Old Posted Feb 5, 2014, 11:40 PM
citydwlr citydwlr is offline
Registered User
 
Join Date: Mar 2013
Posts: 734
A couple updates from the Mayor (via Twitter):

Quote:
LRT progress: The tunnel is now 10% complete, less than one year after we signed the contract. http://jimwatsonottawa.ca/en/lrt-10

Source

Quote:
Four years ago, the future and budget of the LRT project were uncertain. Today, the tunnel is 10% complete.

Source

And there's also some other images/update information from the City of Ottawa Website: http://ottawa.ca/en/ott-city-online/ten-percent-confederation-line-tunnel-construction-done

Last edited by citydwlr; Feb 6, 2014 at 12:21 AM.
     
     
  #802  
Old Posted Feb 6, 2014, 4:54 AM
Catenary Catenary is offline
Registered User
 
Join Date: Dec 2012
Posts: 1,403
It's really great to see frequent updates on this project from the city, with descriptions of what is happening and even definitions of unusual terms. Much better than just a pile of pictures like Metrolinx does in the GTA (Though more pictures are always appreciated).
     
     
  #803  
Old Posted Feb 10, 2014, 6:03 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
Construction Summary
Week of February 2, 2014




Tunneling – The roadheaders are hard at work as we prepare for 24 hour mining at all three access points with 257 metres mined to date.

West Portal (Jawbreaker) (228 metres)
  • Mining continues with tunneling advanced east of Bronson Avenue moving towards Bay Street.
  • Shotcreting to reinforce the tunnel lining and pouring of mud slab are ongoing.

Mining continues:


Central Shaft (Chewrocka) (7 metres of the gallery)
  • Mining is ongoing in the shaft under Queen Street (at Kent Street).
  • Shotcreting and tunnel reinforcing begin.
  • As gantry crane installation is completed, crane testing will occur this week.
  • Work on the tunnel ventilation system continues.

East Portal (Crocodile Rouge) (22 metres)
  • Mining is progressing under Waller Street.
  • With construction on the protective cover completed, Phase 2 of the tunnel umbrella* continues and will be followed by 24 hour mining.
  • Electrical equipment installation continues.

For weekly updates on tunnel excavation progress please visit the Roadheader page.

CIVIC WORKS

Highway 417

Signage
  • Installation of cables and pads to power the three message signs is ongoing.
  • Installation of the sign at Parkdale continues.

Structures

With demolition completed, widening and rehabilitation of various bridge structures are ongoing along the highway.
  • Hurdman Bridge – Phase 1 of demolition has been completed. Next steps include the reconstruction and widening of the footings and the addition of the retaining wall, in preparation for the installation of the bridge girder** in the next weeks.
    • Pouring*** of piers 1 to 4 on the north side continues
    • Curing continues on the northeast and southeast abutments.

Curing a footing:

  • Lees Avenue Bridge – work has begun in preparation of the rapid bridge replacement which will occur later this year.
    • Installation of piles continues in the staging area.
  • St. Laurent Overpass
    • Pouring of support points on which the girder** will eventually rest is ongoing at the north and south piers.
  • Vanier Parkway Overpass
    • Refacing, pouring and curing continues on the south side of the overpass.
  • Coventry Bridge
    • Installation of caissons**** occurs on the north side
    • Formwork*** begins on the south side.

Hurdman Bridge:


Roadworks
  • Sewer work is ongoing along the highway, from Nicholas Street to Vanier Parkway.

Maintenance and Storage Facility (MSF)
  • Construction on the MSF is scheduled to begin this spring. As early as the end February, some site activities, such as equipment mobilization and snow clearing, will begin.

Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

Notes:

*Umbrella refers to a support structure that reinforces the tunnel opening.
**Girder refers to a reinforced concrete beam used a main horizontal support of a bridge.
***Formwork entails pouring concrete into temporary molds to form the pier.
****Caisson installation: a watertight retaining structure used to work on the foundations of a bridge pier.

http://www.ottawalightrail.ca/en#target2888

Last edited by rocketphish; Feb 21, 2014 at 3:57 AM. Reason: Fixed the date.
     
     
  #804  
Old Posted Feb 10, 2014, 6:11 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
Quote:
Originally Posted by rocketphish View Post
  • Coventry Bridge
    • Installation of caissons**** occurs on the north side
    • Formwork*** begins on the south side.
I assume that when they're referring to Coventry Bridge, they're actually talking about the Belfast Rd. bridge over the Queensway. Is that correct? Is that it's official name? Because there are no bridges on Coventry Rd.
     
