  #21  
Old Posted Mar 13, 2014, 11:48 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,610
Quote:
Originally Posted by waterloowarrior View Post
appealed to the OMB (lol)
No kidding. Damned if you do, damned if you don't.
Reply With Quote
     
     
  #22  
Old Posted Mar 26, 2014, 9:39 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,252
hearing is June 19, 2014... guess they can't make the original timeline

Quote:
Timeline

Council Approval (2012)
Public Meeting – 23 January 2013
Award contract for Prime Consultant - 28 June 2013
Introduction Meeting – BIA / GCA representatives – 11 July 2013
Design Charette – BIA / GCA representatives – 29 July 2013
Public Meeting 2 – 19 September 2013
Concurrent Site Plan and Zoning Application submissions and approvals - September 2013 to February 2014
Tender construction - December 2013
Award Contract to construct the garage - March 2014
Commence Construction - March 2014
Complete Construction - October 2014
Reply With Quote
     
     
  #23  
Old Posted Mar 27, 2014, 2:41 AM
mac_junkie1's Avatar
mac_junkie1 mac_junkie1 is offline
CharlesOgilvyLtd FACEBOOK
 
Join Date: Mar 2013
Location: Ottawa
Posts: 141
Same company as the Airport Parkway... Does this mean it'll take them 4 years to build the parking garage just to rip it down as soon as its done I wouldn't trust those losers with building anything else in the city. I won't be parking my car in there

Quote:
Originally Posted by waterloowarrior View Post
hearing is June 19, 2014... guess they can't make the original timeline
Reply With Quote
     
     
  #24  
Old Posted Mar 27, 2014, 2:05 PM
Boxster's Avatar
Boxster Boxster is offline
Registered User
 
Join Date: May 2012
Posts: 996
What happened with the Airport Parkway?

Quote:
Originally Posted by mac_junkie1 View Post
Same company as the Airport Parkway... Does this mean it'll take them 4 years to build the parking garage just to rip it down as soon as its done I wouldn't trust those losers with building anything else in the city. I won't be parking my car in there
Reply With Quote
     
     
  #25  
Old Posted Mar 27, 2014, 4:44 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,195
Quote:
Originally Posted by Boxster View Post
What happened with the Airport Parkway?
I think what Mac_junkie1 meant to imply was "Same company as the Airport Parkway pedestrian bridge"
Reply With Quote
     
     
  #26  
Old Posted Mar 27, 2014, 5:34 PM
Boxster's Avatar
Boxster Boxster is offline
Registered User
 
Join Date: May 2012
Posts: 996
Now I get it!

Quote:
Originally Posted by rocketphish View Post
I think what Mac_junkie1 meant to imply was "Same company as the Airport Parkway pedestrian bridge"
Reply With Quote
     
     
  #27  
Old Posted Mar 27, 2014, 7:21 PM
Capital Shaun Capital Shaun is offline
Registered User
 
Join Date: May 2012
Location: Ottawa
Posts: 862
Quote:
Originally Posted by rocketphish View Post
I think what Mac_junkie1 meant to imply was "Same company as the Airport Parkway pedestrian bridge"
Why the hell we we even let that company bid on anything after that fiasco?
Reply With Quote
     
     
  #28  
Old Posted Mar 27, 2014, 7:26 PM
Boxster's Avatar
Boxster Boxster is offline
Registered User
 
Join Date: May 2012
Posts: 996
Because the company has connections...or because we are just waiting for strike number three.

Ever heard of commission Charbonneau?

Quote:
Originally Posted by Capital Shaun View Post
Why the hell we we even let that company bid on anything after that fiasco?
__________________
The Fast One!
Reply With Quote
     
     
  #29  
Old Posted Mar 27, 2014, 7:41 PM
Capital Shaun Capital Shaun is offline
Registered User
 
Join Date: May 2012
Location: Ottawa
Posts: 862
Quote:
Originally Posted by Boxster View Post
Because the company has connections...or because we are just waiting for strike number three.

