Construction Update
Week of May 18
Albert Street paving between Booth and Empress
Albert Street Civic and Booth Street Bridge
Construction continues for the LeBreton Flats Diversion Chamber while Albert Street widening is being paved. On May 25 traffic will be switched to the north of Albert and the MUP will reopen. Cyclist and pedestrian detour information is available at:
www.ottawa.ca/confederationline.
Jawbreaker mines the Lyon Station cavern
Lyon Station Cavern
Jawbreaker is excavating the top heading and central pillar. Works inside the cavern include installation of drainage, waterproofing, rebar and the installation of sanitary pipe and conduit. Backfilling occurs and formwork assembly begins.
Place de Ville parking garage
Lyon Station East Entrance
Architectural demolition is ongoing at the concourse level within Place de Ville. Other works include electrical and mechanical relocation in the parking garage.
Parliament Station cavern upper drifts
Parliament Station Cavern
Chewrocka is excavating in upper drifts and central pillar of the cavern. Umbrella installation occurs.
Rideau Station cavern umbrella installation
Rideau Station Cavern
Umbrella and rockbolt installation, and shotcreting are ongoing. Invert concrete pouring occurs.
Bus loop construction at Blair Station
Blair Station
Watermain relocation works adjacent to the Transitway are nearing completion as construction of the bus loop that will be used during LRT station construction works begins.
Panel installation on Belfast Yard shed
Belfast Yard Administration and Maintenance Building/Vehicle Storage Shed
Work progresses inside the building, including painting, drywall, electrical and plumbing. Crews continue installing panels and glazing on the shed. Yard works such as duct banks and Overhead Catenary System foundations are nearing completion. Preparations are ongoing for track installation.
Slab work at Belfast Yard connector
Belfast Yard Connector
Connector work continues, including backfilling, formwork, vent construction, waterproofing, insulation, and wall pours and mud slabs along the north and south sides. Electrical works, relocation of the old watermain and a short-term closure of a portion of the pathway are ongoing on Tremblay Road.
Work zone on Nicholas Street
Highway 417
Watermain, sewer installations and lane closures are ongoing on Nicholas Street. Crews continue pouring barrier walls, installing wiring on light poles, paving, grading and backfilling in the median lane. Intersection works occur at Lemieux Street and St. Laurent Boulevard, including curbs and signalization.
Pouring barrier walls on Hurdman Bridge
Hurdman Bridge (Highway 417 over Rideau River)
In addition to waterproofing, crews continue pouring and stripping the median span barrier walls and approach slabs this week. Intermittent flagging and short duration closures occur as required along the Rideau River east and west multi-use pathways.
Site clean-ups at Vanier Parkway overpass
Lees Avenue Overpass/Vanier Parkway Overpass/Belfast Bridge/ Coventry Pedestrian and Cycling Bridge
Final bridge works continue at these structures, including paving, curbs, decorative precast panels and site clean-ups.
Upcoming Construction Activities
In the coming weeks, the following construction activities are scheduled to occur:
- Preparatory Scott Street widening works from Tunney’s Pasture to Bayview Road.
- Construction of Mann Avenue ramp.
- Hurdman Station Hydro relocation.
- Hurdman Station elevated guideway construction resumes with intermittent pathway closures.
- Pickering Place detour construction; detour will be used during guideway construction at the future Tremblay LRT Station.
Additional construction activities scheduled this spring include:
- Lyon Station east entrance excavation
- Excavation and shoring at the future site of the Rideau Station east entrance
- Hurdman Station substructure and foundation work
- Vanier Parkway staging area conversion to bus lay-by area during the East BRT detour
- St-Laurent Station utilities work
- Construction of the St-Laurent Station temporary ramp to Highway 417 westbound
- Intersection lighting works in preparation for Tremblay Road phase 2 detour
- Demolition of the old building at 805 Belfast Road
http://www.ligneconfederationline.ca/construction/construction-update-23/