Construction Update
Week of June 22
LeBreton Flats Diversion Chamber works
Albert Street Civic Works
LeBreton Flats Diversion Chamber construction is ongoing. Road and utility work progress along Albert Street. The Albert Street multi-use pathway has reopened.
Booth Street Bridge pier construction
Booth Street Bridge
Abutment excavation and construction of the pier column on the north side of Booth Street Bridge occur.
Lyon Station cavern
Lyon Station Cavern
Jawbreaker is mining the central pillar and upper drifts of the station cavern. Cavern support continues, including umbrella installation and backfilling. Final lining works are ongoing.
Place de Ville concourse demolition works
Lyon Station East Entrance
Structural demolition is ongoing on the concourse level of Place de Ville and in the parking garage. Sprinkler system relocation and fire protection demolition also occur.
Parliament Station reinforcement works
Parliament Station Cavern
Chewrocka is mining in upper drifts and the central pillar. Lattice girder and umbrella installations also occur.
Rideau Station utilities relocation
Rideau Station Entrances
Weekend centre lane closures for Rideau Station utilities relocation is complete. Paving is scheduled to occur this week on Rideau Street between Sussex Drive and William Street during off-peak hours.
Rideau Station bench excavation
Rideau Station Cavern
Crocodile Rouge is mining the cavern central pillar and the bench in the transition. Umbrella installation and temporary lattice girder installation occurs.
Falsework at Hurdman Station
Hurdman Station
Crews continue elevated guideway work. Rebar cages are being delivered onsite to advance construction on the columns and piers. Pouring of pier caps begins and falsework and formwork occur. Intermittent closures and flagging of the pathway continue.
Final works at Blair Station
Blair Station
Line painting and site clean-ups occur this week to complete the bus loop.
Concrete curb work at Pickering Place detour
Tremblay Station
Pickering Place widening works are being finalized this week, including curbs, paving, line painting, and landscaping. A detour via Pickering Place will be used during construction of the guideway and future Tremblay Station.
Maintenance bays at Belfast Yard building
Belfast Yard Administration and Maintenance Building
Crews continue working on architectural, mechanical and electrical finishes on the second level and begin installing carpets. Work begins on the platforms and preparations to install track in the building occur this week.
Trackwork at Belfast Yard shed
Belfast Yard Vehicle Storage Shed and Yard Works
Crews finalize panel installations on the shed and continue installing ballasted track and ties inside. Fencing and track work progress in the yard and installation of the noise wall begins. Duct bank installations are ongoing from the yard to the connector.
Preparations to pour slabs at Belfast Yard connector
Belfast Yard Connector
Backfilling continues along the connector and Tremblay Road, and pouring of slabs and walls progress. Realignment works, including paving and line painting, have been completed and the next phase of the road detour is in place. Pedestrians will be realigned on the pathway.
Nicholas Street paving
Nicholas Street
Sewer and watermain relocations will be completed this week along Nicholas Street.
Median lane barrier removals on Highway 417
Highway 417
Construction of the St-Laurent Station temporary ramp to Highway 417 westbound is being finalized. Work continues in the median including paving, line painting, sign installations, removing quick moveable barriers and replacing them with barrels, and site clean-ups.
Asphalt pour on Hurdman Bridge
Hurdman Bridge (Highway 417 over Rideau River)
Crews completed asphalt pouring and final construction of the deck. Work will continue under the bridge to strip the soffit. Intermittent flagging and short duration closures are ongoing along the Rideau River east and west multi-use pathways until early July.
Paving on Vanier Parkway bus lay-by area
Vanier Parkway Overpass
Crews continue final works including paving, ramps and curbs. Line painting and electrical, are being completed at the Vanier Parkway bus lay-by area, which will be used by OC Transpo buses.
Site clean-up on Belfast Bridge
Belfast Bridge
Final site clean-ups have been completed and the bridge is now open to pedestrians and cyclists.
Upcoming Construction Activities
In the coming weeks, the following construction activities are scheduled:
- Lyon Station west entrance preparatory works, including watermain and sewer work on Queen Street.
- Lyon Station east entrance excavation.
- Excavation and shoring at the future site of the Rideau Station east entrance.
Additional construction activities scheduled this summer include:
- Station and guideway construction at Tremblay, St-Laurent, Cyrville and Blair stations.
- Hurdman Station temporary bus loop construction.
- Demolition of the building at 805 Belfast Road.
http://www.ligneconfederationline.ca/construction/construction-update-28/