Quote:
Originally Posted by someone123
Setting aside the fact that the province has the authority to circumvent HRM planning rules, there was also a tendering process for the convention centre. Thiel Group could have put in a bid too. Rank isn't getting random special treatment, they are the ones who won the bid to build a public development.
|
sort of. Rank owned the site, the site was designated for the convention Center, so rank was really the only eligible bidder and it was basically sole sourced.
did anyone notice that starfish opposed the extension of the development agreement for the zellers building, since they got the roy started on time.
i think its a thing developers have - if someone else gets an exception, and they didnt, they think its unfair.
besides didnt trilluim start work before they had all their approvals, and got a fine?