The past few floors of the hotel haven't been easy, with different height floors/ceilings for the docks; the office side there is special stuff to do as the are at some roof lines. And the cranes have to be a critical path.
But with this weather, I'm a little surprised there isn't a half-crew working late into the evening.
|
Developer Joe Ramia is quoted today as saying the Nova Centre is still on track for its September 2016 opening. According to ANS, construction was set back by the harsh winter, including significant snow clearing after every one of the massive dumps we endured.
Ramia celebrated topping out of the seven-storey Argyle Street pedestal last week. It was the most complicated part of the project, but Ramia says the towers should go much quicker as each floor from here on is basically a duplicate of the one before.
He says the workers are labouring through the weekends and putting in long days to stay on track.