Originally Posted by Philly Fan
What will that be, about 50-60 truckloads? Or will they be using higher capacity trucks?
|
Started at 4 AM....Standard load is 10 CY per truck in PA (max load on the highway). Ran about 8 trucks an hour, one pump running pretty much non-stop, last clean-up load of 4 CY went in at 10:30.
Ambient was about 26 at 4, 35 at 10 AM, Concrete temps were about 45 deg F at delivery, as it sets up and starts to hydrate it will get much warmer. The middle of the concrete in the mat was 64 deg F at 12:30, will be read again at 4 or 5. This is what the engineer classified as a "mass pour" so he is very concerned about maximum temperature in the center, the difference between the center and at the sides and top, and how fast it cools down. The whole deal is being covered with insulation for the night to keep it warm.
The balance of the mat should be ready to pour just before or after Thanksgiving........there is a lot of reinforcing to set.
Any questions? Beuller? Beuller?