The new Hamilton stadium will be ready in time for the Ticats home owner, the builder announced on Tuesday
Garreth Barkey, site supervisor for Ontario Sports Solutions, the consortium building the $145-million stadium, said he expects to have the facility prepared for the July 26 game versus the Ottawa Redblacks.
"I'm confident that we're going to make the date," Barkey said.
The stadium is about three weeks behind schedule, Barkey said, and while it was originally slated to be delivered by June 30, Barkey acknowledged they won't hit that target. Instead, they are aiming for "substantial completion" in late July with the finishing touches added over the ensuing two to eight weeks.
"Substantial completion means you're watching a game in the stadium," Barkey said "There could some areas that need a final coat of paint, some of the exterior landscaping may not be planted but as a fan, you'll come and see the Ticats and enjoy a good fan experience."
Ticat team president Glenn Gibson said he doesn't think fans will mind if the stadium is still in need of a little spit and polish.
"I think 80 per cent of fan enjoyment comes from seeing our team win - that's a strong pull towards customer satisfaction," Gibson said. "I think the other 20 per cent is amenities, food and beverage and things like that.
"I think fans are just going to be so happy to be in a stadium, they'll be forgiving on the little things."