Quote:
Originally Posted by officedweller View Post
Investigation Report for that shifting guideway segment at Como Lake Road posted here. It says the section was always intended to be part of a continuous span section, so there were no risers on top of the columns.
Very interesting, thanks for posting!
     
     
  #6842  
Old Posted Jun 14, 2014, 6:05 AM
adrianroam95 adrianroam95 is offline
Registered User
 
Join Date: Aug 2010
Location: Coquitlam, BC
Posts: 214
Crude photo I captured today while they blocked off northbound lanes for 5 minutes or so to facilitate construction. Guideway segments are being lifted up right as we speak in the section between the third and fourth northernmost columns in the median of North Road. In other words, as you can see in the image, the guideway is now only two columns away from Foster Ave.

     
     
  #6843  
Old Posted Jun 14, 2014, 4:06 PM
finalcoolman finalcoolman is offline
Registered User
 
Join Date: Nov 2004
Posts: 262
Quote:
Originally Posted by queetz@home View Post
But given the sheer amount of *discussion* that has gone throughout the years, and the whining and complaining about how the Lougheed guideways are turning up right now, I think such a headache is worth it for the long term so things will remain....pretty.
I think you are overblowing this queetz. Yes the Lougheed station spur was kind of an eyesore because it was visible from almost everywhere. It was visible from all along Gatineau St, from the bus loop, from the Sears outlet centre & parking lot, from the White Spot, from the Lougheed Mall parking lot, from the Shell Station, etc... However, the spur at Coquitlam Station will be tucked in behind the station in-between the station and some trees that line the West Coast Express Station. You wont be able to see it from anywhere unless you actually trek south of the station towards the trees or are actually walking as a pedestrian on the Mariner overpass. It's pretty hard to see anything from a vehicle on the overpass unless you are riding in a really high vehicle. You wont even be able to see it from the West Coast Express station as it is clear from the pics the trees will block the view from the WCE platform. I'm glad they are building it.
     
     
  #6844  
Old Posted Jun 14, 2014, 9:26 PM
nname nname is offline
Registered User
 
Join Date: Aug 2005
Posts: 5,076
Quote:
Originally Posted by officedweller View Post
These photos are actually about 1 to 2 months old -

Guideway approaching Inlet Centre - they are already working on the deck on top of the I-beams

Burquitlam - Guideway is now past the curve in the pic.

Tunnel Portal - According to the presentation to the council, they are already laying tracks in this area

Lincoln Stations - All columns around the station are completed. They are now working on the Pinetree crossing

Lafarge Lake - They are currently building the stairs between street and platform level.
     
     
  #6845  
Old Posted Jun 14, 2014, 10:04 PM
GlassCity's Avatar
GlassCity GlassCity is offline
Rational urbanist
 
Join Date: Aug 2012
Location: Metro Vancouver
Posts: 5,270
Are there still plans for future stations at Queens and Falcon or has that been shelved? Or maybe are there new locations for infill stations?
     
     
  #6846  
Old Posted Jun 14, 2014, 10:40 PM
red-paladin red-paladin is offline
Vancouver Moderator
 
Join Date: Sep 2008
Location: Burnaby
Posts: 3,626
Quote:
Originally Posted by GlassCity View Post
Are there still plans for future stations at Queens and Falcon or has that been shelved? Or maybe are there new locations for infill stations?
West Port Moody and Falcon are being built to accomodate future stations.
     
     
  #6847  
Old Posted Jun 14, 2014, 10:42 PM
dpogue dpogue is offline
Registered User
 
Join Date: Aug 2013
Posts: 766
Quote:
Originally Posted by queetz@home View Post
But since its going to be there regardless of how I feel, I think they should try to make it look less of a spur. Perhaps make it part of a platform or something with a food cart or gift shop, add some temporary structure on top to hide it, and so on. The Lougheed Station spur prior to the Evergreen Line contruction has been such a huge pet peeve of mine, just couldn't stand it for over a decade...
I think a decent option would be built it out long enough to park a 6-car Mark I or 5-car Mark II and use it as a pocket track until/if the line gets extended. A few metres of unused guideway aren't enough to be useful, but a pocket track could at least be used for storage or training in the meantime.
     
