construction-update-47/
     
     
  #2482  
Old Posted Nov 9, 2015, 10:02 PM
DarthVader_1961 DarthVader_1961 is online now
Registered User
 
Join Date: Jun 2009
Posts: 469
Airport link in doubt

     
     
  #2483  
Old Posted Nov 9, 2015, 10:41 PM
MalcolmTucker MalcolmTucker is offline
Registered User
 
Join Date: May 2007
Posts: 11,596
The extension in Orleans has the subway to the sea problem.

Calgary does these one or two stop extensions as one offs later usually. Not a big loss to delay it. The neighbourhoods don't look to be oriented in a way to make going to a Trim Rd. station any faster than going to the mall.
     
     
  #2484  
Old Posted Nov 9, 2015, 11:32 PM
bartlebooth bartlebooth is offline
Registered User
 
Join Date: Dec 2010
Posts: 480
Apparently the Lyon Station cavern is over 92% complete. Does anyone know what will happen with the roadheader at Lyon when digging is complete? Does it continue digging the tunnel? Does it help at another station cavern?
     
     
  #2485  
Old Posted Nov 9, 2015, 11:34 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,556
Ottawa's transit troubles force rethink of LRT's financial plans

David Reevely, Ottawa Citizen
Published on: November 9, 2015 | Last Updated: November 9, 2015 6:26 PM EST


Prospects are dimming for a rail link to the airport and an eastern line that goes all the way to Trim Road, as the city struggles to afford the rapid-transit lines it’s already planning. Indeed, the four-year old plan to cover the city’s light-rail costs turns out to be based on some faulty assumptions about ridership and payments from other governments.

You wouldn’t have known it from all the handshakes and sunny speeches on Monday morning at Lincoln Fields, where a bunch of councillors and MPPs gathered to announce the province is giving the city $34.3 million this year — Ottawa’s share of an annual provincial distribution of money Ontario brings in by taxing gasoline. The money, dedicated to transit, is helping to pay for construction right now on the light-rail tunnel under downtown and laying track toward an eastern terminal at Blair Road.

The politicians rhapsodized.

“All this work in enhancing our public transit is going to result further in building a world-class capital city which is our hometown,” said Ottawa Centre MPP Yasir Naqvi.

“Ontario’s gas tax is helping ease traffic congestion and reduce air pollution in Ottawa by getting more people out of their cars and onto the bus,” said transit commission chairman and Cumberland Coun. Stephen Blais.

It sounds like a lot of money and it is. It’s just not as much as the city had been counting on from a permanent program whose transfers are fully accounted for already in the city budget. For the second year running, the payment is short of the $36 million Ottawa has assumed it would get.

The shortage is the second whammy for a budget already hit by lower-than-expected ridership. They’re really the same problem: the gas-tax payment is determined by a formula built on ridership numbers.

“Population growth wasn’t what it was anticipated to be. Housing development wasn’t what it was anticipated to be. The economy has not recovered to the same high levels that people had hoped for,” said Blais. “All those things factor into how much revenue is collected by the city, including by OC Transpo. That impacts the formula by which a lot of our future planning is based. The city manager says he’s working on an update to the affordability model for light rail.”

The “affordability model” is the plan for how the city will cover its share of rail construction over the next several decades, a rolling scheme of taxes and debt and transfers from above covering $1.9 billion and counting. It was written in 2011, using what turned out to be unrealistically high ridership and gas-tax revenues.

The rail plan underwritten by that financial model includes light-rail lines between Bayshore, Baseline and Place d’Orléans, and an extension of the existing O-Train line so it would run from Bayview to Bowesville in Riverside South.

Lots of people want the leg planned for Place d’Orléans to extend a few more kilometres to Trim Road and serve more of Orléans. An O-Train spur to the airport would be nice for travellers and would make Ottawa feel like a more grown-up city. Each would cost about $160 million, according to the city’s estimates.

The model was meant to be conservative, so it isn’t in chaos. But neither is it full of pleasant surprises.

Ottawa West-Nepean MPP Bob Chiarelli, the province’s senior local minister, said he’d want to see “an ask” for the Orléans and airport money, a detailed case; thus far the talk about those extensions is just chatter. Both the provincial and federal governments are looking to spend great vats of money on infrastructure and it’s not beyond imagining they could just get together and pay for something the City of Ottawa can’t find the money for. But a good ask comes with a spending promise of your own.

Thursday, the first public draft of the city’s 2016 budget comes out. In September, OC Transpo revealed it was running an $11.5-million deficit this year and was cutting to try to get that under control. Everyone’s short of money, Blais said, and that means everyone, including OC Transpo, must be cautious about their plans.

Construction projects that would be at least five years away aren’t the same as operating shortfalls this year, but they’re part of the same package. It’s hard to see how caution can square with going hundreds of millions of dollars deeper into a wish list when it’s not clear we can afford the things we’re already planning to buy.