Ever heard of commission Charbonneau?
Corruption is always a possibility. Another possibility is that the city has no mechanism to legally blacklist a firm with a poor track record.
Reply With Quote
     
     
  #30  
Old Posted Apr 19, 2014, 4:04 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,610
Wow, with the stadium expanded to 30,000-40,0000 seats for the FIFA Women's World Cup and no extra parking off-site...

Quote:
Glebe parking garage delayed

By Carys Mills, OTTAWA CITIZEN April 18, 2014

OTTAWA — Construction of an eagerly anticipated Glebe parking garage has been delayed by a year.

The four-storey parkade, with 149 spots and more space for bikes, was supposed to be finished in October. But construction has now been delayed and the deadline pushed back to November 2015, said Capital ward Coun. David Chernushenko.

The $9.5-million project’s initial timeline was overly optimistic, he said, and a nearby property owner is also appealing the project to the Ontario Municipal Board.

Chernushenko said the OMB hearing is scheduled for June 19.

“We met with (the resident) on several occasions to try to address his concerns,” Chernushenko said. “It would have meant a complete redesign of the garage.”

He said he hopes the city gets a favourable outcome at the board so the new construction schedule is uninterrupted.

“Regardless of what comes out of this (OMB) process, this was going to be a challenge for us. The city is learning its lessons from other projects that haven’t gone well lately,” such as the Airport Parkway bridge, which is expected to be three years late and $4.7 million over its $6.5-million budget.

A third-party review of the garage project found the six-month construction timeline was too short by at least a few months, he said.

Instead of construction starting this spring and ending in time for Christmas shopping on Bank Street, up to 10 months of work will begin early in 2015 and is expected to finish in time for the next year’s holiday season.

The garage, meant to help ease future congestion from Lansdowne Park, will be built on an existing city parking lot at 170 Second Ave.

Chernushenko said he wanted to ensure either the existing lot or new parkade were available during each holiday season.

He said the extra parking demand is projected rather than current, so a short delay isn’t a big problem. He said he has “mixed emotions“ about the delay.

“On the one hand, we did want it to be up and running when Lansdowne opens,“ he said. “On the other hand, I am much happier with a realistic timeline.“

[email protected]
http://www.ottawacitizen.com/life/Gl...786/story.html
Reply With Quote
     
     
  #31  
Old Posted Sep 23, 2014, 10:39 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,252
Reply With Quote
     
     
  #32  
Old Posted Sep 29, 2014, 10:29 PM
ThaLoveDocta ThaLoveDocta is offline
Registered User
 
Join Date: Oct 2010
Posts: 170
Quote:
Originally Posted by J.OT13 View Post
A third-party review of the garage project found the six-month construction timeline was too short by at least a few months, he said.
Find me the guy who can build, start to finish, a multi-storey poured concrete garage in a cold climate in 6 months, and i'll hire him yesterday.
Reply With Quote
     
     
  #33  
Old Posted Nov 6, 2014, 2:48 AM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,252
Hearing cancelled...file closed. Approved
https://www.omb.gov.on.ca/ecs/CaseDe...spx?n=PL140189
Reply With Quote
     
     
  #34  
Old Posted Nov 8, 2014, 10:05 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,195
Appeal of Glebe parkade plans dropped

David Reevely, Ottawa Citizen
Published on: November 7, 2014, Last Updated: November 7, 2014 7:19 PM EST


A city plan to build a parking garage in the Glebe is going ahead after a neighbour gave up on appealing the project to the Ontario Municipal Board.

The four-storey garage, to replace a surface parking lot between Second and Third avenues near Bank Street, was originally supposed to be finished last month. Instead, the appeal of a rezoning the project needed has pushed the start of construction into next spring, with completion now expected in fall 2015.

The appeal never came to a hearing, which means the grounds for the appeal aren’t public. A planned hearing day in June was postponed and a new one in late October was cancelled.

