Quote:
Originally Posted by manny_santos
How about the 412? I drove by it on the 401 yesterday and it seems like there's still tons of work to do. However I'm not an expert on how long these large interchanges take to build.
Still feels weird calling a highway "the 412".
|
I think the 401/412 interchange will definitely be completed by the fall. All of the concrete girders are up for the ramp from the 401 EB -> 412 NB, and the steel has been delivered, and is in the process of being erected for he ramp from the 412 SB -> 401 EB. There is a large stockpile of dirt adjacent to Lake Ridge Road just north of Rossland Road which I am assuming will be trucked to the future 412 interchange site soon to complete the fills for the overpass approaches. I don't drive either Hwy 2, Rossland or Taunton with any regularity so I am less certain of how the structures are progressing at any of those locations, but I know that things were well underway the last time I drove by in the spring.