[email protected]
twitter.com/davidreevely

http://ottawacitizen.com/opinion/columni...es-force-rethink-of-lrts-financial-plans
     
     
  #2486  
Old Posted Nov 10, 2015, 3:58 AM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by MalcolmTucker View Post
The extension in Orleans has the subway to the sea problem.

Calgary does these one or two stop extensions as one offs later usually. Not a big loss to delay it. The neighbourhoods don't look to be oriented in a way to make going to a Trim Rd. station any faster than going to the mall.
One needs to look at the Stubway (AKA Sheppard line) to see the truth and lie to this. Since the line has been built, the area near each station has seen lots of growth.

Besides, an empty field means anything can be built.
     
     
  #2487  
Old Posted Nov 10, 2015, 4:33 PM
MoreTrains MoreTrains is offline
Registered User
 
Join Date: Oct 2014
Posts: 858
Quote:
Originally Posted by bartlebooth View Post
Apparently the Lyon Station cavern is over 92% complete. Does anyone know what will happen with the roadheader at Lyon when digging is complete? Does it continue digging the tunnel? Does it help at another station cavern?
Depending on where it is, it will continue tunneling. However, if the tunnel from Lyon to Parliament is already done, it will move on to help excavate Parliament.
     
     
  #2488  
Old Posted Nov 10, 2015, 5:06 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,768
Oof! $160 million for a couple of kms of track from south of Hunt Club to the airport. And I presume this is single tracked. Costs are really escalating. This cost escalation probably relates to the fact that all intersections have to be grade separated, something that was not envisioned when electric LRT was the earlier plan.
     
     
  #2489  
Old Posted Nov 10, 2015, 10:29 PM
bartlebooth bartlebooth is offline
Registered User
 
Join Date: Dec 2010
Posts: 480
Quote:
Originally Posted by MoreTrains View Post
Depending on where it is, it will continue tunneling. However, if the tunnel from Lyon to Parliament is already done, it will move on to help excavate Parliament.
Great, thanks for the response. I believe the tunnel from Lyon to Parliament is already done so I guess it will help at the next station. Exciting.
     
     
  #2490  
Old Posted Nov 11, 2015, 1:11 AM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
Or tunneling under the canal, which I believe has yet to start.
     
     
  #2491  
Old Posted Nov 12, 2015, 5:10 AM
mykl mykl is offline
Registered User
 
Join Date: Jan 2015
Location: Ottawa
Posts: 475
Quote:
Originally Posted by McC View Post
Or tunneling under the canal, which I believe has yet to start.
There's only access to help digging at Parliament station or Rideau station. Those are the only 2 options.
     
     
  #2492  
Old Posted Nov 12, 2015, 1:39 PM
Jamaican-Phoenix's Avatar
Jamaican-Phoenix Jamaican-Phoenix is offline
R2-D2's army of death
 
Join Date: Jun 2007
Location: Downtown Ottawa
Posts: 3,561
It's really unfortunate that we're looking at the monetary cost alone and not at the bigger picture when it comes to the Airport Rail link.
__________________
Franky: Ajldub, name calling is what they do when good arguments can't be found - don't sink to their level. Claiming the thread is "boring" is also a way to try to discredit a thread that doesn't match their particular bias.
     
     
  #2493  
Old Posted Nov 12, 2015, 3:46 PM
MoreTrains MoreTrains is offline
Registered User
 
Join Date: Oct 2014
Posts: 858
Quote:
Originally Posted by lrt's friend View Post
Oof! $160 million for a couple of kms of track from south of Hunt Club to the airport. And I presume this is single tracked. Costs are really escalating. This cost escalation probably relates to the fact that all intersections have to be grade separated, something that was not envisioned when electric LRT was the earlier plan.
Source?
     
     
  #2494  
Old Posted Nov 12, 2015, 3:59 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,834
Quote:
Originally Posted by MoreTrains View Post
Source?
LRTfriend seems to be referencing the article above posted by rocketphish.
     
     
  #2495  
Old Posted Nov 12, 2015, 4:08 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,768
Quote:
Originally Posted by acottawa View Post
LRTfriend seems to be referencing the article above posted by rocketphish.
exactly
     
     
  #2496  
Old Posted Nov 13, 2015, 12:42 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,556
Construction Update
Week of November 9




Scott Street paving looking west

Scott Street Widening


Lighting installation on the multi-use pathways is underway. Paving occurs on Scott Street and relocation of O-Train Trillium Line platform is being finalized.




Lyon Station


Crews continue to install conduits and pour pre-slab in west running tunnel. Excavation of west pit is ongoing.



Elevator base slab for Lyon Station east entrance

Lyon Station East and West Entrance


East Entrance: formwork and rebar for beams are ongoing. Elevator walls and slabs continue.

