Quote:
Originally Posted by nname
I think most of the "promises" now are made by the province (ie. Evergreen Line, Port Mann Rapid Bus) and the city (ie. Surrey LRT). Nowadays, all TransLink's promise are attached with "if funding available, then we'll do this..."
|
Good point.
Quote:
I agree with GEB but not Canada Line... The original weekday ridership estimate from TransLink back in 2006 were:
2010: 117,600
2014: 126,100
2021: 143,100
And then people, including many in this forums, yelled that the projection is overly optimistic, but in fact it is quite close to the actual number. The actual for a normal 2010 weekday, if I remember correctly, was around 114,000.
|
This is where I'm a little confused because we don't really ever find statistics about the 'normal weekday.' The only stats I've ever been able to find are from their quartlery and year end financial reports which simply say how many boardings total. So it averages out weekends too.
2010: 38,447,725 (105336 per day)
2011: 39,668,773 (108681 per day)
2012: 40,832,738 (111870 per day)
Now if we look at:
http://www.translink.ca/en/About-Us/Medi...-ridership-heading-for-a-new-record.aspx
It states Canada Line average weekday bordings as of June 2011 was 136,259.
So doing some math:
1. 136259 x 260 (work days) = 35,427,340
2. 35,427,340 / 39,668,773 = 89.3% of total ridership is weekday
3. 40,832,738 * 89.3% = 36,466,852
4. 36,466,852 / 260 (work days) = 140,257 per average work day
So based on those numbers above from Translink both times, and doing a bit of math, in 2012 the average week day passenger count is very nearly the projected number for 2021.
Side by side:
Projected based on the 2006 numbers
2010: 117,600
2011: 119,725
2012: 121,850
2013: 123,975
2014: 126,100
Actual as of 2013:
2010: 132,053
2011: 136,259
2012: 140,257
2013: 144,355 (projected as of November 2013)
So I don't know about you but that tells me we're 9 years too early and already starting to push towards 2025 numbers...
Then ok I tip my hat to the previous poster about worries about a crush of riders. If they though the 96-B line with a lot of promotion would have been absolutely jam packed, I think in reality next year we should be seeing the 96-B buses during the week looking like something out of India with people riding the roof.
Sarcasm aside, I think the above illustrated my point that Translink and projected numbers don't really seem to mix. They're not very good at predicting the future which is probably why many of us are complaining they don't plan for the future. I tip my hat again to the fact they have realized they are crap at predicting the future so they just don't plan ahead...
</sarcam again>