City of Ottawa
November 1, 2013
- Construction of the iconic wood surround – called the Veil - at the south side stands has started.
- Each of the 24 large wooden ribs are being carefully positioned and fastened. Construction of the entire Veil will take several months.
- Drywall and other fixtures continue to be installed on the three levels of the building.
- Seat installation and work on the roof at the north stands continues.
- Work on the new lower concourse concession has started.
- New floors at the upper concourse are being poured.
From Bank Street, the shape of the renovated stadium can be seen. The last portion of the parking garage, in the foreground, is being finished, while seats continue to be installed in the north stands in the background
At the west end of the south stands, work continues on the new stair case
The curving shape of the new south stands can be seen as the precast bleachers at the third level are installed
Some of the first vertical pieces of the wooden surround at the south stands, called the Veil, have been put up