     
  #805  
Old Posted Feb 10, 2014, 6:52 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,800
Quote:
Originally Posted by rocketphish View Post
I assume that when they're referring to Coventry Bridge, they're actually talking about the Belfast Rd. bridge over the Queensway. Is that correct? Is that it's official name? Because there are no bridges on Coventry Rd.
No, they're talking about the new pedestrian bridge between the Train station and Coventry.

http://ottawa.ca/en/city-hall/public-con...-pathway-between-coventry-road-and-train
     
     
  #806  
Old Posted Feb 11, 2014, 2:50 AM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,806
Quote:
Originally Posted by bradnixon View Post
No, they're talking about the new pedestrian bridge between the Train station and Coventry.

http://ottawa.ca/en/city-hall/public-con...-pathway-between-coventry-road-and-train
I expect you are right. I drove by there yesterday and they are working on it. I hope it turns out better than the South Keys pedestrian bridge.
     
     
  #807  
Old Posted Feb 21, 2014, 3:52 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
Construction Summary
Week of February 16




TUNNEL – Central Segment

Tunneling – We achieved our first of many milestones by mining over 10% of the tunnel; approximately 260 metres to date.

West Portal (Jawbreaker) (over 230 metres)
  • Mining as well as shotcreting and reinforcing the tunnel with bolts continues.
  • Tunneling advances under Queen Street, heading east, near Bay Street.
  • Installation of scrubber* and pouring of the mud slab are ongoing.

Central Shaft (Chewrocka) (over 8 metres)
  • Bench mining continues.
  • Shotcreting and tunnel reinforcements continue.
  • Installation of the tunnel ventilation system is ongoing.

Central shaft:


East Portal (Crocodile Rouge) (over 25 metres)
  • Mining continues moving north, advancing toward Laurier Avenue.
  • Phase 2 of the tunnel umbrella** progresses this week and will be followed by 24 hour mining.
  • Electrical equipment installation is ongoing.

For weekly updates on tunnel excavation progress please visit the Roadheader page.

CIVIC WORKS

Highway 417

Signage

Installation of cables and pads to power the three overhead variable message signs continues until the end of February.

Structures

Widening and rehabilitation of various bridge structures continue along the highway.

Hurdman Bridge – Reconstruction and widening of the footings and the addition of the retaining wall continues, in preparation for the installation of the bridge girder*** anticipated to begin next week.
  • Rebar installation takes place this week on the southwest and southeast abutments and on the north and south pier caps.
  • Installation of support points on which the girder will rest continues on the southeast abutment.

Hoe ramming to remove existing girder 3 - Hurdman:


Lees Avenue Underpass – work has begun in preparation of the rapid bridge replacement.
  • Installation of piles is ongoing for the next few weeks in the staging area.
  • Refacing work continues on the north and south abutments.

St. Laurent Boulevard Overpass
  • Pouring of support points on which the girder*** will eventually rest is ongoing at the northwest corner.

Vanier Parkway Overpass
  • Refacing, pouring and curing continues on the south side of the overpass.
  • Preparatory work for the rapid bridge replacement, scheduled for later this year, begins.

Refacing work - Vanier:


Belfast Road Underpass
  • Refacing work on the north and south abutments continues.
  • Pouring of support points, on which the girder*** will eventually rest, continues at the north and south piers.

Coventry Bridge
  • Installation of caissons**** occurs on the north side.
  • Curing of the newly poured concrete occurs all week at the south side.

Rebar installation - Coventry:


Roadworks

Boring operations and sewer work is progressing along the highway, from Nicholas Street to Vanier Parkway.

Example of boring operations:


Maintenance and Storage Facility (MSF)

Construction on the MSF is scheduled to begin this spring. As early as the end February, some site activities, such as equipment mobilization and snow clearing, will begin.

Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

Notes:

*Scrubbers collect particulate matter or debris as part of tunneling dust mitigation measures.
**Umbrella refers to a support structure that reinforces the tunnel opening.
***Girder refers to a reinforced concrete beam used a main horizontal support of a bridge.
****Caisson installation: a watertight retaining structure used to work on the foundations of a bridge pier.
     
     
  #808  
Old Posted Feb 21, 2014, 3:57 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
Construction Summary
Week of February 16




Central Segment

TUNNEL

West Portal (Jawbreaker – over 250 metres)
  • Mining as well as shotcreting and reinforcing the tunnel is ongoing.
  • Tunneling advances east under Queen Street at Bay Street.
  • The scrubber has been added and installation of the electrical system continues.

