Construction Summary
Week of June 29
Central Segment
Tunnel
West Portal (Jawbreaker)
- The roadheader continues excavating in drifts in the Lyon Station cavern.
- Cavern reinforcement is ongoing and includes umbrella and mesh installation, grouting, and shotcreting.
Spile installation underway at the West Portal
Central Shaft (Chewrocka)
- Mining of the Parliament Station cavern transition begins in drifts
- Pouring of a section of the mud slab was completed.
- Tunnel reinforcement continues, including umbrella and mesh installation, and shotcreting.
East Portal (Crocodile Rouge)
- Installation of tunnel support, including rockbolts and spiles[i], continues as mining advances north under Laurier Street.
For weekly updates on tunnel excavation progress please visit the Roadheader page.
East Segment
Maintenance and Storage Facility(MSF)
Construction activities advance at the MSF as long-term closure of Belfast Road south of Tremblay Road to Trainyards Drive north of Tremblay Road to Coventry Road is ongoing.
- Site utilities, storm sewer work and backfilling continues.
- Excavation progresses on the MSF building foundation.
- Works for the MSF connector are ongoing, including bridge parapet removal, stripping of topsoil, and utilities locates with the VIA right of way.
- Ongoing MSF connector activities include shoring, piling, and the installation of monitoring equipment.
Civic Works
Highway 417 Roadwork, Widening and Structure Rehabilitation
Roadworks
- Utilities and sewer work is ongoing along the north and south sides of the highway.
- From St. Laurent Boulevard to Vanier Parkway panel work progresses for the sound wall along the north and south sides of the highway.
- Roadway construction continues with excavation, milling[ii], paving, grading and pouring of concrete barrier walls along the north and south sides of Highway 417 from St. Laurent Boulevard to Nicholas Street.
Highway 417 roadway construction and noise wall installation continues
Signage
- The three message signs have been installed; final construction and electrical works to power the signs continue.
Structures
- Widening, reconstruction and rehabilitation of various bridge structures along the highway continues to progress.
Hurdman Bridge
- Stripping and waterproofing of the deck continues.
- Construction of the approach and support slabs is underway.
Work continues on Hurdman Bridge deck, seen here with barriers poured
St. Laurent Overpass
- Widening and rehabilitation of the structure is ongoing on the south side, with forming[iii] and pouring, rebar installation and stripping.
- Reconstruction progresses on the north and south off-ramps and includes paving.
- Installation of the noise wall continues at the northwest on-ramp.
Vanier Parkway Overpass– work advances in preparation of the rapid bridge replacement scheduled for mid-October 2014.
- Work continues in the staging area and includes completing placing reinforcing steel and brackets.
- Forming and pouring of support column bases is underway.
Work continues on the deck in the Vanier overpass staging area
Belfast Road Underpass – Demolition of the existing structure advances as long-term closure of Belfast Road, north of Tremblay Road to Coventry Road continues.
- Formwork and pouring continue at the north and south abutments.
- Sawcutting as well as the removal of existing barrier walls, deck and girders is ongoing.
- Installation of the north span underdecking is underway.
Belfast Road Bridge rehabilitation and deck stripping
Belfast Road Bridge rehabilitation and MSF connector track site preparation are underway
Lees Avenue Underpass
- Work on the new deck progresses, including stripping of the formwork.
- Granular and sewer work is ongoing on Robinson Road.
- Installation of steel ties in preparation of the sidewalk, as well as pouring of the sidewalk occur.
Work advances on Lees Avenue new underpass structure, seen alongside with the old, removed deck
Coventry Pedestrian Footbridge
- Stripping and pouring are ongoing on the south abutment and footing.
- Formwork and pouring occur on the north ramp footing.
Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.
[i] Spiles refer to the protective pipe canopies installed to support the tunnel structure.
[ii] Milling refers to the process of removing asphalt pavement with a milling machine.
[iii] Formwork refers to a mold in which concrete is poured.
http://www.confederationline.ca/en/#target6305