Construction Update
Week of June 15
Albert Street multi-use pathway reopens
Albert Street Civic Works
The Albert Street multi-use pathway reopens months ahead of schedule! Traffic ‘switch’ to the north-side of Albert between Preston and Booth allowing for utility and sewer works to continue. LeBreton Flats Diversion Chamber construction is progressing.
Booth Street Bridge pier construction
Booth Street Bridge
Abutment excavation is ongoing and concrete pouring occurs at the Booth Street Bridge piers.
Arch waterproofing in Lyon Station running tunnel
Lyon Station Cavern
In the station cavern Jawbreaker is excavating the central pillar and upper drift, and umbrella installation is ongoing. In the running tunnel, final lining works such as waterproofing and rebar, and formwork installation occur. Pouring of starter wall continues.
Place de Ville concourse demolition works
Lyon Station East Entrance
Structural demolition continues on the concourse level and begins in the Place de Ville parking garage.
Parliament Station reinforcement works
Parliament Station Cavern
Chewrocka continues to excavate in upper drifts and the central pillar. Umbrella installation occurs.
Rideau Station bench excavation
Rideau Station Cavern
Crocodile Rouge is excavating Rideau Station cavern. Rock bolt installation, and shotcreting occurs.
Guideway excavation at Hurdman Station
Hurdman Station
Crews continue construction of columns and piers for the elevated guideway. Other works include excavation, formwork and falsework. Intermittent closures and flagging of the pathway continue.
Granular placement at Blair Station bus loop
Blair Station
Construction of the bus loop is ongoing and includes electrical work, drainage and granular placement.
Sidewalk and road widening on Pickering Place detour
Tremblay Station
Road widening works such as excavation and sidewalk construction continue on Pickering Place. A detour via Pickering Place will be used during construction of the guideway and future Tremblay Station.
Rail support in sanding area at Belfast Yard
Belfast Yard Administration and Maintenance Building
Architectural, mechanical and electrical finishes continue on the second level. Commissioning activities have commenced and exterior cladding is being completed.
Yard works at Belfast Yard
Belfast Yard Vehicle Storage Shed and Yard Works
Crews advance fencing works in the yard and begin a section north of the shed. Panel installations are almost complete and track welding occurs in the yard. Duct bank installation from the yard to the connector begins this week, and landscaping works continue.
Belfast Yard connector
Belfast Yard Connector
Crews continue backfilling along the connector. Other works include concrete placement and electrical. Realignment works progress for the next phase of the road detour. Intermittent short-term flagging is ongoing on the pathway.
Preparations for paving median lane on Highway 417
Highway 417
Sewer and watermain relocations progress and include paving along Nicholas Street. Crews continue wiring, paving, backfilling, completing ground mounted sign installations, and removing quick moveable barriers and replacing them with barrels. In addition, site clean-up begins. Construction of the St Laurent Station temporary ramp to Highway 417 westbound will be completed this week.
Final works on Hurdman Bridge
Hurdman Bridge (Highway 417 over Rideau River)
Crews complete final bridge works this week. Intermittent flagging and short duration closures are ongoing along the Rideau River east and west multi-use pathways.
Bus lay-by mobilization at Vanier Parkway staging area
Vanier Parkway Overpass
Crews continue final works including paving, ramps and curbs. Mobilization, excavation and grading occur at the Vanier Parkway staging area, to allow conversion to a bus lay-by area, which will be used by OC Transpo buses.
Waterproofing and paving final works on Belfast Bridge
Belfast Bridge
Crews complete final site clean-ups; the bridge is scheduled to reopen to pedestrians and cyclists the week of June 22, 2015.
Upcoming Construction Activities
In the coming weeks, the following construction activities are scheduled:
- Preparatory Scott Street widening works from Tunney’s Pasture to Bayview Road.
- Lyon Station west entrance preparatory works, including watermain and sewer work on Queen Street.
- Lyon Station east entrance excavation.
- Utilities relocation for Rideau Station entrances along Rideau Street.
Additional construction activities scheduled this summer include:
- Excavation and shoring at the future site of the Rideau Station east entrance.
- Hurdman Station substructure and foundation work.
- Hurdman Station temporary bus loop construction.
- Station and guideway construction at Tremblay, St-Laurent, Cyrville and Blair stations.
- Demolition of the building at 805 Belfast Road.
http://www.ligneconfederationline.ca/construction/construction-update-27/