Confederation Line update:
Construction Summary
Week of May 11
Central Segment
Tunnel
West Portal (Jawbreaker)
- The roadheader continues excavating the full face of the Lyon Station Cavern in drifts[i], under Queen Street and Lyon Street.
- Tunnel reinforcements and shotcreting are ongoing in the station cavern.
Central Shaft (Chewrocka)
- Installation of the first umbrella was completed for Parliament Station cavern, as mining progresses in the station cavern.
- The roadheader is now past Bank Street (under Queen Street).
Picture of the Roadheader progressing from central shaft
East Portal (Crocodile Rouge)
- Tunneling works advance as mining continues through concrete.
- Twenty-four hour tunneling recommences as installation of the new initial support occurs to allow mining of the full tunnel face to resume mid-month.
Tunneling works progress at East Portal
East Segment
Maintenance and Storage Facility (MSF)
- Utilities excavation continues.
- Excavation progresses on the MSF building foundation.
- Signage and detour notifications have been installed in preparation of the upcoming full closure of Belfast Road scheduled to begin May 20, 2014.
Civic Works
Highway 417 Roadwork, Widening and Structure Rehabilitation
Roadworks
- Boring and sewer work progresses on the north and south side of the highway.
- From St. Laurent Boulevard to Vanier Parkway, drilling of piles, pouring and panel work progresses for the sound wall footings along the south side of the highway, while on the north side grading continues and drilling for the noise wall begins.
Equipment installation for electrical boring
Signage
- The three message signs have been installed; final construction and electrical works to power the signs continue.
Structures
- Widening, reconstruction and rehabilitation of various bridge structures along the highway continues to progress visibly.
Hurdman Bridge
- Preparation for pouring of the new deck occurs on the north side of the structure, as reconstruction advances.
- Formwork[ii] and rebar installation continue at the ends of the deck on the north side of the bridge as formwork and support brackets installation occur on the south side deck.
Hurdman Bridge parapet wall construction advances
St. Laurent Overpass
- Widening and rehabilitation progresses on the south side of the structure with chipping of the deck ends.
- Work continues on the roadway protection wall at the south side of the overpass.
- Shoulder and on-ramp reconstruction advance.
Shoulder reconstruction progresses at St. Laurent overpass
Vanier Parkway Overpass– work advances in preparation of the rapid bridge replacement scheduled for fall 2014.
- Work progresses in the staging area as girder installation begins, which will be followed by installation and forming of the new deck in the next few weeks.
- Reconstruction work on a section of the westbound on-ramp s completed this week, while work on the eastbound on-ramp continues.
- Refacing work continues on the abutments as overpass rehabilitation progresses.
Shoulder reconstruction advances at Vanier Parkway overpass
Belfast Road Underpass– work advances in preparation for conventional demolition of the existing structure and reconstruction of the new bridge.
- Forming of the new wing wall[iii] occurs this week.
- Piling occurs on the new retaining wall as temporary rehabilitation work advances on the existing structure.
Lees Avenue Underpass – work advances in preparation of the rapid bridge replacement.
- Construction of the new bridge components is ongoing in the staging area, including forming of the new deck.
Deck formwork continues at Lees Avenue staging area
Coventry Pedestrian Footbridge– pier and abutment work progresses in preparation of the superstructure installation scheduled for June.
- As work has advanced on the north abutment, extension of the south abutment footing occurs this week.
Structural steel for the Coventry Pedestrian footbridge
Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.
[i]Drifts refer to the sections of the wider station cavern that are excavated in sequence as per diagram below.
[ii] Formwork refers to a mold in which concrete is poured.
[iii] Wing wall refers to a wall at the abutment of a bridge, extending beyond the bridge to restrain soil to unnatural slopes.
and
]
Construction Summary
Week of May 18
Central Segment
Tunnel
West Portal (Jawbreaker)
- The roadheader continues excavating the full face of the Lyon Station Cavern in drifts[i], under Queen Street and Lyon Street.
- Drilling of the support umbrella and shotcreting begins.
Central Shaft (Chewrocka)
- Installation of the second umbrella of Parliament Station cavern begins this week, which will be followed by excavation and return east to complete excavating the bottom, refered to as the bench. Once bench is mined, the mud slab will be poured. These activities will be ongoing for the coming weeks.
