Quote:
Originally Posted by CanSpice
It's in the South Coast British Columbia Transportation Authority Act, which is the legislation that governs TransLink. TransLink has the final say on the removal of any capacity to the Major Road Network:
Since removal of the viaducts definitely counts as a reduction of capacity of part of the major road network, the City of Vancouver needs to have the TransLink board pass a bylaw that removes the viaducts from the major road network.
Oh, and looking at the major road network map, the Dunsmuir Viaduct isn't in the MRN, and only part of the Georgia Viaduct is (the part between Beatty and the offramp leading down to Main Street).
|
Correct. Technically only the Georgia St. viaduct is part of the MRN right up to Main St. But practically ya can't remove one without the other.
I have stated the following ad nauseam on here over the years but will repeat again:
1. Back circa 1999, the Van City engineering dept. advised council the consequences of placing any road within the MRN. Basically, once you're in you'll never be able to get out. Posted the 1999 City Memo on here ages ago;
2. Translink views an MRN-designated road as a "regional" road in terms of regional connectivity, trucking, etc.
3. The City of Surrey has previously requested removal of portion of MRN/Truck Route to no avail. Same with the City of New Westminster. To no avail. I am sure other munis have as well. For same reasons as viaducts in Van City. Translink precedents have already been set.
And Translink always discusses these issues with regional stakeholders:
1. BC MoTI (as Georgia Viaduct connects to Stanley Park Causeway/Lions Gate Bridge);
2. BC Trucking Association as Georgia viaduct is key trucking connector to Georgia St/Lions Gate Bridge. In fact, when the Georgia viaduct was temporarily shutdown this past April, the BC Trucking Association issued a release to truckers of a special downtown detour that required the VPD at an intersection to assist truckers making the corner.
http://www.bctrucking.com/2015/03/26/georgia-viaduct-temporary-closure-april-5-16-2015
3. BC Gateway Council - as part of movement of goods in region;
4. Port of Vancouver - ancillary requirements;
As with past requests for MRN removal all of the foregoing bodies opposed same. No doubt they would have similar response to Van City's request.
Once again. Have never heard a peep from Translink on this issue. And they are the final decision makers.
Frankly, this whole "viaduct removal" meme is all about naught IMHO.
PS. I noticed that this thread was started back in 2009 - almost 6 years ago. The thread dies and then every once in a while, for unknown reason, it revives again. Yet nothing has ever changed.
EDITED TO ADD:
Both the Georgia viaduct AND the Dunsmuir viaduct are also part of the City of Vancouver's "Truck Route Network".
Provincial legislation also requires TransLink approval for any changes that would prohibit truck movement (this applies to all municipal roads, not just the MRN). And, ergo, that includes BOTH viaducts. Another fly in the ointment right there - As Translink has also previously refused other Metro Van muni requests removing the Truck Route Network designation on their own truck route networks.