Mining the bench at the west portal:


Central Shaft (Chewrocka – over 12 metres)
  • Shotcreting and tunnel reinforcements continue as mining advances to the running tunnel.
  • Removal of debris begins using the gantry crane.

East Portal (Crocodile Rouge – over 28 metres)
  • Installation of lattice girders* to support the umbrella has been completed; 24 hour mining begins this week.
  • Mining under the second umbrella continues.
  • Tunnel reinforcement and electrical equipment installation is ongoing.

Installation of bolts to reinforce tunnel at east portal:


East Segment

Maintenance and Storage Facility (MSF)

Construction on the MSF is scheduled to begin this spring. As early as the end February, some site activities, such as equipment mobilization and snow clearing, will begin.

CIVIC WORKS

Highway 417 Widening and Structure Rehabilitation

Structures

Widening and rehabilitation of various bridge structures progresses as planned along the highway.

Hurdman Bridge
  • Construction of the east and west abutment extensions continues.
  • Work on pier cap support points is ongoing this week.
  • Installation of girders begins mid-week.

Formwork at NW abutment of Hurdman Bridge:


Lees Avenue Underpass – work continues in preparation of the rapid bridge replacement.
  • Installation of piles is ongoing for the next weeks in the staging area.
  • Temporary foundation construction is underway.

Piling at Lees Avenue staging area:


St. Laurent Boulevard Overpass
  • Pouring of support points on which the girder** will eventually rest is ongoing at the northwest corner.
  • Formwork on abutment begins.

Vanier Parkway Overpass
  • Refacing and pouring work continues on the north and south sides of the overpass.
  • Preparatory work continues for the rapid bridge replacement.

Belfast Road Underpass
  • Refacing work on the north and south abutments continues.
  • Formwork and pouring continues.

Roadworks

Boring operations and sewer work is progressing as planned along the highway, from Nicholas Street to Vanier Parkway.

Boring to prepare sewer installation:


Signage

Installation of cables and pads to power the three message signs continues at Parkdale Avenue, Walkley Road and on Blair Road on O.R. 174.

ATMS wiring work at Bayswater:


Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

Notes:

*Lattice girder refers to a reinforced beam used a horizontal support of which the web consists of diagonal pieces crossing each other in the manner of latticework.
**Girder refers to a reinforced concrete beam used a main horizontal support of a bridge.
     
     
  #809  
Old Posted Feb 21, 2014, 3:08 PM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
"THE SKY IS FALLING!" erm.. I mean "THE GROUND IS FALLING... further to the ground...!" "I told you we couldn't dig a tunnel without catastrophe! Billion dollar boondoggle, etc., etc., and so on and so forth."


http://www.cbc.ca/news/canada/ottawa/lar...rail-tunnel-site-cause-unknown-1.2546074
     
     
  #810  
Old Posted Feb 21, 2014, 3:18 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,255
‏@alistairsteele 2m
#OLRT employee confirms to #cbcott tunneling - not watermain - caused collapse on Waller St. "Crocodile Rouge" directly underneath #ottpoli
https://twitter.com/alistairsteele/status/436881845435650048
     
     
  #811  
Old Posted Feb 21, 2014, 3:25 PM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
blerg.
     
     
  #812  
Old Posted Feb 21, 2014, 4:02 PM
MalcolmTucker MalcolmTucker is offline
Registered User
 
Join Date: May 2007
Posts: 11,629
^ That is why one contract delivery works much better - externalize risk.


Confederation Line LRT Ottawa central tunnel shaft gantry crane at night by Odarwin1, on Flickr
     
     
  #813  
Old Posted Feb 21, 2014, 5:10 PM
drawarc's Avatar
drawarc drawarc is offline
Registered User
 
Join Date: Jul 2001
Posts: 471
Quote:
Originally Posted by waterloowarrior View Post
‏@alistairsteele 2m
#OLRT employee confirms to #cbcott tunneling - not watermain - caused collapse on Waller St. "Crocodile Rouge" directly underneath #ottpoli
https://twitter.com/alistairsteele/status/436881845435650048
Kinda scary.
     
