Originally Posted by Olden Retreiver
Right after the 4th sinkhole, I was going to post facetiously that they should get back on schedule by skipping the grout and going directly to sinkhole.
Initially I thought the grout was intended to strengthen the ground by essentially flooding a volume of soil with cement material. What is the designed purpose of this (vertical?) grout wall? Isn't the basic problem that the tunnel roof keeps collapsing whenever it's unsupported? Is the grout wall intended to hold back groundwater flow? Inquiring minds really, really want to know.
|
The purpose of the grout wall IS to hold up the ground to prevent sink holes. Nothing to do with stopping water, that is done by a separate dewatering process to lower the water table.
Listen, if you go to a sandy beach, fill up a bucket of sand and plop it upside down to create a little sand mountain, this is how cohesive Burnaby Mountain/Clarke Hill is. The only thing holding it all together is gravity. Now imagine trying to bore a miniature tunnel through that little mountain of sand you got.
I will let you guys judge what is or is not incompetence yourselves through the following information. First of all I want to make clear, that having to build a grout wall in of itself is NOT a sign of incompetent tunneling in any way. When you are tunneling through glacial sediment, building a grout wall is the only chance you have of keeping the soil stable for TBM maintenance and not getting sink holes.
The problem is, the project was building the tunnel through this soil condition WITHOUT building grout walls, hoping to just wing it through the TBM maintenance and hope that no sinkholes appear. This has the benefit of saving ALOT of cash by not having to build any grout walls, and being able to say in the literature that the only tunnel construction disturbance would be at both ends of the tunnel.
The whole reason for the tunnel delay, is that building grout walls wasn't planned for in the time schedule. For example, the TBM arrived at Seaview in March, but was sitting idle waiting for maintenance after the grout wall was completed in June. If the grout wall was already complete by the time the TBM got there in March, there would have been no delay at this maintenance stop (ignoring the fact it was already delayed from the previous stops).
The tunnel could have been completed on schedule if they started construction of the grout walls in the beginning of 2014, with each wall being complete before the TBM got there, letting TBM maintenance begin immediately, and not having the TBM just sit there a couple of meters before the wall waiting for its completion.
But the problem is, the project wanted to save some serious cash by not building the walls and hoping for the best. Well as you all know, even building these walls at the last moment, we still got sinkholes. So it begs to ask the question:
It is pretty obvious that building these walls for 5 months at a time is some serious coin. Would it just be cheaper to forgo the walls, let a huge sinkhole appear, and repair it. Ofcourse the 4th sinkhole would be much larger, than the one that appeared if no wall was constructed. It might have been so large that it may have damaged some other structures. But, it could have been cheaper to just pay off the property repairs, than 5 months of subterranean construction.