Construction Summary
Week of November 16
Central Segment
Tunnel
West Portal (Jawbreaker)
- Mining continues toward the west entrance of Lyon Station.
- Cavern reinforcement progresses with rockbolt installation, shotcrete and the construction of a lower level support system.
- Ongoing mining in drifts is anticipated until December 2014.
Central Shaft (Chewrocka)
- Ongoing mining in drifts progresses west toward Lyon Station.
- Construction of a lower level support system advances as does formwork and support.
- Installation of storm sewers and conduits continue.
Ongoing mining in drifts progresses west in Lyon Station cavern
East Portal (Crocodile Rouge)
- Roadheader is in the transition[i] to Rideau Station cavern.
- Shotcreting and rockbolt installation continue as mining progresses toward Rideau Street.
- Cavern excavation is anticipated to begin as early as late December.
Shotcreting and rockbolting continue as mining from East Portal progresses toward Rideau Street
For weekly updates on tunnel excavation progress please visit the
Roadheader page.
East Segment
Belfast Yard
Long-term closure of Belfast Road, south of Tremblay Road to Trainyards Drive and north of Tremblay Road to Coventry Road continues.
Belfast Yard Administration and Maintenance Building
- Main structural steel erection on the Belfast Yard shed is completed.
- Ongoing masonry work continues in advance of building envelope works scheduled to begin in the coming weeks.
- Site utilities are ongoing north and south of Belfast Road.
- Roofing will be ongoing throughout the winter months.
Masonry work continues on the Administration and Maintenance building at Belfast Yard
Belfast Yard Connector – Works on the Belfast Yard connector, which will allow vehicles to travel to and from the Light Rail Transit (LRT) track to Belfast Yard, advance and include:
- Installation of whalers[ii]
- Formwork, reinforcement, placing concrete and excavation
- Work in support of removal of the steel bridge (Verona System) for the temporary VIA Rail track support systems, including sliding a precast concrete box under the VIA rail tracks, is underway.
Hurdman Station (Station construction is scheduled to begin as early as spring/summer 2015)
- Elevated guideway work for the future Hurdman Station is ongoing until the New Year and includes piling and drilling caissons north of the existing Hurdman Station.
Drilling caissons at Hurdman Station
Civic Works
Highway 417 Roadwork, Widening and Structure Rehabilitation
Roadworks
- Work on median lanes including median barrier wall removal, excavation, drilling of median foundations, pouring median walls and sewers continue along Highway 417.
- Panel installation on the retaining wall progresses along the highway.
- Ongoing light pole installations progress and include wiring, boring[iii], and pouring of concrete footings.
- Intersection work at St. Laurent and Lemieux streets is scheduled to be completed in November and consists of electrical work, curbs and island reconfiguration.
- Roadway excavation, milling[iv], placing and compacting granular is ongoing along the highway as grading work at Robinson Avenue advances.
- Winter preparations along the highway continue.
Median lane rehabilitation continues along Highway 417
Signage
- The three message signs have been installed and are expected to be operational shortly. Ongoing testing is being conducted by the Ministry of Transportation.
Structures
- Widening, reconstruction and rehabilitation of various bridge structures advance along the highway. Final works are ongoing at the Lees Avenue underpass, the Vanier Parkway overpass and on the St. Laurent overpass.
Lees Avenue Underpass
- Pouring, stripping and forming of the retaining wall continues at Lees Avenue underpass as well as installation of precast panels[v] and other final works.
- Site cleanup begins.
Pouring, stripping and forming of the retaining wall at Lees Avenue underpass
Hurdman Bridge
- Reconstruction of the structure’s median span is ongoing with installation of panels at the abutments.
- The placement of reinforcing steel at the east and west abutments continues.
- Closures of the east and west multi-use pathways continue as abutment work and headwall[vi] work progress (sign up for e-updates at [email protected])
Forming of the media span continues at Hurdman Bridge
Vanier Parkway Overpass
- Ongoing works at Vanier Parkway overpass progress and include backfilling, forming and curing of concrete.
- Rehabilitation works for Vanier Parkway roadway are ongoing until the end of November and consist of completing paving and final intersection lighting works.
Backfilling, forming and curing of concrete continues at Vanier Parkway overpass
Coventry Pedestrian Footbridge
- Installation of the roofing system and ceiling system[vii] as well as structural steel to support the canopy on the east side of the footbridge advance.
- Concrete pours continue for the next weeks.
- Construction on the south abutment stairs and ceiling progress.
- General site cleanup in anticipation of substantial completion of works by end of the year is underway.
Construction of ramp continues at Coventry Pedestrian Footbridge
Belfast Road Underpass – Reconstruction is ongoing as long-term closure of Belfast Road, north of Tremblay Road to Coventry Road continues.
- Construction continues on the underpass’ median pier and includes curing, stripping and installation of railings on parapet walls.
Installation of railings at Belfast Road underpass progresses
St. Laurent Overpass
- General site clean-up and demobilization is ongoing for the next weeks on the St. Laurent overpass.
Albert Street Civic Works
- Beginning curb installation on Albert Street, City Centre Avenue and Preston Street.
- Placement of Granular A on Albert Street.
- Albert Street Civic Works are scheduled to stop for the season mid-December resuming spring 2015.
Breaking into the brick sewer at City Centre Avenue
Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.
[i]Transition refers to the area between the running tunnel and the station cavern.
[ii] Whalers are horizontal reinforcement used to secure upright structures, such as formwork for the pouring of concrete.
[iii] Boring refers to the act or process of enlarging a hole.
[iv] Milling refers to the process of removing asphalt pavement with a machine.
[v]Precast concrete is concrete that is made in a reusable mold or “form” which is then transported to the construction site and lifted into place. In contrast, standard concrete is poured into site-specific forms and cured on site.
[vi]Headwall refers to the small retaining wall placed at the outlet of a culvert or stormwater pipe.
[vii]A suspended ceiling is a secondary ceiling, hung below the main (structural) ceiling that is used for the structure’s infrastructure, including piping, wiring and/or ductwork.