City of Ottawa
October 18, 2013
- Work this week at the south side stands focused on installing the precast concrete risers that the seats will be mounted on at the second and third level.
- Inside the south stands, the offices, locker rooms and other spaces at the lower levels are being finished.
- Construction of the Veil, the iconic wooden surround, is expected to begin as early as next week.
- At the north stands, seat installation continues as the red and grey seats continue to go in.
- Inside the arena, repairs to the roof have started.
The south stands are coming together as the precast concrete bleachers the seats will be attached to go in and the new stair well is built
At the back of the new stands, new walls are filled in and exterior sheathing is installed
Seats in the north stands continue to be installed, while work on the new roof is on going
At the top level of the south stands, the new precast concrete bleachers are installed
Lots of activity continues across the stadium as underground conduit for audio-visual cables is run, the parking garage at the west end of the field is finished and work on the stands continues