Quote:
Originally Posted by electricron
The problem with high level buses is accommodating wheelchair or mobility impaired passengers. It was already going to be difficult for them with split platforms on different on/off ramps having to cross the highway to reach park & ride lots. I've never liked the US36 BRT station plans.
|
The US 36 Project as well as almost all of RTD infrastructural efforts is reverse engineered from a bottom line cost, not from public need.
The issue on US 36 was to get a special transportation package of some kind to serve the Boulder-Denver corridor quickly (and finally). This had become political dynamite for RTD, as by not putting Boulder in the infrastructural build out loop, RTD was creating a group of educated, vocal, and, angry voters.
A bit of background:
The BNSF railroad through clever cost escalations, ruled out the possibility of direct rail service to Denver. Skyrocketing cost estimates, combined with CDOT politics and the horrible Goldman Sachs brokered financial agreement to privatize much of the construction and road maintenance on US 36, have resulted in a slow, but steady stripping away of BRT features.
Conclusion:
Of course, all this financial retrenchment will be excused with highly specific surveys whose format will skew survey data towards conclusions that RTD wants. A good example of this might be how high level buses are desired on the route from a survey of Boulder to Denver commuters without including those who might want to use the service for on a segment of the US 36 route.
I expect the BRT built along US 36 to be ineffectual, and, something one might expect to be built in 2014 in Lagos, Nigeria, not in Mumbai, India.