Drilling the umbrella (entry from Central Shaft)
East Portal (Crocodile Rouge)
- Installation of the second support has been completed.
- Twenty-four hour tunneling continues in the full tunnel face.
For weekly updates on tunnel excavation progress please visit the
Roadheader page.
East Segment
Maintenance and Storage Facility (MSF)
Construction activities ramp up at the MSF as long-term closure of Belfast Road south of Tremblay to Trainyards Drive begins.
- Utilities and storm sewer work continues.
- Excavation progresses on the MSF building foundation.
- Mobilization of equipment, installation of trailers, fencing, decommissioning of utilities and stripping of asphalt will begin this week.
Pouring of foundation walls at the MSF
Civic Works
Highway 417 Roadwork, Widening and Structure Rehabilitation
Roadworks
- Boring and sewer work progresses on the north and south side of the highway.
- From St. Laurent Boulevard to Vanier Parkway, drilling of piles, pouring and panel work progresses for the sound wall footings along the south side of the highway. On the north side grading continues and drilling for the noise wall begins.
- Roadway construction continues and includes excavation, grading, casting of concrete barrier walls and paving along the north and south sides of Highway 417 from St. Laurent Boulevard to Nicholas Street.
- Installation of high mast light poles occurs.
Casting in place of concrete barrier walls along south side of Highway 417
Preparation to pour pole base for luminaires along south side of highway
Signage
- The three message signs have been installed; final construction and electrical works to power the signs is ongoing.
Structures
Widening, reconstruction and rehabilitation of various bridge structures along the highway continues to progress visibly.
Hurdman Bridge
- Pouring of the new deck occurs on the north side of the structure as reconstruction advances.
- Installation of rebar and rails continue on the south side deck.
Hurdman Bridge pouring of north deck
St. Laurent Overpass
- Widening and rehabilitation on the south side of the structure progresses with chipping of the deck ends.
- Abutment work continues and includes backfilling and pouring of ballast wall[ii].
- Work continues on the roadway protection wall at the south side of the overpass.
- Shoulder and on-ramp reconstruction are ongoing.
Chipping of deck ends continues at St. Laurent Boulevard overpass
Chipping of deck ends continues at St. Laurent Boulevard overpass
Vanier Parkway Overpass– work advances in preparation of the rapid bridge replacement scheduled for fall 2014.
- Work progresses in the staging area as girder installation continues. Installation and forming[iii] of the new deck will follow in the next few weeks.
- Overnight roadwork continues on the on-ramps.
- Forming and concrete pouring for wing walls[iv] occurs this week.
Grading operations continue at the Vanier Parkway N-E on-ramp
Belfast Road Underpass– work advances in preparation for conventional demolition of the existing structure and reconstruction of the new bridge.
- Forming of the parapet wall[v] begins.
- Piling continues for the retaining wall as temporary rehabilitation work advances on the existing structure.
- Variable message signs indicating upcoming closure on Belfast Road, north of Tremblay Road to Coventry Road, have been installed and will powered this week.
Lees Avenue Underpass – work visibly progresses in the staging area in preparation of the rapid bridge replacement.
- Construction of the new bridge components is ongoing in the staging area, including forming of temporary footings for the existing structure.
- Rebar installation occurs on the new bridge deck.
- Preparatory work continues in advance of existing structure removal by rapid removal during a two-day period on June 21 and 22, 2014.
Rebar installation on new deck at Lees Avenue staging area
Coventry Pedestrian Footbridge – pier and abutment work progresses in preparation of the superstructure installation.
- Work has advanced on the north abutment, extension of the south abutment footing occurs this week, and includes forming as well as pouring of south side abutment walls.
Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.
[i]Drifts refer to the sections of the wider station cavern that are excavated in sequence as per diagram below.
[ii] Ballast wall refers to a wall built on the top of an abutment
[iii] Formwork refers to a mold in which concrete is poured.
[iv] Wing wall refers to a wall at the abutment of a bridge, extending beyond the bridge to restrain soil to unnatural slopes.
[v] Parapet wall refers to a protective barrier on the side of a bridge.