A new website has been set up for the New Central Library. One of the things I found interesting was the timeline has been posted. Of note:
Q1 2016 - Concrete cores complete for the library
Q2 2016 - Steel installation begins and additional cranes will be brought on site
Q4 2016 - Steel structure will be complete as well as the cladding for the south side will be fully installed.
Q1 2017 - Cladding to be complete on east and west exteriors.
Q2 2017 - Interior construction and finishings start
Q3 2017 - Wood soffit underbelly is installed.
Q2 2018 - Interior construction is complete.
Q3 2018 - Library move in begins
Q4 2018 - Opening day.
Great to think that in about a year the exterior will be more or less complete on this iconic building except for the wood soffit underbelly which should be an interesting process to watch be completed!