Quote:
Originally Posted by Sheba
Moving back on topic, I hope they open the VCC to Canada Line section early, while they're still working on the Canada Line to Arbutus section. Filling in that gap will make a lot of difference.
What's your preference for the 99 B-Line after that - only run it from Canada Line, or have say half of them run from there and half from Commercial-Broadway station.
|
There's no way to open the eastern parts of the Broadway subway to the public while tunnel construction is still happening further west. The nature of TBM construction means that all the parts to build the tunnels have to come in via the eastern portal at Great Northern Way and through the completed tunnel, and all the rubble & dirt has to be removed through the completed tunnel and out the same portal. Look at the TBM tunnel for Evergreen as an example.
However, once the TBM tunnels are completed, all the stations could be under construction simultaneously, and with station completions all happening at nearly the same time, what is the use of opening each station on different days?
The Canada line looked finished (from the street) for months before it was opened, but behind the scenes there was still a beehive of activity to get the stations and line ready for opening day. Don't be surprised in 2016 if there are questions about why the Evergreen line is 'finished' and has trains are running on it, but it won't open until the Fall.