I just wanted to re-visit my post from earlier today.
By July 2016 (17 months from now), I would expect:
CITC - Should be topped out or close to being topped out. If you look at construction of the CC on
Phillyskyline , CITC is now where the original building was in Dec of 2005 and the topping off ceremony took place 18 months later. If it stays on schedule, CITC will be very visible from nearly all angles.
FMC - If the CITC is nearly topped off by July 2016, then I'd expect FMC to be topped off and halfway cladded. Due to its location, it will be visible from most angles.
SLS and W/Element - Seems like these two are in the preliminary site prep stages. If both projects pick up pace and go right into construction, then I'd expect cores of a few hundred feet - maybe higher since neither have underground parking.
700 Schuylkill - I recall reading somewhere that Phase 1 (the tall tower) will be complete in 2017, so hopefully by July 2016 we'll see a core of a few hundred feet and a visible crane due to its location.
1601 Vine - L&I sign says anticipated completion date is Dec 2017, so that means it should be topped off or close to it with some cladding. Despite it not being very tall, it's location will make the crane pretty visible from some angles.
Market East Projects - Both East Market and the 1200 Chestnut Street projects should be close to wrapping up, removing huge eyesores so close to the Convention Center. I also think that the 8th Street garage facade redo will be complete (should be done this year).
1919 Market - Should be just completed. Per the L&I sign on site, it's scheduled to be completed May 2016, so this crane will be down.
And who knows what other projects will be breaking ground or under construction by then? 500 Walnut? 1900 Walnut? Some project that hasn't even been announced yet? Exciting times indeed!