West Entrance: shoring and lagging continue in the future entrance area. Work is now complete on the Lyon Street east sidewalk.



Form work and mining continue at Parliament Station

Parliament Station Cavern


Work continues as crews complete reinforcements and begin central pillar excavation.



Utility works begin at O’Connor and Queen Street

Parliament Station East and West Entrance


Utility relocations for future station begin on O’Connor Street at Queen Street. Construction hoarding and fencing is set up on the street and parking levels.



Rideau Station cavern mining

Rideau Station


Excavation continues in Rideau Station, supported by shotcrete, wire mesh and lattice girders.



Rideau Street east entrance hoe ramming and excavation

Rideau Station East and West Entrance


East Entrance: excavation including blasting and hoe ramming continues, along with initial wall reinforcements.

West Entrance: pile installation and concrete pouring are ongoing.

Traffic restrictions on Rideau Street remain in effect.



Nearing completion of the utility corridor at uOttawa Station

uOttawa Station


The majority of the installation of the utility corridor has been completed. Final installations are ongoing along Nicholas Street. This work is expected to continue until the third week of November.



Work continues on the east road next to the VIA Station

Hurdman, Tremblay, St-Laurent, Cyrville and Blair Stations


Preliminary foundation work continues at St-Laurent Station and sections of concrete are being removed from the existing station. At Tremblay Station, piling, reinforcements and installation of hoarding are ongoing. At Cyrville Station, crews continue installation of formwork and rebar on footings and walls. At Blair Station, final mud slab is being poured and crews are continuing to form the footings for the new station.



Work continues at the Booth Street Bridge

Guideway – Booth Street Bridge


Final abutment work is ongoing over the next two weeks. Bridge construction will resume in early January 2016.



Rebar installation on deck of Hurdman Station elevated guideway

Guideway – Hurdman Station


Rebar installation is being finalized on the elevated guideway.

Crews begin pouring the deck for the elevated guideway, and for the structure east of the station.



Work continues on the east road next to the VIA Station

Guideway – Tremblay Station


Crews begin pouring the abutment walls on the road east of VIA Rail Station.



Track installation on guideway west of Blair Station

Guideway – St-Laurent, Cyrville and Blair Stations


Ballast placement and distribution of concrete ties are ongoing between Cyrville and St-Laurent stations. Duct bank and overhead catenary pole foundation installations continue from St-Laurent Station moving west.



Track welding takes place onsite at Belfast Yard

Belfast Yard Administration and Maintenance Building and Yard


Exterior panels, trackwork and paving are being completed at Belfast Yard.



Crews construct Belfast Yard connector walls

Belfast Yard Vehicle Storage Shed and Connector Works


As part of trackwork on the connector, crews continue to pour the concrete slab. Construction continues on slopes surrounding the connector. Road reconstruction begins at Belfast and Tremblay roads, and final works continue on the multi-use pathway.



Upcoming Construction Activities

In the coming weeks, the following construction activities are scheduled to occur:
  • Watermain relocation for Rideau Station entrances.
  • Installation of girders on the remaining Hurdman Station elevated guideway columns.

In the coming months:
  • Lyon Station west entrance blasting operations.
  • Lyon Station east entrance and west shaft construction.

http://www.ligneconfederationline.ca/construction/construction-update-48/
     
     
  #2497  
Old Posted Nov 13, 2015, 2:13 PM
MoreTrains MoreTrains is offline
Registered User
 
Join Date: Oct 2014
Posts: 858
Quote:
Originally Posted by lrt's friend View Post
exactly
Yep, my bad. I even re-read that article before posting.
     
     
  #2498  
Old Posted Nov 13, 2015, 4:25 PM
Richard Eade Richard Eade is offline
Registered User
 
Join Date: Mar 2008
Location: Nepean
Posts: 2,612
I'm hoping that they plan to add drainage for the north 'Y' of the Connector. From the picture, it looks like a bit of a water collector.
     
     
  #2499  
Old Posted Nov 13, 2015, 5:03 PM
MaxHeadroom's Avatar
MaxHeadroom MaxHeadroom is offline
Registered User
 
Join Date: Oct 2009
Posts: 189
Quote:
Originally Posted by Richard Eade View Post
I'm hoping that they plan to add drainage for the north 'Y' of the Connector. From the picture, it looks like a bit of a water collector.
I think that area will be backfilled once the connector tunnels are done, and the intersection of Tremblay and Belfast restored on top of it.
     
     
  #2500  
Old Posted Nov 13, 2015, 5:12 PM
HighwayStar's Avatar
HighwayStar HighwayStar is offline
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Try as I might, I can't quite grasp where that water filled Y is... would some kind soul please enlighten me
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 11:21 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.