     
  #814  
Old Posted Feb 21, 2014, 6:01 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,806
Quote:
Originally Posted by waterloowarrior View Post
‏@alistairsteele 2m
#OLRT employee confirms to #cbcott tunneling - not watermain - caused collapse on Waller St. "Crocodile Rouge" directly underneath #ottpoli
https://twitter.com/alistairsteele/status/436881845435650048
oh oh, as soon as I heard the location, I wondered if there was connection. This has to be worrisome.
     
     
  #815  
Old Posted Feb 21, 2014, 6:03 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
Update: Giant sinkhole closes Laurier Avenue; LRT tunnelling suspended

By Meghan Hurley, OTTAWA CITIZEN February 21, 2014 12:16 PM


OTTAWA — A large sinkhole closed the intersection of Laurier Avenue East and Waller Street and stopped tunnelling work on the East Portal of the city’s LRT project early Friday morning.

The City of Ottawa said in a statement Waller Street collapsed around 1 a.m. just south of Laurier Avenue East.

The cause of the sinkhole that police say is about eight metres wide has not been determined.

Crews from the Rideau Transit Group (RTG) were working on site but no one was injured. Twenty-four hour tunnelling work had just begun on the LRT East Portal site on Wednesday. The last position report on the official LRT site was dated Feb. 9 and said the tunnel crew was “approaching Laurier” as the tunnel made its way north along Waller Street.

Tunnelling operations were suspended for an investigation and engineers were on the scene to assess the ground conditions.

The city said crews were filling the sinkhole with concrete to stabilize it.

The city was to hold a technical briefing about the sinkhole at 1 p.m. Friday. A Friday afternoon media event for the Confederation Line has been cancelled.

Residents at 50 Laurier Ave. were without water as a result of the sinkhole.

Eastbound Laurier Avenue between Queen Elizabeth Drive and Waller Street is closed to traffic.

[email protected]

twitter.com/meghan_hurley










© Copyright (c) The Ottawa Citizen

http://www.ottawacitizen.com/news/Large+sinkhole+closes+Laurier+Avenue/9534673/story.html
     
     
  #816  
Old Posted Feb 22, 2014, 3:56 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
LRT tunnelling likely cause of Waller Street sinkhole: city

By David Reevely and Meghan Hurley, OTTAWA CITIZEN February 21, 2014 9:30 PM


OTTAWA — Tunnelling under Waller Street for the city’s light-rail project is the only explanation anyone has yet for why a sinkhole opened up near the intersection of Waller and Laurier Avenue, deputy city manager Nancy Schepers said Friday afternoon.

A section of road about three metres by three metres collapsed around 1 a.m. just south of Laurier. Waller is closed there for the rail project and isn’t travelled, though the city closed the nearby intersection while the cause of the collapse is investigated.

Leaking pipes, typically water mains, are the most frequent cause of sinkholes, as slow trickles of water wear away at underground soil and then the surface falls in all at once. But the only pipe running through the area is a small sewer and there’s no indication there was anything wrong with it until the collapsing ground broke it, according to the city.

“At this point, we cannot confirm its root cause,” Schepers said of the sinkhole at a news conference 12 hours after the collapse. The tunnelling is the obvious thing to look to, she said.

For now, there’s no reason to expect the sinkhole to spread, she said. “Monitoring equipment has confirmed that the impact is localized and the geotechnical team has not identified any safety concerns at this point.”

The first sign of trouble came at about 10 p.m. Thursday, according to Tim Stewart, the construction director for the city’s rail contractor, Rideau Transit Group. Miners, who’d just started 24-hour-a-day work on the tunnel there the previous day, noticed “material” falling from the top of the face where a massive digging machine called a roadheader was clawing away at the earth under Waller. They stopped digging and watched for a short time, and when the sand and debris kept coming down, they pulled the roadheader back and got out, Stewart said.

Nobody was hurt. Once the sinkhole stopped growing, crews filled it with concrete to stabilize it, work that needed to be done before inspectors could get close enough to start figuring out exactly what happened.

“It’s early for us. We’re continuing to analyze what happened and why it happened,” Stewart said. “We have ensured that our operation is safe.”

The roadheader (“Crocodile Rouge” is the nickname given to this one) is safely away from the collapse, he said.

The east portal for the rail tunnel is being dug in the soft ground of Sandy Hill and it’s been the subject of constant assessments and reassessments as tunnelling has progresses, with engineers determining just how much support the roof of the tunnel needs as the digging goes on. In that spot, the roof of the tunnel had been supported with horizontal pilings and a layer of “shotcrete,” a form of concrete that’s sprayed on with a hose, Stewart said. The tunnelling is 15 to 20 metres from hitting the hard bedrock that’s under most of downtown Ottawa, where the digging is expected to get simpler.

