GO station on track despite bridge delay
The Hamilton Spectator
By: Matthew Van Dongen
CN says an unexpected six-month delay in replacing the Bay Street bridge won't derail planned construction on the new Hamilton GO station nearby.
Local residents and businesses are stuck with a road closure that will continue until next June, however — a full year after work began to replace the bridge over the CN railway.
Metrolinx is planning to open a new, two-storey GO station by 2015 just east of the McNab Street bridge, with a platform that extends under Bay Street.
Metrolinx spokesperson Vanessa Thomas said "constant co-ordination" with CN is required because the new bridge and its abutments must accommodate the platform and a proposed pedestrian access from Bay Street.
But so far, Thomas said Metrolinx believes station completion is still on target for the summer of 2015.
CN has hand-delivered letters to area residents apologizing for the delay, which it attributed to a decision to put off pouring concrete for the bridge deck until warmer weather returns, avoiding a potential freeze during the curing process.
Spokesperson Lindsay Fedchyshyn said excavation for the new south bridge abutment took longer than expected, leading to the cold-weather time crunch.
A CN letter to the city in late October noted "co-ordination" between the new GO station design and abutment construction "is currently in resolution."
But the letter also says the delay won't prevent Metrolinx from starting its station construction later this year.
That's no consolation for the owner of Hutch's Harbour Front restaurant, which sits on the north side of the demolished bridge at the entrance of Bayfront Park.
Construction started last June — the start of the of parkside restaurant's busy season, said owner Rod Styles. "We'd like to see it done as soon as possible," he said. "The road will have been closed for a full year by the time they're done … That doesn't help us."
The bridge delay will also force a reroute of the Around the Bay Road Race, which was supposed to head north on Bay Street from the Copps Coliseum starting point.
Runners will likely jog east and cross the railway tracks on the McNab bridge, said race director Mike Zajczenko. "It should be a small detour only; nothing I'm worried about," he said.
http://www.thespec.com/news-story/4201315-go-station-on-track-despite-bridge-delay/