I'm curious why these smaller, 6 ish floor buildings say that they need roughly 18 months to build then?
|
Services (water, sewer, electrical, gas), permitting, excavation, landscaping, roofing, paving & curbs.
Just to name a few, all have nearly the same schedule duration for a big (tall) job as they do for a small one (similar scope too).
Remember, the trades can chase each other in the tall jobs. You can't paint, floor, millwork, hang doors, install sinks and install lights at the same time & place, they'd kill each other. Not to mention they might ruin the electricians hair - they can be really touchy about that.