Tunnelling at the west portal near Bronson Avenue and at a central shaft near Queen and Lyon streets is already in bedrock and is continuing, Schepers said. The mess at the east portal is Rideau Transit Group’s problem for now, she said, because unless it turns out the city was somehow at fault, the contract with the construction consortium makes risks associated with the tunnelling part of the $2.1-billion deal.

“RTG is fully engaged in first containing and mitigating the impact, secondly in identifying the cause, and finally in putting forward a plan to resume tunnelling operations in the area when it’s safe to do so,” Schepers said.

[email protected]
twitter.com/davidreevely



© Copyright (c) The Ottawa Citizen
     
     
  #817  
Old Posted Feb 22, 2014, 6:24 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,672
Sinkhole filled, traffic may return to normal Monday

By Tom Spears, OTTAWA CITIZEN February 22, 2014 1:12 PM




OTTAWA — Workers have filled in the downtown sinkhole that was likely caused by LRT tunnelling, and the area’s city councillor says traffic may roll on all lanes of Laurier Avenue East by Monday.

But there’s still work to be done, Mathieu Fleury cautioned:

• Engineers have to inspect the filling to make sure it’s stable;
• Traffic signals aren’t hooked up yet;
• An apartment building at 50 Laurier Ave. East still doesn’t have complete sewer connections, though service has been on and off.

Still, the work went fast.

A section of road about three metres by three metres collapsed about 1 a.m. Friday just south of Laurier. Waller Street is closed there for the rail project and isn’t travelled, though the city closed the intersection while the cause of the collapse is investigated.

There has been no sinkhole under Laurier itself.

Fleury notes that LRT construction “is the biggest contract the city has ever awarded.”

The sinkhole that opened under Waller Street delayed underground tunnelling that is supposed to be going 24 hours a day, so Rideau Transit Group was motivated in repairing the damage as soon as possible, he said.

When all that is done, it will take a “final coat” of asphalt on the road, Fleury said.

Asked when the nearby intersection with Laurier Avenue would reopen, he said Monday looks like a safe prediction, and he hopes it could even reopen before that.

Unlike the sinkhole on Highway 174 in September 2012, this one does not appear to be caused by underground water eroding soil. City officials say LRT tunnelling probably caused the Waller collapse. The area is built on loose, sandy soil.

[email protected]

twitter.com/TomSpears1
© Copyright (c) The Ottawa Citizen

http://www.ottawacitizen.com/news/Sinkhole+filled+traffic+return+normal+Monday/9539722/story.html
     
     
  #818  
Old Posted Feb 22, 2014, 7:34 PM
Nouvellecosse's Avatar
Nouvellecosse Nouvellecosse is offline
Volatile Pacivist
 
Join Date: Aug 2005
Location: Nova Scotia
Posts: 11,351
Why are they using that type of machine instead of a conventional circular TBM?
__________________
"The reasonable man adapts himself to the world; the unreasonable one persists in trying to adapt the world to himself. Therefore all progress depends on the unreasonable man." - George Bernard Shaw
Don't ask people not to debate a topic. Just stop making debatable assertions. Problem solved.
     
     
  #819  
Old Posted Feb 22, 2014, 7:41 PM
eemy's Avatar
eemy eemy is offline
Closed account
 
Join Date: Aug 2006
Posts: 4,425
It's my understanding that this method is cheaper. Although it is slower, the tunnel construction isn't the limiting factor for the overall project. I'm also under the impression that this method allows the mining out of the stations from underground, limiting surface interruptions, though I'm not sure why that wouldn't be possible with TBMs as well.
     
     
  #820  
Old Posted Feb 22, 2014, 10:39 PM
Nouvellecosse's Avatar
Nouvellecosse Nouvellecosse is offline
Volatile Pacivist
 
Join Date: Aug 2005
Location: Nova Scotia
Posts: 11,351
Makes me wonder if this method is more prone to collapse. It seems logical that it would be since a TBM supports the tunnel while it excavates and set the precast wall shells in place directly behind it.
__________________
"The reasonable man adapts himself to the world; the unreasonable one persists in trying to adapt the world to himself. Therefore all progress depends on the unreasonable man." - George Bernard Shaw
Don't ask people not to debate a topic. Just stop making debatable assertions. Problem solved.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 9:11 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.