Was the tunnel in the Chiarelli official plan for phase 2 or is that an assumption you are making based on the needs of downtown? (I admit I didn't live in Ottawa back then so I'm not quite as aware of all the older details some people here probably are).
Regardless wouldn't building a surface line for LRT downtown and putting in the infrastructure for it and then building a tunnel after have been kind of redundant and a waste of money (though cancelling the original contract still was a waste as well....). I'm assuming (which is probably fairly realistic) that the tunnel would have become necessary sooner rather than later. I don't consider the 2 to 3 minute transfer period to be a big deal either.
On needing more capacity to deal with the combined western LRT and O Train traffic under the current plan we'd have had to deal with some of it anyways since the number of bus routes going downtown from the west would probably have been reduced with LRT under the original plan. Meaning a lot of people transferring from buses to LRT around Bayview anyways. Possibly the same with buses coming from the east as well. (Plus if the number of buses wasn't reduced then we'd likely have a big problem with the sections of merged bus/LRT lanes.)
I agree to some extent on the limitations of the O Train and having a single track, even with the plan to double track a few more areas. That being said I think getting the downtown tunnel done and the east-west focus is probably a bit more important as a starting point. While I admit it doesn't expand the area transit service covers as much LRT is a considerable improvement from the present bus system (I believe you agree on that considering what I've seen in past posts).
Capacity on the O Train is less of a pressing issue from what I can tell. While it is anecdotal I end up riding the O Train frequently (probably at least a few times a week) and I rarely see it absolutely filled to capacity. Definitely more than enough to justify the service but the only times it has generally come close to being full up is around 8 to 8:30 am on week days when all the students (until recently myself included) head to Carleton for morning classes in fall and winter. Even if you extend the O Train a bit further south and add the extra stops at Walkley and Gladstone I don't think capacity on the O Train will be a problem for the medium term future once frequency is up to 8 minutes. I'm pretty sure the trains themselves also can be expanded to add more passenger space.
Admittedly though the city has foregone building a stronger connection to Barrhaven and Riverside South by cancelling plans for the original O Train extension and now ending the potential extension at Riverside instead of in Barrhaven.
---------------
With service shut downs I assume you mean when something blocks the track or it is closed for maintenance issues. We probably deal with them the same way as in the past, try our best to work around it and add an extra bus route in the interim. Might be a bit obvious but double tracking the whole O Train doesn't insulate it from service disruptions either, even if it does reduce the risk of the whole service going down a bit.
|
Thanks for the reasonable response. I have never tried to be unreasonable. I understand the primary need for east-west service.
Back when the NSLRT project was being chosen, it was all about a logical extension of the a pilot O-Train project that proved to be more successful than anticipated.
The city had already decided to build southward but there was a lack of transportation infrastructure. It was decided to use trains partly on existing track rather than build all sorts of new roads. And today, the south end is growing faster than either Kanata or Orleans. So, the justification still exists today.
I admit the Chiarelli plan was far from perfect. It did not address the downtown congestion problem. However, Bob Chiarelli also said that he was confident that City Council could deal with the issue. Blowing $100M was not the answer to this problem.
While the Chiarelli plan was not perfect, it was far more visionary than what we have today. It addressed the changing patterns of employment and retailing, which is moving to the suburbs. There is a limit to how much employment will be downtown in the future based on the geographical limits of downtown. It was sincerely trying to increase transit modal share. The current plan will have problems maintaining current modal share as the movement of employment to the suburbs will continue to bleed ridership.
I have said repeatedly that the tunnel is a necessity, however, we have perhaps chosen the most expensive approach to address the downtown issue. Before we have run one train from Place d'Orleans to Bayshore, we will have spent $4B. A lot of money to end up with the same rapid transit system as we have today. Yes, it will have more capacity and heads off congestion problems but the average rider will not experience faster service by the time they get out to Kanata or Barrhaven or Orleans or Beacon Hill. Its ability to attract new riders is questionable and City Council realizes that they don't know whether the public will take to the Confederation Line.
My concern with the O-Train relates to further service enhancements and it will be necessary some day. I understand the day to day problems, but I am most concerned about the day when more trains are needed. And this will come sooner now that it has been decided that service will be split to the airport. Every significant upgrade to the O-Train has shut the system down for months. We have to date worked around Carleton schedules because most of the riders are Carleton students but extensions southward will change this. This will further change when direct downtown service on the southeast transitway closes. At the present time, the vast majority of downtown passengers use the southeast transitway because of the direct service and because it is a more direct route to Ottawa U, Rideau Centre and the main office district east of Bank.
I am not a regular O-Train rider but I have been on it when it is very crowded. The current equipment is poorly designed for standing. I experienced that recently. The need for better service is apparent. The future changes will push more riders onto it and if service is extended, ridership will further increase. If trains only run every 16 minutes to Riverside South, those trains will eventually be filled to capacity and then what? If certain trains are at capacity, who cares if they run on time? People will be waiting for the next train. We talk about 2 or 3 minute waits but that only applies to the Confederation Line and only at peak hours.