Coun. David Chernushenko said John Kaczmarek, who owns a rental property next door, had sought a full redesign of the garage but was eventually satisfied with a city promise to erect a fence, re-arrange some ventilation, and let him or his tenants park on a corner of the city’s land.

“It’s all water on the bridge now and we’re delighted we can move forward,” Chernushenko said.

The $9.5-million, 150-space garage isn’t needed yet, according to a city parking study, but the city is building it anyway because it expects the Glebe to have a shortage of parking eventually. City staff had suggested charging different rates for parking on Glebe streets — which tend to be more crowded farther south, emptier at the north end of the neighbourhood — might spread cars out and eliminate the need for the garage, but city councillors rejected the idea.

[email protected]
twitter.com/davidreevely

http://ottawacitizen.com/news/local-...-plans-dropped
Reply With Quote
     
     
  #35  
Old Posted Nov 9, 2014, 6:50 PM
S-Man S-Man is offline
Registered User
 
Join Date: Mar 2011
Posts: 1,639
The Glebe is a lot like Westboro, in that almost everyone owns a car, but there are constant demands that no one else park near where they're living.

The funny thing is, a lot of those parked cars are owned by people from other neighbourhoods shopping in Westboro and the Glebe, thus keeping the treasured institutions of their 'hood operational.
Reply With Quote
     
     
  #36  
Old Posted Nov 10, 2014, 8:45 AM
Jamaican-Phoenix's Avatar
Jamaican-Phoenix Jamaican-Phoenix is offline
R2-D2's army of death
 
Join Date: Jun 2007
Location: Downtown Ottawa
Posts: 3,576
Quote:
Originally Posted by S-Man View Post
The Glebe is a lot like Westboro, in that almost everyone owns a car, but there are constant demands that no one else park near where they're living.

The funny thing is, a lot of those parked cars are owned by people from other neighbourhoods shopping in Westboro and the Glebe, thus keeping the treasured institutions of their 'hood operational.
Shh, you're thinking rationally and looking at the bigger picture. Stop it.
__________________
Franky: Ajldub, name calling is what they do when good arguments can't be found - don't sink to their level. Claiming the thread is "boring" is also a way to try to discredit a thread that doesn't match their particular bias.
Reply With Quote
     
     
  #37  
Old Posted Nov 10, 2014, 3:22 PM
kwoldtimer kwoldtimer is offline
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 25,989
Quote:
Originally Posted by S-Man View Post
The Glebe is a lot like Westboro, in that almost everyone owns a car, but there are constant demands that no one else park near where they're living.

The funny thing is, a lot of those parked cars are owned by people from other neighbourhoods shopping in Westboro and the Glebe, thus keeping the treasured institutions of their 'hood operational.
Actually, the Glebites I know were anxious to see the garage built and perturbed by the delay.
Reply With Quote
     
     
  #38  
Old Posted Nov 14, 2014, 4:37 PM
umbria27's Avatar
umbria27 umbria27 is offline
Registered User
 
Join Date: Jun 2009
Location: Ottawa
Posts: 287
Quote:
Originally Posted by kwoldtimer View Post
Actually, the Glebites I know were anxious to see the garage built and perturbed by the delay.
Shh, you're talking about actual Glebites. The imaginary stereotype is preferred on this board.
Reply With Quote
     
     
  #39  
Old Posted Nov 14, 2014, 8:05 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,252
Public art for Glebe Parking Garage
http://ottawa.ca/en/city-hall/public...parking-garage
Reply With Quote
     
     
  #40  
Old Posted Nov 15, 2014, 4:06 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,195
Quote:
Originally Posted by waterloowarrior View Post
Public art for Glebe Parking Garage
http://ottawa.ca/en/city-hall/public...parking-garage
Don't miss your chance to complete the Online Survey after viewing the short-listed designs.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Downtown & Urban Ottawa
Forum Jump



Forum Jump


All times are GMT. The time now is 9:39 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.