     
  #6848  
Old Posted Jun 14, 2014, 10:45 PM
GlassCity's Avatar
GlassCity GlassCity is offline
Rational urbanist
 
Join Date: Aug 2012
Location: Metro Vancouver
Posts: 5,270
Quote:
Originally Posted by red-paladin View Post
West Port Moody and Falcon are being built to accomodate future stations.
Great to hear, thank you.
     
     
  #6849  
Old Posted Jun 14, 2014, 11:28 PM
gkz gkz is offline
Registered User
 
Join Date: Jul 2013
Posts: 71
How much would an extension to PoCo station cost? 2.5km following the existing rail right of way - it doesn't seem it would be that expensive
     
     
  #6850  
Old Posted Jun 14, 2014, 11:35 PM
finalcoolman finalcoolman is offline
Registered User
 
Join Date: Nov 2004
Posts: 262
Quote:
Originally Posted by dpogue View Post
I think a decent option would be built it out long enough to park a 6-car Mark I or 5-car Mark II and use it as a pocket track until/if the line gets extended. A few metres of unused guideway aren't enough to be useful, but a pocket track could at least be used for storage or training in the meantime.
You know that's how I always felt about the third platform at Lougheed station. Why oh why were the tracks not installed in the third platform guideway all these years so it could have actually been used to store a train like Stadium station for the past decade. That's something that always boggled my mind.

As for Coquitlam station, being the closest station to the new storage facility I dont think the ability to store a train would be useful.
     
     
  #6851  
Old Posted Jun 15, 2014, 11:33 PM
adrianroam95 adrianroam95 is offline
Registered User
 
Join Date: Aug 2010
Location: Coquitlam, BC
Posts: 214
Quote:
Originally Posted by gkz View Post
How much would an extension to PoCo station cost? 2.5km following the existing rail right of way - it doesn't seem it would be that expensive
A one station extension to downtown Port Coquitlam could become a reality in the future, after Broadway and Surrey are taken care of. In terms of cost, I would estimate it to be roughly about $175-200 million using statistics that indicate the cost of SkyTrain per kilometre, which in the case of the Millennium Line, was around $70 million/km in 2012 dollars.

Anyway, here's a pic I took from Henderson Place of Lincoln Station on June 14th:

     
     
  #6852  
Old Posted Jun 16, 2014, 5:07 AM
xd_1771's Avatar
xd_1771 xd_1771 is offline
(daka_x)
 
Join Date: Aug 2010
Location: Metro Vancouver, Canada
Posts: 1,740
Quote:
Originally Posted by adrianroam95 View Post
A one station extension to downtown Port Coquitlam could become a reality in the future, after Broadway and Surrey are taken care of. In terms of cost, I would estimate it to be roughly about $175-200 million using statistics that indicate the cost of SkyTrain per kilometre, which in the case of the Millennium Line, was around $70 million/km in 2012 dollars.
I can guarantee all of you that it's going to be lower than even this. And when it comes, I think it'll be an interesting indicator of the raw costs of elevated guideway.

The Milllennium Line's costs did account for fancier stations, a brand new fleet, testing for this brand new fleet, some Expo Line refits for this brand new fleet, OMC expansions for this brand new fleet, some tunnel sections in addition to the components you would expect, and traffic management (since huge portions were built over-street; whereas just about the entirety of a Port Coquitlam extension would be built over a railway ROW with next to no property acquisition and property management requirements and little in terms of fleet requirement).

Honestly, I see the affordability prospect of a PoCo extension to be so good that I can imagine an extension of the line coud continue down Kingsway Ave and terminate in front of the Coast Meridian Overpass. Maybe even further, but that extent should be enough.
     
     
  #6853  
Old Posted Jun 16, 2014, 7:44 PM
queetz@home's Avatar
queetz@home queetz@home is offline
Go Rotem! Die Bombardier!
 
Join Date: Jul 2001
Location: Ortigas
Posts: 3,679
Quote:
Originally Posted by xd_1771 View Post
I can guarantee all of you...
Sure...I'm sure you must have some magical crystal ball out there that gives you infinite knowledge of the future...

Quote:
Originally Posted by adrianroam95 View Post
Crude photo I captured today while they blocked off northbound lanes for 5 minutes or so to facilitate construction. Guideway segments are being lifted up right as we speak in the section between the third and fourth northernmost columns in the median of North Road. In other words, as you can see in the image, the guideway is now only two columns away from Foster Ave.

The guideway segment from this pic is still not 100% complete, its actually missing one piece of as this morning, but it should be completed for today. I think the crane and possibily the guideway segment will be over Foster Avenue by the end of the week at the rate they are going.

One thing interesting I saw this morning was the Lougheed steel guideway. The end part by Gatineau Place is now covered in concrete. But sadly, I wasn't able to take a pic because a truck was blocking my view when the light was red.
     
     
  #6854  
Old Posted Jun 17, 2014, 3:50 AM
DKaz DKaz is offline
Registered User
 
Join Date: Nov 2008
Location: Kelowna BC & Edmonton AB
Posts: 4,299
Quote:
Originally Posted by giallo View Post
This is pretty cool. It looks like local rapper Snak The Ripper filmed part of his video at an Evergreen Line construction site.


Video Link
Love this song. Feels like my current life anthem.

The slow-mo spitting at the Skytrain station was disgusting tho, but good video otherwise. Down to earth real hip hop.
     
     
  #6855  
Old Posted Jun 18, 2014, 12:06 AM
adrianroam95 adrianroam95 is offline
Registered User
 
Join Date: Aug 2010
Location: Coquitlam, BC
Posts: 214
The evergreen line gantry crane has collapsed on North Rd. North Road is shut down.
     
     
  #6856  
Old Posted Jun 18, 2014, 12:31 AM
queetz@home's Avatar
queetz@home queetz@home is offline
Go Rotem! Die Bombardier!
 
Join Date: Jul 2001
Location: Ortigas
Posts: 3,679
Quote:
Originally Posted by adrianroam95 View Post
The evergreen line gantry crane has collapsed on North Rd. North Road is shut down.
I heard on the radio on my way home. Wow! What a hassle! I guess we won't be seeing the guideways at North Road completed by summer...

From Global News

     
     
  #6857  
Old Posted Jun 18, 2014, 12:47 AM
jsbertram jsbertram is offline
Registered User
 
Join Date: Sep 2009
Posts: 3,245
Quote:
Originally Posted by queetz@home View Post
I heard on the radio on my way home. Wow! What a hassle! I guess we won't be seeing the guideways at North Road completed by summer...

From Global News

http://forum.skyscraperpage.com/showpost.php?p=6604555&postcount=5602

shows how it is supposed to sit on the concrete base.

It appears those snaps show the crane system just two concrete bases north of the failure location.
     
     
  #6858  
Old Posted Jun 18, 2014, 1:19 AM
VancouverOfTheFuture's Avatar
VancouverOfTheFuture VancouverOfTheFuture is offline
Registered User
 
Join Date: Apr 2014
Posts: 3,481
are they really cutting corners with the E line construction? this isn't a new process of building guide-ways in the GVRD.

i don't remember the millennium line construction, but for the Canada Line they were going a lot faster (if i remember right about 1 section every 3-4 days). i don't remember any of these "failures" happening with that. yet there have been 2 relatively close together.
     
     
  #6859  
Old Posted Jun 18, 2014, 1:32 AM
Meraki Meraki is offline
Registered User
 
Join Date: Mar 2012
Posts: 473
Quote:
Originally Posted by VancouverOfTheFuture View Post
are they really cutting corners with the E line construction? this isn't a new process of building guide-ways in the GVRD.

i don't remember the millennium line construction, but for the Canada Line they were going a lot faster (if i remember right about 1 section every 3-4 days). i don't remember any of these "failures" happening with that. yet there have been 2 relatively close together.
These incidents combined with the wildly varying spacers between column and guideway start to paint a picture of corner cutting or incompetence.
     
     
  #6860  
Old Posted Jun 18, 2014, 6:39 AM
queetz@home's Avatar
queetz@home queetz@home is offline
Go Rotem! Die Bombardier!
 
Join Date: Jul 2001
Location: Ortigas
Posts: 3,679
The funny thing is the media has hardly been covering this, especially compared to the Como Lake incident. I guess the Enbridge pipeline approval is grabbing all the headlines, or maybe this incident is simply not that big a deal and things will be back to normal tomorrow?

From the Province....



Except for the crushed platform seen at the right, it seems the gantry is okay and being moved forward per normal. We shall find out in the morning, I guess...

Last edited by queetz@home; Jun 18, 2014 at 6:50 AM.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 3:49 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.